31 62 19.13 Wood Marine Piles-Final

View the file

Other files

File Type Posted
BBN_Laurel_Hill_Plans_Post-100__20150710_Bid_doc.pdf PDF
W912DS-14-B-0014.pdf PDF
BBN_Stonehedge_Plans_Post-100__20150710_Bid_doc.pdf PDF
Bartlett_Brook_Specs_100_Kim_01_57_20.00_10_Edit_.pdf PDF
Bid_Abstract.pdf PDF
W912DS-15-B-0012-0009.pdf PDF
W912DS-15-B-0012-0008.pdf PDF
W912DS-15-B-0012-0007.pdf PDF
02_32_00.pdf PDF
Amendment_0006.pdf PDF
Main_Table_of_Contents.pdf PDF
Submittal_Register.pdf PDF
W912DS-15-B-0012-0005.pdf PDF
W912DS-15-B-0012-0004.pdf PDF
W912DS-15-B-0012-0003.pdf PDF
C-106.pdf PDF
C-107.pdf PDF
DTM_07-2014_ELBERON_TO_LOCH_ARBOUR_NAVD88.xyz XYZ file
W912DS-15-B-0012-0002.pdf PDF
90-PDFSW912DS-15B-0012-0015-C-309.pdf PDF
G-102.pdf PDF
W912DS-15B-0012-0015-C-104.pdf PDF
amend2_G-001.pdf PDF
W912DS-15-B-0012-0001.pdf PDF
Pages_11-20_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
Pages_21-40_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
04_00_90_05_Geotechnical_ReportL_AppendixVolume_144DPI.pdf PDF
01_00_90_05_Geotechnical_Report_DEAL_MainReport.pdf PDF
02_00_90_05_Geotechnical_Report_DEAL_QuadrantsReport_1and2.pdf PDF
W912DS-15-B-0012.pdf PDF
03_00_90_05_Geotechnical_Report_QuadrantsReport_3and4.pdf PDF
Pages_1-10_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
W912DS-15-B-0012_Deal_Final_Specs_-CT_2-june_25_red.pdf PDF
Pages_41-51_W912DS-15-B-0012_Deal_Final_Plans-CT_2-june_25.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 31 62 19.13

WOOD MARINE PILES

04/06

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)

AWPA A4 (2011) Standard Methods for Sampling Wood Preservatives

AWPA A9 (2013) Standard Method for Analysis of Treated Wood and Treating Solutions by X-Ray Spectroscopy

AWPA M2 (2011) Standard for Inspection of Treated Wood Products

AWPA M4 (2011) Standard for the Care of Preservative-Treated Wood Products

AWPA M6 (2013) Brands Used on Preservative Treated Materials

AWPA U1 (2013) Use Category System: User Specification for Treated Wood

ASTM INTERNATIONAL (ASTM)

ASTM A1011/A1011M (2014) Standard Specification for Steel, Sheet, and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability and Ultra-High Strength

ASTM D25 (2012) Round Timber Piles

ASTM D450/D450M (2007; E 2013; R 2013) Coal-Tar Pitch Used in Roofing, Dampproofing, and Waterproofing

ASTM D3689 (2007; E 2013; R 2013) Standard Test Methods for Deep Foundations Under Static Axial Tensile Load

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 1110-2-2906 Design of Pile Foundations

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 171 Certification of Pesticide Applicators

WESTERN WOOD PRESERVERS INSTITUTE (WWPI)

WWPI Mgt Practices (1996; R 2011) Best Management Practices for the Use of Treated Wood in Aquatic Environments

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are [for Contractor Quality Control approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Piles; G, AE

Pile driving equipment; G, AE

Submit complete descriptions of pile driving equipment, including hammers, leads, driving helmets, cushion blocks, driving blocks, collars, extractors, and other appurtenances for approval prior to commencement of work.

Pile caps; G, AE

Pile shoes; G, AE

Jetting equipment; G, AE

Spudding equipment; G, AE

Predrilling equipment; G, AE

SD-04 Samples

Test piles; G, AE

If approved after test completion, include properly located test piles in finished work.

SD-06 Test Reports

Test Pile Plan; G, AE

Load tests; G, AE

Test data and results as specified in paragraph entitled "Load Tests."

Preservative treated piles; G, AE

A certified test assay analysis from an approved testing organization attesting that the piles to be used in the work have been given the preservative treatment required by these specifications shall be submitted prior to commencement of the work.

SD-07 Certificates

MSDS and CIS; G, AE

Best Management Practices (BMPs); G, AE

SD-11 Closeout Submittals

Test piles and Job piles driving records; G, AE

Submit pile driving records within 24 hours after completion of driving.

1.3 MEASUREMENT AND PAYMENT

No measurement is required. Payment will be included in the lump sum prices shown on the bid schedule, which shall include cost of materials, equipment, and installation, including all items incidental to furnishing and driving the piles, redriving uplifted piles, any required notching and dapping, the cutting off of all piles at the cutoff elevation, the preservative treatment of the tops and daps of treated piles, and the removal and disposal of any new piles damaged during driving as per Paragraph REJECTION OF PILES, and its subparagraphs, herein. Payment also includes the marine warning sign installation and materials as shown on the Contract Drawings.

The bid schedule includes a unit price item for "Southern Yellow Pine Pile, Class A, 45' Long" with a unit of EACH. This only applies to the instance if a pile is damaged during driving ONLY due to buried obstructions. The unit price per each includes removal of damaged pile, installing a new pile in place with steel shoe, and includes all other installation, materials, and equipment as specified herein. If this occurs, the use of the unit price item will only be at the discretion of the Contracting Officer.

1.4 QUALITY ASSURANCE

1.4.1 Preservative Treated Piles - Timber

The Contractor shall be responsible for the quality of treated wood products. The Contractor shall provide the Contracting Officer's Representative (COR) with the inspection report of an independent inspection agency, approved by the Contracting Officer, that offered products comply with applicable AWPA standards. Identify treatment on each piece by the quality mark of an agency accredited by the Board of Review of the American Lumber Standard Committee. Inspect all preservative-treated wood visually to ensure there are no excessive residual materials or preservative deposits. Materials shall be clean and dry or it will be rejected because of environmental concerns.

1.4.2 MSDS and CIS

Provide Materials and Safety Data Sheets (MSDS) and Consumer Information Sheets (CIS) associated with timber pile preservative treatment.

Contractor shall comply with all safety precautions indicated on MSDS and

CIS.

1.4.3 Best Management Practices (BMPs)

The producer of the treated wood products shall provide certification that Best Management Practices (BMPs), published by the WWPI Mgt. Practices, for the use of Treated Wood in Aquatic Environments were utilized including a written description and appropriate documentation of the BMPs utilized.

1.5 DELIVERY, STORAGE, AND HANDLING

Handle and store piles in accordance with AWPA M4. Comply with paragraph entitled "MSDS and CIS." Special care shall be taken in supporting piles to prevent the including of excessive bending stresses in the piles. Piles shall be carefully handled without dropping, breaking of outer fibers, and penetrating the surface with tools. Peaveys, cant hooks, pikes, and other pointed tools shall not be used in handling treated piles.

1.6 UNIT PRICES

1.6.1 Pile Load Tests

1.6.1.1 Payment

Payment for each complete test load of a single pile will be made at the contract unit price for each pile load test.

1.6.1.2 Measurement

Pile load test will be measured for payment based upon furnishing, placing, and removing testing equipment and test loads.

1.6.1.3 Unit of Measure

Unit of measure: each.

PART 2 PRODUCTS

2.1 MATERIALS

2.1.1 Piles

Provide Southern Yellow Pine clean-peeled, treated piles conforming to ASTM D25, Class "A" and other requirements as specified; diameters shown on places. Piles shall be in one piece of the lengths required to obtain the minimum capacities and lengths indicated in Table 1. For each outfall, the minimum length of pile shall be measured from the bottom of the pile cap at each pile location as shown in the contract drawings. The elevation of the bottom of the pile cap is referred to herein as the cutoff elevation. The bottom of a pile driven in accordance with Table 1 is referred to herein as the tip elevation.

Splices will not be permitted. Each treated pile shall be branded by the producer, in accordance with AWPA M6. The Contractor shall have additional pile shoes and steel collars on hand as needed to accommodate variable conditions.

Table 1 - PILE REQUIREMENTS

LOCATION

(NOTE 1)

LENGTH (MIN) SHOES

REQUIRED

COLLARS

REQUIRED

PILE

CAPACITY

(MIN)

OUTFALL 19 40 FT Y N 35 T

INTAKE

32/OUTFALL

35 FT Y N 15 T

OUTFALL 34 40 FT Y Y 35 T

OUTFALL 36B 40 FT Y Y 35 T

NOTE 1: LOCATIONS INCLUDE ASSOCIATED MANHOLE PILES AND MARKER PILES

2.1.2 Preservative Treatment

Treat all piles in accordance with AWPA U1. Use Category UC5A with waterborne preservatives (ACA - Ammoniacal Copper Arsenate, ACZA - Ammoniacal Copper Zinc Arsenate or CCA - Chromater Copper Arsenate).

2.1.3 Coal-Tar Pitch

Coal-tar pitch for brush treatment of piles shall conform to ASTM D450/D450M, Type A.

2.1.4 Pile Shoes

Comply with ASTM A1011/A1011M. Welded-plate point shoe especially fabricated for pile driving. Shoes shall be the product of a manufacturer regularly engaged in the manufacture of pile fittings. Welding procedures shall be in accordance with a nationally recognized welding code. Provide size to fit pile tip. Fabricate welded-plate point type of four 3/16 inch or 1/4 inch steel plates, fully welded and sized to adequately cover full pointed area of pile; provide each plate with one 3/16 inch or one 1/4 inch nail hole. The length of the joints formed by the intersection of the sides shall not be less than one half of the height of the shoe. Shoes may be furnished without painted finish. Provide on the point of piles within 15 feet of exposed toe of existing groins and as indicated in Table 1.

2.1.5 Warning Marker Pile Caps

Provide 20 ounce copper sheet for warning marker piles only.

2.2 TESTS, INSPECTIONS, AND VERIFICATIONS

2.2.1 Inspection of Piles

The Contractor shall provide the necessary facilities for the proper inspection of each pile. Piles to be preservative treated will be inspected prior to treatment. Piles will be inspected at the shipping point or at the work site as coordinated with the Contracting Officer.

Pile inspection at the shipping point will not be performed for less than 100 piles in one locality. Piles with specified variations in characteristics shall be placed in separate lots for inspection. Piles shall be so marked or segregated into marked lots that there will be no possibility of error in assignment after they have been inspected. Piles damaged after inspection may be subsequently rejected if damage is deemed sufficient for rejection. All rejected piles shall be removed and properly disposed of as directed at no additional cost to the Government.

The Contractor shall notify the Contracting Officer of the pile inspection not less than 15 days prior to the anticipated data and shall provide the necessary facilities for the proper inspection. Allow the Contracting Officer unlimited access and inspection privileges.

2.2.2 Inspection of the Preservative Treatment Process

Inspection of the preservative treatment process will be in accordance with AWPA M2. The Contractor shall notify the Contracting Officer where preservative treatment will be done not less than 15 days prior to the start of the treatment and shall provide the necessary facilities for the proper inspection of the treatment process. Allow the Contracting Officer unlimited access to the plant and inspection privileges for each facet of the treating process.

2.2.3 Sampling and Testing

Sampling and testing shall be performed by an approved testing organization adequately equipped to perform such services.

2.2.3.1 Sampling

Representative samples of preservatives for testing shall be obtained from storage containers using the methods described in AWPA A4. The analysis of wood treated with waterborne preservatives shall be done in accordance with

AWPA A9.

2.2.3.2 Testing

Waterborne preservatives shall be tested for conformance to AWPA A9. The determination of the net retention of waterborne preservatives in piles which have received the dual treatment of waterborne preservatives and creosote or creosote solutions shall be made after the extraction of the creosote or creosote solutions.

PART 3 EXECUTION

3.1 INSTALLATION

3.1.1 Pile Driving Equipment

Pile driving equipment shall meet the following requirements.

3.1.1.1 Pile Driving Hammers

Pile driving hammers shall be steam, air or diesel drip, single-action, double-acting, differential-acting, or vibratorytype. The size or capacity of hammers shall be as recommended by the manufacturer for the pile weights and solid formation to be penetrated. The pile hammer shall be of sufficient weight and energy to install the specified pile without damage into the soils as indicated. The maximum driving energy of hammers shall be 18,500 foot-pounds for piles for any length. Test piles shall be driven with the same size and type hammer, operating with the same effective energy and efficiency as that to be used in driving job piles. Diesel powered hammers shall be operated at the rate recommended by the manufacturer throughout the entire driving period. Sufficient pressure shall be maintained at the hammer so that:

a. For double-acting hammers, the number of blows per minute during and at the completion of driving of a pile is equal approximately to that at which the hammer is rated;

b. For single-acting hammers, there is a full upward stroke of the ram;

and,

c. For differential-type hammers, there is a slight rise of the hammer base during each upward stroke.

3.1.1.2 Operating Speed

Provide sufficient compressor capacity at all times to maintain the rated speed of hammer during the full time of driving a pile. Maintain the valve mechanism and other parts of the hammer in first class condition so that the length of stroke, for a single acting hammer, and the number of blows per minute, for a double acting hammer, for which the hammer is designed, will be obtained. Any double acting hammer not operating at the rated hammer speed specified in the manufacturer's catalogue, for the particular hammer being used, shall be deemed unsatisfactory and shall be removed from the site.

3.1.1.3 Diesel Hammers

Provide all diesel hammers with an acceptable means of measuring hammer energy. When pressure gages are included as normal equipment, furnish and maintain them in operable condition. Submit hammer manufacturer's charts and graphs that are required to calibrate hammer energy. Arrange easy access to the pressure gages so the Contracting Officer may conveniently take readings at the site.

3.1.1.4 Leads

Leads are required and shall be fixed at the top and adjustable at the bottom. Swinging leads may be allowed if site conditions merit their use and are approved or if a driving template is provided.

3.1.1.5 Driving Cap or Helmet and Cushion Block

Driving cap or helmet shall be an approved design and shall be capable of protecting pile heads, minimizing energy absorption, and transmitting hammer energy uniformly and consistently to piles. Place driving helmet or cap and cushion block combination between top of pile and the ram. Driving cap shall fit snugly on the top of piles and shall employ a cushion block to prevent impact damage to piles. The cushion block may be a solid or laminated softwood block with the grain parallel to the pile axis and enclosed in a close-fitting steel housing. The thickness of the block shall be suitable for the length of pile to be driven and the character of subsurface material to be encountered. If block is damaged, split, highly compressed, charred or burned, or has become spongy or deteriorated, replace with new block at no additional cost to the Government. Under no circumstances will the use of small wood blocks, wood chips, rope or other material permitting excessive loss of hammer energy be permitted.

3.1.1.6 Pile Collars and Shoes

Collars or bands for protecting pile butts against splitting, brooming, and other damage while being driven shall be of an approved design. Shoes shall be fitted to protect pile tips from damage during driving. Provide as indicated in Table 1.

3.1.2 Piles

Inspect piles when in the leads immediately before driving. Cut piles at specified cutoff elevation with pneumatic tools by sawing or other approved method. Where cutoff is below existing ground surface, complete excavation, sheeting, and dewatering, if elected, before pile is driven to cutoff elevation.

3.1.2.1 Driving Piles

When driving long piles of high slenderness ratio, special precautions shall be taken to ensure against overstressing and leading away from a plumb position. During driving, pile driving hammers shall be operated at all times at the rate and conditions recommended by the hammer manufacturer. Each pile shall be driven continuously and without interruption until the required depth of penetration and penetration rate per blow have been attained.

Piles shall be driven to the full penetration required where practicable to do so without damage to the piles. If found impracticable to drive any pile to the depth required, such pile shall be cut off and abandoned or pulled as directed. Driven piles which have a penetration of less than indicated and have not been driven to the established maximum penetration per blow are unsatisfactory. Driving of piles beyond the point of refusal defined as 5 blows per 1/4 inch or as indicated by excessive bonding of the hammer or kicking of the pile shall not be attempted. Piles which have uplifted after driving shall be be redriven to grade after conclusion of driving in that general area.

When the penetration per blow of any pile during the final blows exceeds that permitted or it is found that a pile is not of sufficient length to give the capacity specified, and the pile has been driven to its full length, the Contractor shall pull the pile and furnish and drive a longer pile or take other corrective measures as directed by the Contracting Officer. The use of followers or splices shall not be permitted except where specially authorized by the Contracting Officer.

After driving is completed, all piles shall be "headed" or cut off normal at the cutoff elevation. Headed treated piles, shall be given two heavy coats of preservative, followed by the application of a heavy coat of coal-tar pitch. Piles driven in locations where they are constantly subject to water spray shall be given this treatment immediately after they are cut off and before the cutoff surface has been wetted. Cutoffs shall become the property of the Contractor and shall be removed at no additional cost to the Government.

3.1.2.2 Test Piles

Provide 15 test piles conforming to the same requirements as specified for job piles. Contractor shall prepare and submit a Test Pile Plan indicating the location of the proposed test piles and the load testing schedule for the test pile. The plan shall include a minimum of two (2) representative test piles for each outfall facility, one (1) at a landside location and one (1) at a waterside location, for each accepted pile driving method, jetting, spudding, or predrilling (as approved by contracting office and the project design engineer).

Test piles shall be driven in the same manner as specified for job piles.

Record driving data as specified in paragraph entitled "Job Pile Driving Records." Confirmation of the assumed allowable working loads of single piles shall be made by static loading and measuring each test pile in the manner described below. Test piles indicated or directed to be driven in permanent locations may be incorporated into the work if, after satisfactory completion of the load test, they are approved for inclusion in the work by the Contracting Officer. Every facility shall be provided by the Contractor for the Contracting Officer to inspect and measure the deflection or settlement of the pile under test. Furnishing of measuring equipment and making measurements of deflection or settlement will be the responsibility of the Contractor.

3.1.2.3 Load Tests

Perform load tests on 15 test piles in accordance with ASTM D3689, Standard Test Methods for Deep Foundations Under Static Axial Tensile Load. Perform load tests at locations as directed. Provide testing and measuring equipment, perform loading, and provide observation facilities for a registered professional engineer employed by the Contractor to inspect and record settlement and deflection of piles under test loads. Do not mobilize load test equipment until directed. Loading frames and equipment shall be ready to place in operation as soon as a test pile has been driven. The maximum tension load to be applied during the test shall be 30 tons. The maximum test load shall be maintained for not less than 24 hours and then unloaded in accordance with ASTM D3689.

3.1.2.4 Tolerances in Driving Bearing Piles

Piles shall be accurately placed plumb and in the correct location both laterally and longitudinally. At the cutoff elevation, butts shall be within 4 inches laterally of the location indicated. Manipulation of piles is prohibited. A variation of not more than 0.25 inch per foot of pile length from plumb will be permitted. Redesign of pile caps or additional work required due to improper location of piles will be the responsibility of the Contractor. Inspect piles for heave. Piles shall be driven to the depths shown and capacities specified. Redrive heaved piles to the required tip elevation. Remove and replace with new piles those damaged, misplaced, driven below the design cutoff, or driven out of alignment, or provide additional piles, driven as directed at no additional cost to the

Government.

3.1.2.5 Job Piles Driving Records

A complete and accurate record of the driving of piles shall be compiled by the Contractor for submission to the Contracting Officer. Indicate pile location, deviations from design location, diameter, original length, installed length, ground surface, tip elevation, cutoff elevation, penetration in blows per foot for the full length of all job piles, hammer data including rate of operation, make, and size, and unusual pile behavior or circumstances experienced during driving such as redriving, heaving, weaving, obstructions, spudding, predrilling, and unanticipated interruptions. Make pile driving records available to the Contracting Officer at the job site, within 24 hours after each day of pile driving.

Include in the construction records the wood species, preservative type, retention, and producer of installed treated timber.

The elevation at the top of the pile shall be measured and recorded by a New Jersey Professional Licensed Surveyor after completion of driving.

3.1.2.6 Lengths of Job Piles

The Contractor shall determine the actual lengths of piles required to be driven below cutoff elevation for the various locations in the work. The Contractor shall determine the number of overlength piles, if any, to be ordered to provide for variations in subsurface conditions. The Contractor may drive as many indicator piles as he considers necessary at no additional cost to the Government. Contractor should understand that this would been done solely for Contractor's own information and to ascertain the approximate length required for each pile to reach the required bearing capacity. Indicator piles may be driven at the same location as required for the design piles as shown in the Contract Drawings, provided they satisfy the Contract requirements as to exact location, minimum embedment, bearing capacity, etc. as specified herein. Indicator piles that are not driven at the required locations and/or do not satisfy any other requirements as specified, shall be pulled out completely and disposed of properly off site at no additional cost to the Government. To provide for "heading" or cutting off normal after driving, piles shall be furnished in lengths at least one foot greater than the minimum lengths specified in paragraph 2.1.1, including Table 1.

3.1.2.7 Framing Treated Piles

Treated piles shall not be cut to permit fitting of timbers except as indicated or specified. Piles of uniform size shall be selected for each bent. If necessary, treated filler blocks shall be used to fill out between piles and bracing. Holes for drift bolts in the tops of piles shall be drilled to a depth of 3 inches less than the penetration of drift bolts in the piles. Drill holes for drift bolts 1/8 inch smaller than bolt diameter. Drill holes for through bolts 1/16 inch larger than diameter of bolt shank. Dap piles to receive straps where indicated. Holes drilled into piles shall be filled with and daps shall be coated with the same preservative used to treat the piles in accordance with AWPA M4. When holes are not used for bolts they shall be tightly closed by a treated plug.

Holes shall not be drilled or spikes shall not be driven into piles to support scaffolding.

3.1.3 Fastening

Use washers of the size and type specified under bolt heads and nuts which would otherwise come in contact with wood.

3.1.4 Pile Obstructions

The Contractor is solely responsible for the costs associated with drilling-through or relocating a pile when an obstruction is encountered.

All such costs shall be included in the Contractor's bid price.

3.1.4.1 Jetting of Piles

Water jets shall be permitted to assist in driving of the pile though strata which cannot be penetrated practicably by use of the hammer alone.

Discontinue jetting when the pile tip is approximately 5 feet or more above the indicated pile tip elevation. Jetting method and equipment shall be approved by the Contracting Officer prior to commencing jetting operations.

3.1.4.2 Spudding of Piles

Spudding will be permitted. Discontinue driving and withdraw the spudding mandrel approximately 5 feet or more above the indicated pile tip elevation. Drive pile the final 5 feet of penetration. Obtain Contracting Officer's approval of spudding equipment, prior to commencing spudding operations.

3.1.4.3 Predrilling of Piles

Predrilling will be permitted if it is demonstrated that the piles cannot be driven to the minimum pile elevation specified by driving only.

Discontinue predrilling when pile tip is approximately 5 feet or more above the indicated pile tip elevation. Drive pile the final 5 feet of penetration to the maximum penetration per blow established by the Contracting Officer. Obtain Contracting Officer's approval of predrilling equipment prior to commencing predrilling operations.

3.1.4.4 Auger Diameter for Predrilling

The maximum diameter of the auger permitted to be used for predrilling shall be 12 inches. The drilling rig used for augering shall be robust and capable of drill through hard stratum and boulders.

3.2 PROTECTION

3.2.1 Protection of Piles

Square the heads and tips of piles to the driving axis. Laterally support piles during driving, but do not unduly restrain piles from rotation in the leads. Swinging leads will not be permitted. Handle, protect, and field treat piles in accordance with AWPA M4.

3.2.1.1 Damaged Piles

Driving of piles shall not subject them to damage. Piles which are damaged, split, broomed, or broken by reason of internal defects or by improper driving below cutoff elevation so as to impair them for the purpose intended shall be removed and replaced; a second pile may be driven adjacent thereto at the Contractor's expense. Minor damaged areas of treated piles shall be brush-coated with creosote or the same preservative used to treat the piles.

3.2.1.2 On Site Application of Wood Preservatives

All on site application of wood preservatives must be performed by a person certified through an EPA approved training program for the application of wood treatment products in accordance with 40 CFR 171, regulated under 7 U.S.C.A. Sections 136 to 136y, Federal Insecticide, Fungicide, and Rodenticide Act (FIFRA). On site treatment shall also be in accordance with AWPA M4, Sections 1.5, 2.2, 2.3, and 3.1.

3.3 REJECTION OF PILES

3.3.1 Cause of Rejection

The following shall be causes for rejection of a pile:

a. Pile location or batter is incorrect.

b. Pile damaged from any cause whatsoever, except buried obstructions.

c. Pile is determined by the Contracting Officer to be unserviceable for other reasons related to the furnishing and installing of the pile.

d. Piles which are driven so that, when cut off, the tops are below the elevation fixed by the plans or as established by the Contracting Officer, shall be withdrawn and replaced by new and if necessary, longer piles.

e. Piles that are split, splintered or broomed from driving operations are not acceptable. Any pile broken by reason of internal defects (even though the Contracting Officer permitted it to be put in the leads) or by improper driving shall be rejected.

3.3.2 Corrective Measures

If piles are rejected by Contracting Officer for any other reason than damage due to buried obstructions, the damaged pile will be removed, properly disposed of, and a new pile will be reinstalled as directed herein at no additional cost to the Government. Furthermore, no additional payment will be made for:

a. Backfilling of cavities left by the extraction of rejected piles or from auger holes or soil deformations necessary to place pile.

b. Redriving piles that are forced up by any cause.

3.3.2.1 Correction of Deficiencies

a. Notify the Contracting Officer immediately, in writing, of the failure of a pile to meet any requirements specified herein. Include with such written notification all information required for the evaluation of remedial measures, including all information required for redesign.

b. If it is determined that a pile does not meet the requirements specified herein, perform all remedial work associated with the deficient pile, including changes to pile caps or driving and spudding any natural or manmade object or obstruction which does not permit the pile to be advanced with the approved pile driving hammer.

c. No work on the piles shall be done until the survey affecting the new piles has been analyzed and approval to proceed with the work is given by the Contracting Officer.

3.4 FIELD QUALITY CONTROL

3.4.1 Inspections

When Government inspections result in product rejection, the Contractor shall promptly segregate and remove rejected material from the premises.

The Government may also charge the Contractor an additional cost of inspection or test when prior rejection makes reinspection or retest necessary.

3.5 Vibration Monitoring

Pre-construction surveys and vibration monitoring shall be as per Section

02 01 51 VIBRATION MONITORING OF STRUCTURES.

3.6 Noise Monitoring

Noise monitoring shall be as per Section 00 73 00 SPECIAL CONTRACT

REQUIREMENTS.

-- End of Section --