KC 46A Two Bay General Purpose MX Hangar Federal contract opportunity
Solicitation number
W912DS-19-R-0001
Issued by
Department of the Army Corps of Engineers Engineering District New York

View the file

Other files for this federal contract opportunity

Other files attached to KC 46A Two Bay General Purpose MX Hangar, newest first.
File Type Posted
Amendment_0009.pdf PDF
hangar_site_visit_sign_in_12.27.18.pdf PDF
Amendment_0007.pdf PDF
Amendment_0008_Plan.pdf PDF
Amendment_0008_Spec.pdf PDF
Amedment_0006.pdf PDF
Amendment_0006_-_2-Bay_MX_Hangar_Plans.docx.pdf PDF
Appendix_Q_-_KC46_2-Bay_Hangar_Soil_Erosion_Plans.pdf PDF
Amendment_0006_-_2-Bay_MX_Hangar_Specs.pdf PDF
Amendment_0005.pdf PDF
Amendment_0004.pdf PDF
Appendix_P_-_Site_Visit_14_NOV_2_Bay_Hanger.pdf PDF
Amendment_0003_-KC46_2-Bay_Hangar_-_Specs.pdf PDF
Amendment_0003.pdf PDF
Amendment_0003_-KC46_2-Bay_Hangar_-_Plans.pdf PDF
W912DS19R0001-0002.pdf PDF
Amendment_0001.pdf PDF
Appendix_G_-_KC46_2-Bay_Hangar_CADD_Files_(Aval_After_Award).pdf PDF
Appendix_B_-_As-Built_Drawings_For_Buildings_1801_and_1823.pdf PDF
Package_2_-_KC46_-_2-Bay_Hangar_-_Specifications.pdf PDF
Package_4_-_KC46_-_2-Bay_Hangar_-_FFE.pdf PDF
Pages_from_Package_1_-_KC46_-_2-Bay_Hangar_-_Plans_2.pdf PDF
Pages_from_Package_1_-_KC46_-_2-Bay_Hangar_-_Plans-1.pdf PDF
Package_3_-_KC46_-_2-Bay_Hangar_-_CID.pdf PDF
Appendix_D_-_Hydrant_Flow_Test.pdf PDF
Appendix_L_-__McGuire_Environmental_Survey_of_B1801_and_B1823_(September_1999).pdf PDF
Appendix_O_-_Hangar_Acceptance_Test_Procedures_AFCEC.pdf PDF
Appendix_F_-_USACE_Joint_Base_MDL_HazMat_Assessment_Report_5-8-18_(KM).pdf PDF
Appendix_I_-_SOO-KC-46A_Beddown.pdf PDF
Appendix_C_-_Sustainability_Checklists_and_References.pdf PDF
Appendix_J_-_ATFP_Flightline_Securitypdf.pdf PDF
Appendix_B_-_As-Built_Drawings_For_Buildings_1801_and_1823.pdf PDF
Appendix_K_-_KC46_-_Apron_and_Fuel_Hydrant_Relocation.pdf PDF
Appendix_A_-SOW_Attachment_2_-_AMRS_Meter_Specifications_dated_28_January_2016.pdf PDF
Appendix_H_-_JB_MDL_-_Pavement_Evaluation_Report_North_of_1837.pdf PDF
W912DS19R0001.pdf PDF
Appendix_N_-_KC-46A_MOB_4_Public_FEIS_ExecSumm_June_2018.pdf PDF
Appendix_M_-_Soil_Contamination_Maps.pdf PDF
Appendix_E_-_McGuire_KC-46A_Two-Bay_MX_Hangar_Geotech_Report.pdf PDF
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W16ROE82576289

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Provide updates to f inal RFIs

2) Provide revised and reissued draw ings

3) Provide revised and reissued specif ications section

NOTE: Offerors must acknow ledge receipt of this amendment by the date specif ied or as amended in the bid by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, OR WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 03-Jan-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS19R0001

X 9B. DATED (SEE ITEM 11)

02-Nov-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

03-Jan-2019

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS19R0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been added by full text:

UPDATED CHANGES 2

KC46 – ADAL B2319 for Boom Operator Trainer Joint Base McGuire-Dix-Lakehurst, NJ

W912DS-19-R-0001

Amendment 0008

AMENDMENT 0008 to DRAWINGS and SPECIFICATIONS for KC46 Two Bay Maintenance Hangar, Joint Base McGuire-Dix-Lakehurst, New Jersey

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- None

2. The following DRAWINGS have been REVISED and REISSUED:

- Drawing ES602

3. The following DRAWINGS have been ADDED:

- None

4. The following DRAWINGS have been DELETED:

- None

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- None

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- None

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- Section 10 14 00.20 – Specialties

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

- None

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

1. Paragraph 2.3 gives requirements for building directories which are not included in the signage schedule. Please confirm that building directories are not required. Response: The building directories are not included in the project. The spec section has been revised and reissued to clarify that this is not a requirement.

2. In regards to the resinous flooring, the specifications and the finish schedule do not match. Please clarify. Response: The intent is for the Contractor to meet the requirements of the specification for bidding. Since the product selected for color does not meet the spec, we would like to direct the Contractor to meet the spec requirements and select a similar color.

W912DS19R0001

3. 1) What is the cable length of the 350mcm from SW1828 to SW-2 Bay 1?

2) What is the cable length of the 350mcm from SW-2 Bay 1 to SW1837?

3) What is the cable length of the 4/0awg from MH1835A to MH1835B?

4) What is the cable length of the 4/0awg from MH1835B to SW-2 Bay 2?

5) Drawing ES602 shows 350mcm from SW-2 Bay 1 to 1000kVA transformer. The notes say to use 4/0awg.

6) Drawing ES602 shows 350mcm from SW-2 Bay 2 to 1000kVA transformer. Is that to be a 4/0awg?

Response:

1) Length is approximately 450 feet based on base map

2) Length is approximately 960 feet based on base map 3&4) Only 4/0 from 1835B to SW-2 to be replaced as shown on ES602. Length is 370 feet approx.

based on base map 5&6) Drawing ES602 has been revised and reissued to show 4/0 in lieu of 350 from SW to XFMR.

(End of Summary of Changes)