Bartlett_Brook_Specs_100_Kim_01_57_20.00_10_Edit_.pdf

PDF 6 MB Posted

Attached to
Elberon to Loch Arbor Reach, Contract 2 Deal to Elberon, New Jersey
Solicitation number
W912DS-15-B-0012
Issued by

About this file

Specs

View the file

Other files

File Type Posted
BBN_Laurel_Hill_Plans_Post-100__20150710_Bid_doc.pdf PDF
W912DS-14-B-0014.pdf PDF
BBN_Stonehedge_Plans_Post-100__20150710_Bid_doc.pdf PDF
Bid_Abstract.pdf PDF
W912DS-15-B-0012-0009.pdf PDF
W912DS-15-B-0012-0008.pdf PDF
W912DS-15-B-0012-0007.pdf PDF
02_32_00.pdf PDF
Amendment_0006.pdf PDF
31_62_19.13_Wood_Marine_Piles-Final.pdf PDF
Main_Table_of_Contents.pdf PDF
Submittal_Register.pdf PDF
W912DS-15-B-0012-0005.pdf PDF
W912DS-15-B-0012-0004.pdf PDF
W912DS-15-B-0012-0003.pdf PDF
C-106.pdf PDF
C-107.pdf PDF
DTM_07-2014_ELBERON_TO_LOCH_ARBOUR_NAVD88.xyz XYZ file
W912DS-15-B-0012-0002.pdf PDF
90-PDFSW912DS-15B-0012-0015-C-309.pdf PDF
G-102.pdf PDF
W912DS-15B-0012-0015-C-104.pdf PDF
amend2_G-001.pdf PDF
W912DS-15-B-0012-0001.pdf PDF
Pages_11-20_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
Pages_21-40_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
04_00_90_05_Geotechnical_ReportL_AppendixVolume_144DPI.pdf PDF
01_00_90_05_Geotechnical_Report_DEAL_MainReport.pdf PDF
02_00_90_05_Geotechnical_Report_DEAL_QuadrantsReport_1and2.pdf PDF
W912DS-15-B-0012.pdf PDF
03_00_90_05_Geotechnical_Report_QuadrantsReport_3and4.pdf PDF
Pages_1-10_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
W912DS-15-B-0012_Deal_Final_Specs_-CT_2-june_25_red.pdf PDF
Pages_41-51_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DuBois & King Inc.

NEW YORK DISTRICT Randolph, VT

USACE Bartlett Brook

Bartlett Brook North Stormwater Treatment Improvements

Stonehedge and Laurel Hill

City of South Burlington, Vermont

IFB No. W912DS-15-B-0014

Specifications

100% July 2015

COVER SHEET

NEW YORK DISTRICT

CORPS OF ENGINEERS

NEW YORK, NEW YORK 10278-0090

INVITATION FOR BIDS

FOR

USACE Bartlett Brook Bartlett Brook North Stormwater Treatment Improvements

Stonehedge and Laurel Hill City of South Burlington, Vermont

1. Attached is INVITATION FOR BIDS (IFB) No. W912DS-15-B-0014

2. BIDS MUST BE SET FORTH full, accurate, and complete information as required by this Invitation for Bids, including attachments. The penalty for making false statements in bids is prescribed under Title 18, United States Code, Section 1001.

3. SUBMISSION OF BIDS: Complete details concerning proper submission of bids are contained in the INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS (Section 00100).

4. Note the REQUIREMENT FOR AFFIRMATIVE ACTION of the EQUAL OPPORTUNITY clause as it applies to the contract resulting from this solicitation.

(See paragraph NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY in Section 00100 of this IFB).

5. REPRESENTATIONS AND CERTIFICATIONS – SECTION 00600

Bidders and Offerors are required to complete the REPRESENTATIONS AND CERTIFICATIONS and submit them with their bids.

Within Section 00600, note in particular the PROHIBITION SEGREGATED FACILITIES. Failure of a bidder or offeror to agree to the certification will render His bid or offer non-responsible to the terms of solicitations involving awards of Contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity Clause.

6. THIS PROJECT IS A CIVIL WORKS PROGRAM PROCUREMENT AND IS NOT

FUNDED BY THE DEPARTMENT OF DEFENSE.

7. Please review all bonds and accompanying documents required to be submitted.

Bonds, Powers of Attorney, statements of authenticity and continuing validity, and all related documents MUST NOT bear computer printer-generated signatures and/or seals. Documents bearing signatures and/or seals generated as part of a document, as

COVER SHEET

opposed to being affixed to the document after its generation, will not be accepted.

Submission of such documents may render the bid or offer non-responsive and ineligible for award.

CHECKLIST - 1

US ARMY ENGINEER DISTRICT, NEW YORK

INVITATION FOR BIDS NO. W912DS-15-B-0014

CHECK LIST FOR BIDDERS

ATTACHED IS IFB NO W912DS-15 -B-0014

USACE Bartlett Brook Bartlett Brook North Stormwater Treatment Improvements Stonehedge and Laurel Hill City of South Burlington, Vermont

ALL INFORMATION REQUIRED BY THE TERMS OF THIS SOLICITATION

MUST BE FURNISHED. MISTAKES OR OMISSIONS MAY RENDER YOUR

OFFER INELIGIBLE FOR AWARD. IMPORTANT ITEMS FOR YOU TO CHECK

ARE INCLUDED IN BUT NOT LIMITED TO THOSE LISTED BELOW. THIS

INFORMATION IS FURNISHED ONLY TO ASSIST YOU IN SUBMITTING A

PROPER BID

__HAVE YOU ACKNOWLEDGED ALL AMENDMENTS?

__HAVE YOU COMPLETED THE “REPRESENTATIONS AND CERTIFICATIONS”

(SECTION 00600) PORTION OF THE SOLICITATION?

__IS YOUR DUNS NUMBER LISTED ON THE STANDARD FORM 1442?

__IS YOUR BID PROPERLY SIGNED?

__IS YOUR BID GUARANTEE PROPERLY SIGNED BY BOTH THE BIDDER AND

SURETY AND ARE ALL SEALS AFFIXED?

__DO THE BID BOND AND ACCOMPANYING DOCUMENTS BEAR

SIGNATURES AND SEALS AFFIXED AFTER THE DOCUMENT WAS

GENERATED, AS OPPOSED TO COMPUTER PRINTER-GENERATED

SIGNATURES AND/OR SEALS?

__HAVE YOU ENSURED THAT YOU HAVE NOT RESTRICTED YOUR OFFER

BY ALTERING THE PROVISIONS OF THE SOLICITATION?

__WHEN REQUIRED, HAVE YOU ENTERED A UNIT PRICE FOR EACH PRICE

ITEM? (THE SOLICITATION SPECIFICALLY STATES WHEN THIS IS

NECESSARY.)

__ARE DECIMALS IN YOUR PRICES IN THE PROPER PLACE? ARE YOUR

CHECKLIST - 2

FIGURES LEGIBLE?

__IF YOU HAVE MADE ERASURES OR CORRECTIONS ON YOUR BID, ARE

THEY INITIALED BY THE PERSON SIGNING THE BID?

__DOES THE ENVELOPE CONTAINING YOUR BID PROPERLY IDENTIFY

THAT IT ISA SEALED BID AND DOES IT CONTAIN THE CORRECT

SOLICITATION NUMBER AND BID OPENING TIME?

__WILL YOUR OFFER ARRIVE ON TIME? (SEE PARAGRAPH ENTITLED “LATE

SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS” IN THE

INSTRUCTIONS, CONDITIONS, AND NOTICES TO BIDDERS, SECTION 00100

OF THE SOLICITATION.)

NOTE: THERE ARE INCREASED SECURITY MEASURES AT JACOB K.

JAVITS FEDERAL BUILDING, 26 FEDERAL PLAZA THAT MAY AFFECT THE

TIME IT TAKES TO ENTER THE BUILDING. BIDDERS IS RESPONSIBLE TO

ENSURE THAT ITS BID IS SUBMITTED TIMELY.

Bartlett Brook Tributary 3 Stormwater Treatment Section 542 Project, South Burlington, VT

MTOC - 1

MAIN TABLE OF CONTENTS

SECTION TITLE

00 10 00 SF 1442 AND BIDDING SCHEDULE

00 21 13 INSTRUCTIONS, CONDITIONS, AND NOTICE TO BIDDERS

(to be provided by Contracting Division)

00 45 00 REPRESENTATIONS AND CERTIFICATIONS

(to be provided by Contracting Division)

00 71 00 CONTRACTING DEFINITIONS

(to be provided by Contracting Division)

00 73 00 SUPPLEMENTARY CONDITIONS

LIST OF DOCUMENTS, EXHIBITS & OTHER ATTACHMENTS

00 90 00 WAGE RATES

00 90 01 PERMITS

00 90 02 GEOTECHNICAL REPORT

TECHNICAL PROVISIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 12 00.00 18 DESIGN AND RECORD DRAWING REQUIREMENTS

01 22 00.00 10 MEASUREMENT AND PAYMENT - LAUREL HILL

01 22 01.00 10 MEASUREMENT AND PAYMENT - STONEHEDGE

01 32 01.00 18 PROJECT SCHEDULE

01 33 00.00 18 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 02.00 18 QUALITY CONTROL SYSTEM (QCS)

01 45 04.00 18 CONTRACTOR QUALITY CONTROL

01 57 20.00 18 ENVIRONMENTAL PROTECTION

01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT

01 78 00.00 18 CLOSEOUT SUBMITTALS

DIVISION 03 - CONCRETE

Bartlett Brook Tributary 3 Stormwater Treatment Section 542 Project, South Burlington, VT

MTOC - 2

03 40 00.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION - LAUREL HILL

03 40 01.00 10 PLANT-PRECAST CONCRETE PRODUCTS FOR BELOW GRADE

CONSTRUCTION - STONEHEDGE

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK - LAUREL HILL

31 00 01 EARTHWORK - STONEHEDGE

31 11 00 CLEARING AND GRUBBING - LAUREL HILL

31 11 01 CLEARING AND GRUBBING - STONEHEDGE

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 92 19 SEEDING - LAUREL HILL

32 92 20 SEEDING - STONEHEDGE

32 93 00 EXTERIOR PLANTS - LAUREL HILL

32 93 01 EXTERIOR PLANTS - STONEHEDGE

DIVISION 33 - UTILITIES

33 40 00 STORM DRAINAGE UTILITIES - LAUREL HILL

33 40 01 STORM DRAINAGE UTILITIES - STONEHEDGE

The graphic format for this 4' x 6' sign panel follows the legend guidelines and layout as specified below. The large 4' x 4' section of the panel in the right is to be white with black legend. The 2' x 4' section of the sign on the left with the full corps Signature (reverse version) is to be screen printed Communications Red on the white background. The castle insignia will be furnished by the Government in pressure sensitive vinyl for affixing by the Contractor.

See attached sheet for fabrication and mounting guidelines.

SAMPLE:

2"

(Dimensions are in inches)

48"

Post Specification Code

Color various 4' x 6' Height Bkg/Lgd Mounting

4' x 4' HDO-3 Type

Legend

* Appendix D

Color: Black

(architect, general contractor, etc.), Size Size

3" 21" 1"

7.75"

* Refers to the U.S. Army Corps of Engineers, "Sign Standards Manual", EPS-310-1-6.

CID-01 WH-RD/BK

21" 3" 42" 3"

4.5"

6"

STORMWATER TREATMENT IMPROVEMENTS

9.5"

2.25"

6"

4.5"

2"

1.875"

1.875"

1.875"

1.875"

USACE BARTLETT BROOK

21"

STONEHEDGE AND LAUREL HILL

Typeface: 1.5" Helvetica Regular Maximum line length: 42" identification of project or facility (civil works) or name of sponsoring

US Army Corps

Sign

New York District

10.5" of Engineers

Panel corporate or firm name, city, state.

Use of Legend Group 5 is optional.

contractors including: type line identification of prime

Letter and word spacing to follow

Group 4 with the first line of the Corps Signature (US Army Corps) as shown.

Legend Group 5a-b: One-to-five

Corps standards as specified in

Typeface: 1.25" Helvetica Regular Maximum line length: 21"

All typography is flush left and rag right upper and lower case with initial capitals only as shown.

department (military).

Color: Black

Cross-align the first of Legend describes the work being done under this contract.

Color: Black Typeface: 3" Helvetica Bold Maximum line length: 42"

Legend Group 4: One-to two-line

3"

Castle)

Color: White

District Name (optional). Place below 10.5" Reverse Signature (6"

Typeface: 1.25" Helvetica Regular Maximum line length: 19"

Legend Group 2: Division or

2.5"

PROJECT IDENTIFICATION SIGN

CIVIL WORKS PROJECT

4.5"

6.25"

Supervised by Design and Construction description of Corps relationship to project

Legend Group 1: One- to two-line three-line project title legend

Color: White Typeface: 1.25" Helvetica Regular

Legend Group 3: One- to

CITY OF SOUTH BURLINGTON, VT

The graphic format, color, size and type-faces used on the sign are to be reproduced exactly as specified below. The title with First Aid logo in the top section of the sign, and the performance record captions are standard for all signs of this type. Legend Group 2 and 3 below identify the project and the contractor and are to be placed on the sign as shown.

Safety record numbers are mounted on individual metal plates and are screw-mounted to the background to allow for daily revisions to posted safety performance record.

Legend Group1: Standard two-line title "safety is a Job Requirement", with (8" od.) Safety Green First Aid logo. Color: To match PMS 347 Typeface: 3" Helvetica Bold Color: Black

Legend Group 2: One- to two-line project title legend describes the work being done under this contract and name of host project.

Color: Black 2.25" Typeface: 1.5" Helvetica Regular Maximum line length: 42"

2.25" Legend Group 3: One - to two-line identification: name of prime This project has Days without & contractor and city, state address. 1.875" operated: lost time injury 4.875" Color: Black Typeface: 1.5" Helvetica Regular Total days worked Maximum line length: 42" 1.875" on this contract 4.875"

Legend Group 4: Standard safety Lost time record captions as shown. 1.875" injuries 4.875" Color: Black

Typeface: 1.25" Helvetica Regular

Replaceable numbers are to be mounted on white .060: aluminum plates and screw-mounted to background.

Color: Black Typeface: 3" Helvetica Regular Plate size: 2.5"x.5"

All typography is flush left and rag right, upper and lower case with initial capitals only as shown.

Letter- and word-spacing to follow Corps standards as specified in Appendix D. *

* Refer to the U.S. Army Corps of Engineers, "Sign Standards Manual", EPS-310-1-6.

Sign Legend Post Specifications Mounting Color Type Size Size Code Height Bkg/Lgd CID-02 various HDO-3 48" WH/BK-GR

SAFETY PERFORMANCE SIGN

Safety is a Job Requirement

3" 3"8"

4.5"

3"

4"

3"

USACE BARTLETT BROOK

STORMWATER TREATMENT

IMPROVEMENTS

10.5"

3" 31"

Dimensions inches.

3" 2"

STONEHEDGE AND LAUREL HILL

17"

6"

3.875"

4"x4" 4"x4"

2.5" 2.5"

See attached sheet for fabrication and mounting guidelines.

Panel Size

CITY OF SOUTH BURLINGTON, VT

.875"

3.125"

.975"

2.5"

3"

PROHIBITED ACTIVITIES

DISTRICT ENGINEER: COLONEL "name"

COMPLETION DATE:

FOR YOUR SAFETY

1. DO NOT ENTER DESIGNATED WORK AREAS

2. OBEY ALL STATE AND LOCAL REQUIREMENTS CONCERNING

US ARMY

CORPS OF ENGINEERS, NEW YORK DISTRICT

USACE BARTLETT BROOK

STORMWATER TREATMENT IMPROVEMENTS

CONTRACTOR:

FUNDED BY:

STONEHEDGE AND LAUREL HILL, CITY OF SOUTH BURLINGTON, VT

As Construction Project Identification signs Detailed specifications for and Safety Performance signs are to be HDD plywood panel preparation are pro-fabricated and installed as described vided in Appendix B.** below. The signs are to be erected at a Shown below the mounting diagram is location designated by the contracting of- a panel layout grid with spaces provided ficer and shall conform to the size, format, for project information. Photocopy this and typographic standards shown on page and use as a worksheet when pre-the attached sheets. paring sign legend orders.

The sign panels are to be fabri-cated from .75" High Density Over-lay Plywood. Panel preparation to follow HDD specifications provided in Appendix B. **

Sign graphics to be prepared on a white non-reflective vinyl film with positionable adhesive backing.

All graphics except for the Com-munications Red background with Corps signature on the project sign are to be die-cut or computer-cut non-reflective vinyl, pre-spaced legends prepared in the sizes and typefaces specified and applied to the background panel following the graphic formats shown on the attached sheets.

The 2'x4' Communications Red panel (to match PMS-032) with full Corps signature (reverse ver-sion) is to be screen printed on the white background. Identifica-tion of the District or Division may be applied under the signature with white cut vinyl letters pre-pared to Corps standards. Large Construction Project Sign scale reproduction artwork for the Legend Group 1: Corps Relationship signature is provided on page 4.8

Drill and Insert six (6) .375" T-nuts from the front face of the HDD Legend Group 2: Division/District Name

Apply graphic panel to prepared Legend Group 3: Project Title HDD plywood panel following better. Post to be 12" long. Drill six (6) .375" mounting holes in Legend Group 4: Facility Name uprights to align with T-nuts in sign

Assemble sign panel and uprights. Legend Group 5a: Contractor/A&E Legend Group 5b: Contractor /A&E Imbed assembled sign panel and

Safety Performance Sign Legend Group 1: Project Title

Legend Group 2: Contractor/A&E

Fabrication and Mounting Guidelines

48"

48"

(Dimensions in inches)

** Refers to the U.S. Army Corps of Enginee "Sign Standards Manual", EP-310-1-6.

2.

sign panel. Position holes as 1.

shown. Flange of T-nut to be flush

18"

(photographically enlarge from 1.

6.875" to 10.5"). **

2.Sign uprights to be structural grade 4"x4" treated Douglas Fir

3.or Southern Yellow Pine. No.1 or with sign face. 2.

manufacturers' instructions. 1.

uprights in 4" hole. Local soil con- 1. 1.

ditions and/or wind loading may panel. Countersink (.5") back of 1.

hole to accept socket head cap screw (4"x.375"). 2.

reinforce installation as shown. 3. 3.

4. 4.

require bolting additional 2"x4" 2. 2.

struts on inside face of uprights to

1.

2.

5. 5.

1.

2.

00 90 00

Section 00 90 00

Wage Rates

Section 00 90 01

Permits

Vermont Department of Environmental Conservation Agency of Natural Resources Watershed Management Division Main Building, Second Floor [phone] 802-828-1535 One National Life Drive Montpelier, VT 05620-3522

To preserve, enhance, restore, and conserve Vermont's natural resources, and protect human health, for the benefit of this and future generations.

The Notice of Intent for the discharge of stormwater runoff from Low Risk Construction Activity under Construction General Permit (CGP) 3-9020 (Amended 2008) has been authorized. Enclosed are four documents that you will need to maintain compliance with this authorization.

1. Authorized Notice of Intent (NOI) The authorized NOI for Low Risk Projects is valid for two years from the date of the authorization. If the project will proceed past the automatic termination date, you must reapply for coverage under this or another construction stormwater permit before that time.

2. Notice of Authorization for Posting The notice of Authorization, which details the authorization and conditions you selected in completion of Appendix A to the CGP, must be posted in a location visible to the public in accordance with Subpart 4.5.C of the CGP. In accordance with subpart 5.1 of the CGP, the project risk score must be re-evaluated prior to any major changes to the construction plan.

3. Low Risk Site Handbook for Erosion Prevention and Sediment Control Please provide the Principal Operator with the low risk site handbook. This handbook details the practices that must be implemented throughout the construction project to prevent erosion and the discharge of sediment from the construction site. Some practices must be in place before construction begins, so please review the entire handbook before starting the project.

4. Notice of Addition of Co-Permittee This form must be submitted for every new landowner or principal operator who joins the project, in accordance with Subpart 7.2 of the CGP.

The CGP, copies of pertinent forms, and an electronic version of the Low Risk Site Handbook for Erosion Prevention and Sediment Control are available on the stormwater website at:

http://www.vtwaterquality.org/stormwater/htm/sw_cgp.htm. If you have any questions related to your authorization, please contact the appropriate analyst in the Stormwater District where your project is located. Use our District Look-up Tool for details.

Sincerely, Stormwater Management Program

Cc: Co-Permittee/Application Preparer/Designer (if applicable) http://www.vtwaterquality.org/stormwater/htm/sw_cgp.htm http://www.anr.state.vt.us/dec/waterq/stormwater/htm/sw_districtcontacts_newcm.htm http://www.anr.state.vt.us/dec/waterq/stormwater/htm/sw_districtcontacts_newcm.htm

Notice of Authorization Under Vermont Construction General Permit 3-9020

For Low Risk Projects

Project Name: Stonehedge Stormwater

Improvements

Permittee Name: Stonehedge North Area

Association and Stonehedge South Area

Association

Notice of Intent Number: 7220-9020

Date of Authorization: July 7, 2014

Date of Expiration: July 7, 2016

The project listed above has received authorization under General Permit 3-9020 to discharge stormwater from the following construction activities: Five catch basins, new 18" HDPE storm drains totaling approx. 581', a new 43' long 2' by 3' concrete box culvert, new stoned lined ditch, a new stone headwall, new storm drain, 3 new bioretention areas, stormwater treatment and detention pond, pond outlet and control structure.

This authorization includes the following requirements:

1. Implementation of erosion prevention and sediment control practices required by the Low Risk

Site Handbook for Erosion Prevention and Sediment Control.

2. All areas of disturbance must have temporary or final stabilization within 7 days of the initial disturbance. After this time, all disturbed soil must be stabilized at the end of each work day.

Between October 15 and April 15 all disturbed soil must be stabilized at the end of each work day. The following exceptions apply:

a. Stabilization is not required if work is to continue in the area within the next 24 hours and there is no precipitation forecast for the next 24 hours.

b. Stabilization is not required if the work is occurring in a self-contained excavation (i.e.

no outlet) with a depth of 2 feet or greater (e.g. house foundation excavation, utility trenches).

3. No more than 2 acres of land may be disturbed at any one time.

4. Inspections shall be conducted at least once every (7) calendar days and within twenty-four (24) hours of the end of a storm event resulting in discharge of Stormwater from construction site.

5. If there is a discharge of visibly discolored stormwater from the construction site or from the construction site to waters of the State, the permittee shall take immediate corrective action.

6. If, after completing corrective action, there continues to be a discharge of sediment from the construction site to waters of the State, the permittee shall notify DEC by submitting a report within 72 hours of the discharge.

To request information on this authorization, or to report compliance concerns, please contact:

Vermont DEC, Watershed Management Division Main Building, Second Floor

One National Life Drive Montpelier, VT 05620-3522

(802) 828-1535 [See next page for posting requirements]

Notice of Addition

Of Owners or Operators To Coverage Under Vermont Construction General Permit 3-9020

Submission of this completed form constitutes notice that the entity in Section C seeks to be added as a co-permittee to an existing authorization to discharge under Vermont’s Stormwater Construction General Permit (CGP) from the project identified in Section A. All landowners and persons who meet the definition of Principal Operator (Subparts 2.1B, 3.1B of the CGP) and who were not included on the original NOI must submit a Notice of Addition form.

A. Project Information

1. Project Name:

2. Notice of Intent Number:

B. Original Permittee Information 1.Name:

2. Mailing Address:

a. Street/PO Box:

b. City/Town:

c. State:

d. Zip:

3. Contact Information

a. Phone:

b. Fax:

c. Email:

C. New Co-Permittee Information

Check one or both: New Landowner New Principal Operator

1.Name:

2. Business Name:

3. Mailing Address:

a. Street/PO Box:

b. City/Town:

c. State:

d. Zip:

4. Contact Information

a. Phone:

b. Fax:

c. Email:

D. Request for Addition as Co-Permittee I hereby request that the entity in Section C be added as co-permittee to the existing authorization to discharge stormwater from construction activities stated in Section A. In requesting co-permittee status, I hereby certify under the penalty of law that I have read, understand, and meet the eligibility conditions of the CGP; that I agree to comply with all applicable terms and conditions of the CGP; that I understand that continued authorization under the CGP is contingent on maintaining eligibility for coverage, and that the applicable practices in the authorized Erosion Prevention and Sediment Control Plan must be implemented and maintained for the duration of the construction activities. I agree to comply with all applicable terms and conditions of the General Permit 3-9020.

Signature: Date:

Submit Original Form to:

VT DEC, Watershed Management Division

1 National Life Drive, Main 2 Montpelier, VT, 05620-3522

Permittee Directions for Posting:

This notice shall be placed near the construction entrance at a location visible to the public. If displaying near the main entrance is infeasible, the notice shall be posted in a local public building such as the town hall or public library. For linear projects, the notice shall be posted at a publicly accessible location near the active part of the construction project (e.g., where a pipeline project crosses a public road).

Section 00 90 02

Geotechnical Report

Bartlett Brook North Stormwater:

Stonehedge and Laurel Hill

South Burlington, Vermont

GEOTECHNICAL REPORT

Prepared for:

City of South Burlington

Prepared by:

SEPTEMBER 2012

TABLE OF CONTENTS

1. INTRODUCTION

1.1. Existing Project Description

2. STONEHEDGE

3. LAUREL HILL

1. INTRODUCTION

1.1. Existing Project Description

A stormwater study was developed for the Greater Stonehedge Stormwater Committee and the City of South Burlington in 2007. According to that report, “The Stonehedge development, located off of Spear Street in South Burlington, had been experiencing stormwater drainage problems for a number of years. Changes in the watershed and aging infrastructure have resulted in damage to personal and city property, safety issues, and aesthetic concerns. Some of these problems include standing water, ice accumulation in the winter, wet soil, erosion, and sedimentation. The Stonehedge development was issued a temporary pollution (stormwater) permit from the State of Vermont Agency of Natural Resources (ANR) when it was constructed. However, this permit expired on July 1, 1985. In order for the City’s Stormwater Utility to consider taking ownership of the Stonehedge stormwater system, it will need to be brought into compliance under the ANR Engineering Feasibility Analysis (EFA), which attempts to comply with the State of Vermont ANR 2002 Stormwater Treatment Standards.”

In 2010, the City of South Burlington brought the Laurel Hill development, which was experiencing similar problems, into the study process, and commissioned a study to identify solutions to the stormwater problems in both neighborhoods. These neighborhoods are shown on the below project location map.

2. STONEHEDGE

The purpose of the borings within the Stonehedge development was to characterize soil materials, groundwater depths, and absence of shallow ledge at key locations where improvements were proposed. A total of 5 borings were performed: two in the location of the proposed stormwater pond and three along the proposed drainage pipe routes. Note that the drainage pipe proposed along SH4 and SH5 was abandoned during the design process due to its depth, disruption and serviceability.

The soils were characterized as sand with little silt overlaying clay at a depth of 16 feet.

3. LAUREL HILL

The purpose of the borings within the Laurel Hill Project was to characterize the soil type and depth of groundwater to support an in-ground stormwater infiltration system under Deborah Drive. Deborah Drive was chosen as it was free of other utilities and easily accessible form the existing stormwater piping network. The soils were found to be sand with suitable characteristics to support an infiltration system. However, the groundwater conditions were not. At the time (fall 2010) of the borings, groundwater was reported in the range of 2 to 5 feet below the surface. Several ground water monitoring wells were installed at that time. These wells were checked again in the summer (July 2011) and groundwater was found to be between 32 and 52 inches below the surface. It was therefore concluded that an inground stormwater infiltration system was not feasible.

Additional subsurface explorations were not necessary as the proposed pipeline will follow the alignment of the existing stormsewers at approximately the same depth. In addition the City Public Works Department reported that the soils within the project area are sands with no ledge encountered within the depth range proposed.

Stonehedge Boring Plan 12/10/10

Stonehedge #1 and #2 (SH1, SH2)

• Intended to characterize material at the pond site and document groundwater elevation.

• Locate on side of existing trail/berm in woods.

• Install screened well casing (PVC or other) for future GW level monitoring.

• Finish with removable cap and 0 – 6” casing exposed above grade.

• Continuous recovery/sampling from 0’ to 20’ for possible future lab testing following engineer’s review of logs.

• SPT in 2’ increments from 0’ to 20’.

• Continuous log of soil classification based on visual observations.

• Document groundwater level at time of boring and note any visual indication of seasonal high water.

Stonehedge #3, #4, and #5 (SH3, SH4, SH5)

• Intended to characterize material and document groundwater elevation along future pipe alignments.

• SPT in 2’ increments from 0’ to 20’.

• Continuous log of soil classification (USCS) based on visual observations.

• Document groundwater level at time of boring and note any visual indication of seasonal high water.

• Restore lawn around boring and any access path.

"?B

"?B"?B

"?B

"?B

"?B

"?B "?B

"?B

"?B

"?B "?B

"?B

"?B "?B

"?B

"?B "?B

"?B

"?B "?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B "?B"?B

"?B

"?B

"?B

"?B

"?B "?B

"?B

"?B

"?B "?B

"?B "?B

"?B

"?B"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B

"?B "?B

"?B

"?B

OAK HILL DR

STONEHEDGE DR

CEDAR GLEN DR

ST

O

N

EH

ED

G

E D

R

SP

EA

R S

T

CITY

PARK

37033

270 38 mmurawski Oval

Text Box

SH5

mmurawski Text Box

SH4

mmurawski Text Box

SH3

mmurawski Text Box

SH2

mmurawski Text Box

SH1

mmurawski Oval mmurawski Oval mmurawski Oval

Laurel Hill Boring Plan 12/9/10

Laurel Hill #1, #2, and #3 (LH1, LH2, LH3)

• Intended to characterize material and document groundwater elevation.

• Locate just off curb in lawn area.

• Install screened well casing (PVC or other) for future GW level monitoring.

• Finish with removable cap and 0 – 6” casing exposed above lawn.

• Continuous recovery/sampling from 0’ to 20’ for possible future lab testing following engineer’s review of logs.

• SPT in 2’ increments from 0’ to 20’.

• Continuous log of soil classification based on visual observations.

• Document groundwater level at time of boring and note any visual indication of

• Restore lawn around well.

Laurel Hill #4 (LH4)

• Intended to characterize road materials and depths

• Locate in roadway near curb.

• SPT in 2’ increments from 0’ to 10’.

• Continuous log of soil classification based on visual observations.

• Document groundwater level at time of boring and note any visual indication of

• Fill boring hole and restore pavement.

Laurel Hill #5 (LH5)

• Intended to document on-site infiltration rate

• Locate just off curb in lawn area.

• Install 4-6” solid casing (PVC or other) to a depth of 12’. NOTE: Engineer may reduce depth to less than 12’ in response to shallow groundwater or consistent soil characteristics.

• Finish with removable cap and 0 – 6” casing exposed above lawn.

"?B "?B "?B

"?B "?B "?B

"?B "?B

"?B "?B "?B

"?B

"?B

"?B

"?B "?B "?B

"?B

"?B

"?B"?B

"?B "?B

"?B

"?B"?B

"?B "?B

"?B "?B

"?B "?B "?B"?B "?B

"?B "?B

"?B

"?B "?B"?B

"?B "?B "?B"?B

"?B "?B

"?B

"?B

"?B

ANDREWS AV

G R

EE

N

D O

LP

H

IN

D

R

SCOTSDALE RD

SANDALWOOD RD

SEBRING RD

D

EB

O

R A

H D

R

YA

N

D O

W D

R

BARTLETT BROOK

BARTLETT

BROOK

FF

F F

FF

FF

F F

FF FF

F F

FF

FF

FF

FF

FF

INFILTRATION CHAMBERS

REPLACEMENT STORM

DRAIN PIPING

NEW STORM

DRAIN PIPING

EXISTING STORM

DRAIN PIPING

FF

mmurawski Oval mmurawski Text Box

LH1

mmurawski Oval mmurawski Oval mmurawski Text Box

LH1

mmurawski Text Box

LH3

mmurawski Text Box

LH4

mmurawski Text Box

LH5

mmurawski Text Box

LH2

Stone Hedge and Laurel Hill Stormwater Improvements BARTLETTBROOKN

SECTION 01 11 00

SUMMARY OF WORK

09/13

PART 1 GENERAL (For Laurel Hill)

WORK COVERED BY CONTRACT DOCUMENTS

1.1 Project Description

The work includes construction of new storm drains, catch basins, precast concrete stormwater structures and incidental related work.

Location

The work is located at the Laurel Hill residential area in South Burlington, VT, approximately as indicated. as shown on the drawings.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.00 18 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Plan; G, RO

Submit for approval 15 days prior to commencement of work.

1.3 OCCUPANCY OF PREMISES

The Contractor shall submit,15 days before work is started, to the Contracting Officer for approval a construction plan, which shall include sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Owner. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

SECTION 01 11 00 Page 1

1.5 LOCATION OF UNDERGROUND UTILITIES

Verify the locations, elevations and sizes of existing piping, utilities,and any type of underground obstruction in locations to be traversed or crossed by new piping, structures, and other work to be conducted or installed. Contact DIG-SAFE at 1-800-DIG-SAFE (WWW.DIGSAFE.COM) to locate existing underground utilities prior to construction.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 01 11 01

SUMMARY OF WORK

09/13

PART 1 GENERAL (For Stonehedge)

WORK COVERED BY CONTRACT DOCUMENTS

1.1 Project Description

The work includes construction of new storm drains, catch basins, precast concrete stormwater structures, stone-lined ditches, a stormwater treatment and detention pond, bio-retention areas, a wetland mitigation landscape area, and incidental related work.

Location

The work is located at the Stonehedge Drive residential area in South Burlington, VT, approximately as indicated. as shown on the drawings.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00.00 18 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Construction Plan; G, RO

Submit for approval 15 days prior to commencement of work SD-01

1.3 OCCUPANCY OF PREMISES

Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Owner. At the completion of

SECTION 01 11 01 Page 1 operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.5 LOCATION OF UNDERGROUND UTILITIES

Verify the locations, elevations and sizes of existing piping, utilities,and any type of underground obstruction in locations to be traversed or crossed by new piping, structures, and other work to be conducted or installed. Contact DIG-SAFE at 1-800-DIG-SAFE (WWW.DIGSAFE.COM) to locate existing underground utilities prior to construction.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 01 Page 2

SECTION 01 12 00.00 18

DESIGN AND RECORD DRAWING REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

All RECORD DRAWINGS (or "as-builts") to be provided under this contract shall be accomplished and developed using computer-aided design and drafting (CADD) software and procedures conforming to the following criteria.

1.2 GRAPHIC FORMAT

All CADD data shall be supplied in Bentley Systems, three-dimensional, MicroStation V8, native electronic digital format (i.e., .dgn, .cel). The contractor shall ensure that all digital files and data (e.g., model files, sheet files, reference files, cell libraries) are compatible with the Government's target CADD system (i.e., basic and advanced CADD software, platform, database software), and adhere to the standards and requirements specified herein. The term "compatible" means that data can be accessed directly by the target CADD system without translation, preprocessing, or postprocessing of the electronic digital data files. It is the responsibility of the contractor to ensure this level of compatibility.

1.3 CADD STANDARDS

CADD drawings shall be prepared in accordance with the Department of Defense Architectural/Engineering/Construction (A/E/C) Computer-Aided Design and Drafting (CADD) Standard, Release 5. Standard drawing size shall be ANSI-D CADD drawings shall be prepared using inch-pound units.

All model files and sheet files shall include the following project code in their A/E/C CADD Standard file-name: Bartlett Brook North Stormwater Treatment Improvements, Stonehedge and Laurel Hill, City of South Burlington, VT

The Contractor shall submit a written request for approval of any deviations from the Government's established A/E/C CADD standard. No deviations from the Government's established A/E/C CADD standard will be permitted unless prior written approval of such deviation has been received from the Government.

1.4 DELIVERY MEDIA AND FORMAT

All CADD data and files developed under this contract shall be delivered to the Government on electronic digital media at project completion, with each submittal as required in the Schedule of Work. The electronic digital data and files shall be provided on optical media (CD-ROM or DVD-R), referred to as a "disc." Each disc shall be delivered to the Government in a separate container, commonly referred to as a "jewel box." The electronic digital media shall be in a format that can be read and

SECTION 01 12 00.00 18 Page 1 processed by the Government's target CADD system.

Model files, sheet files, and other associated files shall not be device-dependent, nor shall the directory structure of the disc require any reconfiguration or other manipulation on the Government's part to view, print, and plot the files directly from the disc. The directory structure of the disc shall be configured such that a complete download of the disc's contents to an electronic folder on a Government computer's hard drive will not require any reconfiguration or other manipulation on the Government's part to view, print, and plot the files.

A tagged portable document format (.pdf) file containing the set of full-sized plotted Sheet Files shall be also included on each disc. This .pdf set shall contain active bookmarks linking to each drawing in the set. The initial view of this set shall conform to the following settings: Layout and Magnification/Navigation Tab set to Bookmarks Panel and Page. Layout and Magnification/Page Layout set to Single Page. Layout and Magnification/Magnification set to Fit Page. (For further information on tagged .pdf documents refer to this website:

http://blogs.adobe.com/acrolaw/2006/01/understanding_t_1.html.)

Each disc shall be labeled with a printed label and each printed disc label shall contain, as a minimum, the following information:

(1) The Project's Name, Contract Number (and Delivery Order Number if applicable), date, and version and/or submission number.

(2) The name of the preparer's firm and the name and phone number of the preparer's Point-of-Contact for the project.

(3) The sequence number of the digital media for multiple-disc submittals.

(4) A description of the contents of the disc (e.g., "Architectural Plans," etc.).

Note: it is acceptable, storage permitting, to include specifications, design analyses and other data on the disc as space permits. These items shall be included in the disc label in accordance with paragraph above.

1.5 HARD COPY TRANSMITTALS

A transmittal letter shall accompany each electronic digital media submittal to the Government. The transmittal letter shall be dated and signed by the appropriate Contractor's representative. The transmittal letter shall be provided to the Government on 8-1/2-inch by 11-inch paper. An electronic copy of the transmittal letter in .pdf format shall also be provided on the electronic digital media submitted to the Government. The transmittal letter shall contain, as a minimum, the following information:

(1) The information included on the external label of each CD-ROM, along with the total number being delivered, and a list of the names and descriptions of the files on each media unit.

(2) List of all new symbol cells created for the project, which were not provided to the Contractor with the Government-furnished materials. List of all new figures, symbols, tables, schedules, details, and other cells created for the project, which were not provided to the Contractor with

SECTION 01 12 00.00 18 Page 2 the Government-furnished materials, and any associated properties. List of all database files associated with each drawing, as well as a description and documentation of the database format and schema design. Recommended modifications which will be necessary to make the data available for GIS use.

(3) Certification that all delivery media are free of known computer viruses. A statement including the name(s) and release date(s) of the virus-scanning software used to analyze the delivery media, the date the virus scan was performed, and the operator's name shall also be included with the certification. The release or version date of the virus-scanning software shall be the current version which has detected the latest known viruses at the time of delivery of the digital media.

(4) A statement indicating that the A-E will retain a copy of all delivered electronic digital media (with all files included) for at least one year and, during this period of time, will provide up to 2 additional copies of each to the Government, if requested, at no additional cost.

(5) List of any deviations from the Government's standard level scheme and file-naming conventions and a copy of the Government's signed and dated approval letter allowing these exact deviations from the DoD A/E/C CADD Standard.

1.6 OWNERSHIP

The Government, for itself and such others as it deems appropriate, will have unlimited rights under this contract to all information and materials developed under this contract and furnished to the Government and documentation thereof, reports, and listings, and all other items pertaining to the work and services pursuant to this agreement including any copyright. Unlimited rights under this contract are rights to use, duplicate, or disclose text, data, drawings, and information, in whole or in part in any manner and for any purpose whatsoever without compensation to or approval from the Contractor. The Government will at all reasonable times have the right to inspect the work and will have access to and the right to make copies of the above-mentioned items. All text, electronic digital files, data, and other products generated under this contract shall become the property of the Government. By reference, the following DFAR clauses are included in this contract as a part of the requirements herein:

a. DFAR 252.227-7013, "Rights in Technical Data - Noncommercial Items."

b. DFAR 252.227-7017, "Identification and Assertion of Use, Release, or Disclosure Restrictions."

c. DFAR 252.227-7020, "Rights in Special Works."

d. DFAR 252.227-7028, "Technical Data or Computer Software Previously Delivered to the Government."

e. DFAR 252.227-7037, "Validation of Restrictive Markings on Technical Data."

f. DFAR 252.227-7025, "Limitations on the Use or Disclosure of Government-Furnished Information Marked with Restrictive Legends."

g. DFAR 252.227-7014, "Rights in Noncommercial Computer Software and

SECTION 01 12 00.00 18 Page 3

Noncommercial Computer Software Documentation."

1.7 GOVERNMENT-FURNISHED MATERIALS

The DoD A/E/C CADD Standard, Cover and Border sheet model files shall be downloaded from this website:

https://cadbim.usace.army.mil/CAD.

1.8 RETAINAGE

Failure of the contractor to provide the associated design or construction documents in compliance with the DoD A/E/C CADD Standard, will result in withholding of the progress payment.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 12 00.00 18 Page 4

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

09/13

PART 1 GENERAL (For Laurel Hill)

1.1 LUMP SUM PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Mobilization and Demobilization (Item 1)

1.1.1.1 Payment

Payment will be made for costs associated with mobilization and demobilization including movement of personnel, equipment, and materials to project site, establishment of field offices and related facilities, movement of same from the project site, and cleanup work as required.

1.1.1.2 Unit of Measure

Unit of measure: lump sum.

1.1.2 Maintenance of Traffic (Item 2)

1.1.2.1 Payment

Payment will be made for costs associated with maintaining traffic flow in and adjacent to the project site. Payment for this item shall include costs for traffic officers, flag persons, detour signage, and any other work items associated with traffic control.

1.1.2.2 Unit of Measure

Unit of measure: lump sum.

1.1.3 Storm Drain Vaults (Items 3A to 3C)

1.1.3.1 Payment

Separate payments will be made for costs associated with the construction and installation of Vault No. 1, No. 2 and No. 3 as shown on the drawings.

SECTION 01 22 00.00 10 Page 1

1.1.3.2 Unit of Measure

Unit of measure: lump sum.

1.1.4 Precast Concrete Headwall(Item 4)

1.1.4.1 Payment

Payment will be made for costs associate with the construction and installation of the precast conrete headwall as shown on the drawings.

1.1.4.2 Unit of Measure

Unit of measure: lump sum.

1.1.5 Chain Link fence with 12 foot swing gate (Item 5)

1.1.5.1 Payment

Payment will be made for costs associate with the installation of the chain link fence and gate as shown on the drawings. Payment will include costs for removal and disposal of the existing fence.

1.1.5.2 Unit of Measure

Unit of measure: lump sum.

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.2.1 60" by 24" Precast Concrete Box (Item 6)

1.2.1.1 Payment

Payment will be made for costs associated with the construction and installation of the concrete box as shown on the drawings.

1.2.1.2 Measurement

Measure actual length of concrete box installed from the inside face of Vault No. 1 to the outlet.

1.2.1.3 Unit of Measure

Unit of measure: linear foot

1.2.2 HDPE Storm Drains (Items 7A to 7F)

1.2.2.1 Payment

Payment will be made for costs associated with installation of the various

SECTION 01 22 00.00 10 Page 2 sizes of storm drain piping as shown on the drawings.

1.2.2.2 Measurement

Measure actual length of the storm drains installed from the inside faces of structures to the outlets.

1.2.2.3 Unit of Measure

Unit of measure: linear foot

1.2.3 Manholes and Catch Basins (Items 8A to 8D)

1.2.3.1 Payment

Payment will be made for costs associated with installation of the various sizes of catch baisins and manholes including frames, grates, and covers as shown on the drawings.

1.2.3.2 Measurement

Count the number of units installed for each item

1.2.3.3 Unit of Measure

Unit of measure: each

1.2.4 Stone Protection (Item 9)

1.2.4.1 Payment

Payment will be made for costs associated with placement of stone protection as shown on the drawings

1.2.4.2 Measurement

Measure the area of stone protection placed

1.2.4.3 Unit of Measure

Unit of measure: square yard

1.2.5 Connect Existing Storm Drains (Item 10)

1.2.5.1 Payment

Payment will be made for costs associated with the connection of existing storm drains to new storm drain structures.

1.2.5.2 Measurement

Count the number of storm drains connected to new structures

1.2.5.3 Unit of Measure

Unit of measure: each

SECTION 01 22 00.00 10 Page 3

1.2.6 Remove Exiting Storm Drains (Item 11)

1.2.6.1 Payment

Payment will be made for costs associated with the removal and disposal of existing storm drains as shown on the drawings.

1.2.6.2 Measurement

Measure the actual length of storm drains removed

1.2.6.3 Unit of Measure

Unit of measure: linear foot

1.2.7 Remove Existing Catch Basins (Item 12)

1.2.7.1 Payment

Payment will be made for costs associated with removal and disposal of existing catch baisins.

1.2.7.2 Measurement

Count the number of catch basins removed

1.2.7.3 Unit of Measure

Unit of measure: each

1.2.8 Relocate Existing Water Mains (Item 13A to 13C)

1.2.8.1 Payment

Payment will be made for costs associated with relocation of the various sizes of water mains necessary to avoid conflicts with the new work.

1.2.8.2 Measurement

Count the number of water mains relocated

1.2.8.3 Unit of Measure

Unit of measure: each

1.2.9 Extend and Connect Existing Basement/Foundation Drains (Item 14)

1.2.9.1 Payment

Payment will be made for costs associated with extending and reconnecting existing drains to new sotrm drain structures.

1.2.9.2 Measurement

Measure the actual length of drains extended

1.2.9.3 Unit of Measure

Unit of measure: linear foot

SECTION 01 22 00.00 10 Page 4

1.2.10 Rock Excavation (Item 15)

1.2.10.1 Payment

Payment will be made for costs associated with the excavation and disposal of rock as defined in the specifications including necessary drilling and blasting.

1.2.10.2 Measurement

Measure the in place volume of rock to be excavated within the limits described in the specifications

1.2.10.3 Unit of Measure

Unit of measure: cubic yard

1.2.11 Pavement Replacement (Item 16)

1.2.11.1 Payment

Payment will be made for costs associated with temporary and permanent replacement of bituminous pavement within the limits shown on the drawings. Included for payment under this item are costs for cutting exisitng pavement, removal and disposal of exisiting and temporary pavement, and replacement and regrading of subbase material

1.2.11.2 Measurement

Measure the area of replaced pavement within the limits shown on the drawings.

1.2.11.3 Unit of Measure

Unit of measure: square yard

1.2.12 Replace Existing Concrete Curbs (Item 17)

1.2.12.1 Payment

Payment will be made for costs associated with replacing existing concrete curbs that are removed to facilitate construction of the storm drain system. Included for payment under this item are costs associated with removal and disposal of existing curbs.

1.2.12.2 Measurement

Measure the actual lengths of the various types of curbs replaced

1.2.12.3 Unit of Measure

Unit of measure: linear foot

1.2.13 Remove and Replace Existing Paved Drive (Item 18)

1.2.13.1 Payment

Payment will be made for costs associated with the removal and replacement

SECTION 01 22 00.00 10 Page 5 of the existing driveway as shown on the drawings. Included for payment under this item are costs for replacement and regrading of subbase material.

1.2.13.2 Measurement

Measure the area of paved driveway replaced

1.2.13.3 Unit of Measure

Unit of measure: square yard

1.2.14 Removal of Existing Trees and Stumps (Item 19)

1.2.14.1 Payment

Payment will be made for costs associated with the removal of…