W9128F25R0014 Amendment 07 - 04.01.2025.pdf

PDF 1 MB Posted

Attached to
CANCELED - USDA Dairy Forage Research Center (DFRC)
Solicitation number
W9128F25R0014
Issued by

About this file

This document is an Amendment (Amendment 07) to a federal solicitation for construction of the USDA Dairy Forage Research Center (DFRC) in Prairie du Sac, Wisconsin. The solicitation (W9128F25R0014) is for a design-bid-build construction project with an estimated value between $25 million and $100 million, issued by the U.S. Army Corps of Engineers Omaha District. Key amendments include removing the Project Labor Agreement requirement, updating proposal instructions and evaluation sections, deleting specific Contract Line Item Numbers (CLINs), incorporating updated wage determinations, and revising specifications and drawing sheets across multiple addenda.

The project involves constructing approximately 254,003 building gross square feet across 18 buildings on a 75-acre site, with most structures being pre-engineered metal buildings on concrete spread footings. The facility will support agricultural research, accommodating up to 452 lactating cows, 144 calves, 1,300 acres of crop production, and supporting 12 permanent researchers, 12 operations personnel, and 10 student researchers. The solicitation's response deadline is 27 May 2025 at 2:00 PM local time, with proposals to be submitted electronically to specified U.S. Army Corps of Engineers contracting personnel. The project will use a best value tradeoff source selection process with evaluation factors including past performance, key personnel, project management, schedule, and small business participation.

View the file

Other files

File Type Posted
W9128F25R0014 Amendment 16 - 09.09.2025.pdf PDF
W9128F25R0014 Amendment 15 - 07.22.2025.pdf PDF
Am_0015_Dwgs_ARS01.pdf PDF
W9128F25R0014 Conformed thru Amd 15 - 07.22.2025.pdf PDF
JA_CECT-NWO-25-15_DFRC_Calan Feeding System_Redacted.pdf PDF
W9128F25R0014 Conformed thru Amd 14 - 07.11.2025.pdf PDF
W9128F25R0014 Amendment 14 - 07.11.2025.pdf PDF
W9128F25R0014 Amendment 13 - 07.10.2025.pdf PDF
Am_0013_Specs_ARS01.pdf PDF
W9128F25R0014 Conformed thru Amd 13 - 07.10.2025.pdf PDF
Am_0013_Dwgs_ARS01.pdf PDF
Am_0012_Specs_ARS01.pdf PDF
Am_0012_Dwgs_ARS01.pdf PDF
W9128F25R0014 Amendment 12 - 06.16.2025.pdf PDF
W9128F25R0014 Conformed thru Amd 12 - 06.16.2025.pdf PDF
W9128F25R0014 Amendment 11 - 06.06.2025.pdf PDF
W9128F25R0014 Conformed thru Amd 11 - 06.06.2025.pdf PDF
Am_0011_Dwgs.pdf PDF
Am_0010_Specs.pdf PDF
W9128F25R0014 Conformed thru Amd 10 - 05.30.2025.pdf PDF
Am_0010_Dwgs.pdf PDF
W9128F25R0014 Amendment 10 - 05.30.2025.pdf PDF
W9128F25R0014 Conformed thru Amd 09 - 05.23.2025.pdf PDF
Am_0009_Dwgs_ARS01.pdf PDF
W9128F25R0014 Conformed thru Amd 09 - 05.23.2025.pdf PDF
W9128F25R0014 Amendment 09 - 05.23.2025.pdf PDF
Am_0009_Specs_ARS01.pdf PDF
Am_0008_Specs_ARS01.pdf PDF
Am_0008_Dwgs_ARS01.pdf PDF
W9128F25R0014 Amendment 08 - 05.16.2025.pdf PDF
Site Visit_24 Apr 2025_Sign in Sheet.jpg JPG image
W9128F25R0014 Conformed thru Amd 08 - 05.16.2025.pdf PDF
W9128F25R0014_Conformed Amd 07 - 04.01.2025.pdf PDF
Amendment 07 - Ad_0007_Drawings_04.01.2025.pdf PDF
Amendment 07 - Ad_0005_Drawings_04.01.2025.pdf PDF
Amendment 07 - Ad_0006_Drawings_04.01.2025.pdf PDF
Amendment 07 - Ad_0011_Drawings_04.01.2025.pdf PDF
Amendment 07 - Ad_0008_Drawings_04.01.2025.pdf PDF
Amendment 07_Specifications_04.01.2025.pdf PDF
Amendment 07 - Ad_0003_Drawings_04.01.2025.pdf PDF
W9128F25R0014_CONFORMED THROUGH Amd 07 - 04.01.2025.pdf PDF
Amendment 07 - Ad_0010_Drawings_04.01.2025.pdf PDF
Amendment 07 - Ad_0009_Drawings_04.01.2025.pdf PDF
Amendment 07 - Ad_0002_Drawings_04.01.2025.pdf PDF
Amendment 07 - Ad_0004_Drawings_04.01.2025.pdf PDF
W9128F25R0014-0006_Dairy Forage_02.14.2025.pdf PDF
W9128F25R0014 - Amendment 0005 - 20250114.pdf PDF
Site Visit Sign in Sheet.pdf PDF
W9128F25R0014 - Amendment 0004 - 20241223.pdf PDF
Am_0004_Specs_Div 01.pdf PDF
Show 40 more

Latest 50 of 94 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9128F25R0014

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is as follow s: 1. Remove the requirement for Project Labor Agreement(s) (PLA). 2. Update Sections 00 21 00 and 00 22 00 for the proposal instructions and evalation. 3. Delete CLINs 0020 and 0027. The proposal shall not included pricing for these tw o CLINs. 4. Update/add/remove clauses to comply w ith Executive Order(s). 5. Incorporate the udpated w age determinations WI20250011 and WI202500015. 6. Incorporate revised specif ications and draw ing sheets as identified in the continuation page. These specif ications and draw ing sheet display changes that are incorporated into the solicitation and proposal.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 117

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Apr-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9128F25R0014

X 9B. DATED (SEE ITEM 11)

22-Nov-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Apr-2025

CODE

U.S. ARMY CORPS OF ENGINEERS, OMAHA DIST

CONTRACTING OFFICE

1616 CAPITOL AVENUE

OMAHA NE 68102-4901

W9128F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMD 7 - SUMMARY OF CHANGES

01 APR 2025

Solicitation No. W9128F25R0014

Date of Issue: 22 NOV 2024 [New] Date of Receiving Proposals: 27 MAY 2025

SUBJECT: Amendment No. 0007 to Request for Proposal Solicitation Package for Construction of

USDA DAIRY FORAGE RESEARCH CENTER

TO: Prospective Offerors and Others Concerned

1. The specifications and drawings for subject project are hereby modified as follows (revise all specification indices, attachment lists, and drawing indices accordingly).

a. Specifications (New and/or Revised and Reissued). Delete and substitute or add specification pages or sections as noted below. The substituted pages or sections are revised and reissued with this amendment.

For convenience, on the revised specification pages, changes have been identified by “[*Am-7]”(underlining of added text and/or strikeout of deleted text).

Pages or Sections Deleted Pages or Sections Substituted or Added

DIVISION 00 DIVISION 00*

00 01 15 00 01 15* 01 31 12 01 31 12* 01 45 00 01 45 00* 01 91 00.15 10 01 91 00.15 10*

01 91 00.15 10AT2-BASIS OF DESIGN 01 91 00.15 10 – COMMISSIONING PLAN

07 42 13 07 42 13* 07 61 14.00 20 07 61 14.00 20* 08 11 13 08 11 13* 09 29 00 09 29 00* 09 30 10 09 30 10* 09 62 00 09 62 00* 10 14 00.10 10 14 00.10*

10 14 00.10AT 10 14 00.10AT*

10 88 00 10 88 00* 11 92 16 11 92 16* 11 92 25 11 92 25* 11 92 79 11 92 79* 12 36 00 12 36 00* 13 21 00 13 21 00*

13 21 10 13 21 10* 22 30 00 22 30 00* 26 05 00.00 40 26 05 00.00 40* 26 20 00 26 20 00* 27 13 23.00 40 27 13 23.00 40* 27 21 10.00 40 27 21 10.00 40* 27 22 42 27 22 42* 28 10 05 28 10 05*

28 10 05AT 28 10 05AT*

41 12 00 41 12 00* 41 14 00 41 14 00* 41 52 00 41 52 00* ** ** ** Final Environmental Assessment ** ** ** G3_Site-NaturalGasLoads ** ** ** G-4-P10_NaturalGasLoads

b. Drawings (Reissued). The following drawings are revised with latest revision date indicated on each sheet and reissued with this amendment.

ADDENDUM 2

(1) Sheet A-340-A, STANDARD EXTERIOR WALL TYPES - AREA A - LAB & ADMIN

(2) Sheet A-350-A, WALL SECTIONS - AREA A - LAB & ADMIN

(3) Sheet A-351-A, WALL SECTIONS - AREA A - LAB & ADMIN

(4) Sheet A-352-A, WALL SECTIONS - AREA A - LAB & ADMIN

(5) Sheet A-353-A, WALL SECTIONS - AREA A - LAB & ADMIN

(6) Sheet A-510-A, WALL DETAILS - AREA A - LAB & ADMIN

(7) Sheet I-001-A, INTERIOR NOTES AND FINISH LEGEND - AREA A - LAB &

ADMIN

(8) Sheet I-101-A, INTERIOR FINISH PLAN - FIRST FLOOR - AREA A - LAB

& ADMIN

(9) Sheet A-700-A, STANDARD PARTITION TYPES - AREA A - LAB & ADMIN

ADDENDUM 3

(1) Sheet Q-401-A, FLOOR PLAN - FIRST FLOOR - ENLARGED - AREA A - LAB &

ADMIN

(2) Sheet Q-503-A, LABORATORY CTR SCHEDULE & DETAILS - AREA A - LAB & ADMIN

(3) Sheet ES-101, ELECTRICAL SITE PLAN

(4) Sheet ES-103, BADGER WELL 5 0 WELL PUMP DIAGRAM AND FIRE PUMP HOUSE

SCHEDULES

(5) Sheet FA-001-A, FIRE ALARM ABBREVIATIONS, SYMBOLS, AND NOTES - AREA A

(6) Sheet FA-001-B, FIRE ALARM ABBREVIATIONS, SYMBOLS, AND NOTES - AREA B

ADDENDUM 4

(1) Sheet A-101-A, FIRST FLOOR PLAN - AREA A - LAB & ADMIN

(2) Sheet A-700-A, STANDARD PARTITION TYPES - AREA A - LAB & ADMIN

(3) Sheet A-103-B6, ARCHITECTURAL AREA PLAN-CENTER - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(4) Sheet A-105-A, FIRST FLOOR REFLECTED CEILING PLAN - AREA A - LAB &

ADMIN

(5) Sheet A-301-B5, BUILDING CROSS SECTIONS - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(6) Sheet S-105-B5, STRUCTURAL CONCRETE AREA PLAN - WEST - AREA B5 -

SPECIAL NEEDS AND MATERNITY

(7) Sheet S-106-B5, STRUCTURAL CONCRETE AREA PLAN - EAST - AREA B5 -

SPECIAL NEEDS AND MATERNITY

(8) Sheet A-611-A, INTERIOR FRAME DETAILS - AREA A - LAB & ADMIN

(9) Sheet E-101-B14, FIRST FLOOR ELECTRICAL PLAN - AREA B14 - FUEL STORAGE

(10) Sheet E-102-B2, ELECTRICAL LIGHTING SECTION - AREA B2 - ADVANCED ANIMAL

NUTRITION

(11) Sheet E-102-B7, ELECTRICAL LIGHTING PLAN - AREA B7 - CALF BARN

(12) Sheet E-501-B1, ELECTRICAL DETAILS - AREA B1 - AIR EMISSIONS

(13) Sheet E-601-B2, ELECTRICAL SCHEDULES - AREA B2 - ADVANCED ANIMAL

NUTRITION

(14) Sheet E-601-B3, ELECTRICAL SCHEDULES - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(15) Sheet E-602-B3, ELECTRICAL DIAGRAMS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(16) Sheet E-601-B14, ELECTRICAL SCHEDULES - AREA B14 - FUEL STORAGE

(17) Sheet I-001-A, INTERIOR NOTES AND FINISH LEGEND - AREA A - LAB & ADMIN

(18) Sheet M-501-B3, MECHANICAL SCHEDULES AND DETAILS - AREA B3 -

CONVENTIONAL FREESTALL & DRY COW

(19) Sheet M-601-B6, MECHANICAL SCHEDULES - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(20) Sheet Q-102-B3, EQUIPMENT FLOOR PLAN - WEST - AREA B3 - CONVENTIONAL

FREESTALL AREA & DRY COW

(21) Sheet Q-103-B3, EQUIPMENT FLOOR PLAN - MIDDLE - AREA B3 - CONVENTIONAL

FREESTALL AREA & DRY COW

(22) Sheet Q-104-B3, EQUIPMENT FLOOR PLAN - EAST - AREA B3 - CONVENTIONAL

FREESTALL AREA & DRY COW

(23) Sheet Q-102-B4, EQUIPMENT FLOOR PLAN-WEST - AREA B4 - MILKING PARLOR

(24) Sheet Q-102-B7, EQUIPMENT FLOOR PLAN - WEST - AREA B7 - CALF BARN

(25) Sheet Q-501-B6, EQUIPMENT DETAILS - AREA B6 - ROBOTIC MILKING FREESTALL

AREA

(26) Sheet Q-502-B3, EQUIPMENT DETAILS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

ADDENDUM 5

(1) Sheet A-531-A, EXTERIOR WINDOW AND LOUVER DETAILS - AREA A - LAB &

ADMIN

(2) Sheet A-532-A, EXTERIOR WINDOW AND LOUVER DETAILS - AREA A - LAB &

ADMIN

(3) Sheet EL-501-A, ELECTRICAL LIGHTING SCHEDULE - AREA A - LAB & ADMIN -

PART 1

(4) Sheet EL-502-A, ELECTRICAL LIGHTING SCHEDULE - AREA A - LAB & ADMIN -

PART 2

(5) Sheet EL-611-A, LIGHTING CONTROL RISERS AND DETAILS - AREA A - LAB &

ADMIN

(6) Sheet EL-612-A, LIGHTING CONTROL RISERS AND DETAILS - AREA A - LAB &

ADMIN

(7) Sheet EL-820-A, LIGHTING FIXTURE PLATES - AREA A - LAB & ADMIN

(8) Sheet EL-821-A, LIGHTING FIXTURE PLATES - AREA A - LAB & ADMIN

(9) Sheet EL-822-A, LIGHTING FIXTURE PLATES - AREA A - LAB & ADMIN

(10) Sheet Q-101-B9, EQUIPMENT PLAN - AREA B9 - FEED MIXING CENTER

(11) Sheet Q-301-B9, EQUIPMENT SECTIONS - AREA B9 - FEED MIXING CENTER

(12) Sheet Q-302-B9, EQUIPMENT SECTIONS - AREA B9 - FEED MIXING CENTER

(13) Sheet E-101-B9, FIRST FLOOR ELECTRICAL PLAN - AREA B9 - FEED MIXING

CENTER

(14) Sheet Q-501-B4, EQUIPMENT SCHEDULE AND DETAILS - AREA B4 - MILKING

PARLOR

(15) Sheet Q-503-A, LABORATORY CTR SCHEDULE & DETAILS - AREA A - LAB & ADMIN

(16) Sheet Q-601-B5, EQUIPMENT SCHEDULES - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(17) Sheet S-501-B6, STRUCTURAL DETAILS - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(18) Sheet A-301-B3, BUILDING CROSS SECTIONS - AREA B3 - CONVENTIONAL

FREESTALL AREA & DRY COW

(19) Sheet A-340-A, STANDARD EXTERIOR WALL TYPES - AREA A - LAB & ADMIN

(20) Sheet A-530-A, EXTERIOR WINDOW, LOUVER AND CURTAIN WALL TYPES - AREA A

- LAB & ADMIN

ADDENDUM 6

(1) Sheet A-101-B9, FIRST FLOOR PLAN - AREA B9 - FEED MIXING CENTER

(2) Sheet A-101-B11, ARCHITECTURAL FLOOR PLAN - AREA B11 - MACHINE STORAGE

& SHOP & PESTICIDE

(3) Sheet A-102-B4, ARCHITECTURAL AREA PLAN - WEST - AREA B4 - MILKING

PARLOR

(4) Sheet A-201-B8, ELEVATIONS - AREA B8 – AGRONOMY

(5) Sheet A-203-B7, INTERIOR ELEVATIONS - AREA B7 - CALF BARN

(6) Sheet A-301-B8, BUILDING CROSS SECTION - AREA B8 – AGRONOMY

(7) Sheet E-601-B7, ELECTRICAL SCHEDULES - AREA B7 - CALF BARN

(8) Sheet E-601-C2, ELECTRICAL DIAGRAMS - AREA C2 - SOLID STACK BUILDING

(9) Sheet E-101-C3, C3 POWER PLAN

(10) Sheet E-601-C3, C3 ONE-LINE DIAGRAM & SCHEDULES

(11) Sheet P-101-B6, PLUMBING PLAN - AREA B6 - ROBOTIC MILKING FREESTALL

AREA

(12) Sheet P-601-B8, PLUMBING SCHEDULES - AREA B8 – AGRONOMY

(13) Sheet A-101-B2, ARCHITECTURAL FLOOR PLAN - AREA B2 - ADVANCED ANIMAL

NUTRITION

(14) Sheet A-501-B2, DETAILS - AREA B2 - ADVANCED ANIMAL NUTRITION

(15) Sheet A-601-B1, DOOR SCHEDULE AND DETAILS - AREA B1 - AIR EMISSIONS

(16) Sheet A-601-B4, DOOR AND WINDOW SCHEDULES - AREA B4 - MILKING PARLOR

(17) Sheet A-601-B6, DOOR AND WINDOW SCHEDULES - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(18) Sheet A-601-B7, DOOR SCHEDULE AND DETAILS - AREA B7 - CALF BARN

(19) Sheet A-601-B8, DOOR AND WINDOW SCHEDULES - AREA B8 – AGRONOMY

(20) Sheet A-601-B9, DOOR SCHEDULE AND DETAILS - AREA B9 - FEED MIXING

CENTER

(21) Sheet A-601-B11, DOOR AND WINDOW SCHEDULES - AREA B11 - MACHINE STORAGE

& SHOP & PESTICIDE

(22) Sheet A-601-B12.1, DOOR AND WINDOW SCHEDULES - AREA B12.1 – CONNECTOR

(23) Sheet A-601-B13, DOOR AND WINDOW SCHEDULES - AREA B13 - MILK HOUSE

(24) Sheet A-602-B1, DOOR DETAILS - AREA B1 - AIR EMISSIONS

(25) Sheet A-603-B2, DOOR SCHEDULE AND DETAILS - AREA B2 - ADVANCED ANIMAL

NUTRITION

(26) Sheet A-603-B3, DOOR SCHEDULE AND DETAILS - AREA B3 - CONVENTIONAL

FREESTALL AREA & DRY COW

(27) Sheet E-102-B11, ELECTRICAL POWER PLAN - NORTH - AREA B11 - MACHINE

STORAGE & SHOP & PESTICIDE

(28) Sheet A-101-B7, ARCHITECTURAL FLOOR PLAN - AREA B7 - CALF BARN

(29) Sheet A-101-B12.1, ARCHITECTURAL FLOOR PLAN - AREA B12.1 – CONNECTOR

(30) Sheet Q-103-B6, EQUIPMENT FLOOR PLAN - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(31) Sheet Q-603-B6, EQUIPMENT SCHEDULES AND DETAILS - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(32) Sheet A-101-B8, ARCHITECTURAL FLOOR PLAN - AREA B8 – AGRONOMY

(33) Sheet A-302-B8, BUILDING LONGITUDINAL CROSS SECTION - AREA B8 -

AGRONOMY

ADDENDUM 7

(1) Sheet A-102-B4, ARCHITECTURAL AREA PLAN-WEST - AREA B4 - MILKING PARLOR

(2) Sheet A-310-B7, WALL SECTIONS - AREA B7 - CALF BARN

(3) Sheet A-401-B7, ENLARGED FLOOR PLANS - AREA B7 - CALF BARN

(4) Sheet A-102-B11, ARCHITECTURAL AREA PLAN-NORTH - AREA B11 - MACHINE

STORAGE & SHOP & PESTICIDE

(5) Sheet A-301-B4, BUILDING CROSS SECTIONS - AREA B4 - MILKING PARLOR

(6) Sheet A-301-B7, BUILDING CROSS SECTIONS - AREA B7 - CALF BARN

(7) Sheet A-301-B11, BUILDING CROSS SECTION - AREA B11 - MACHINE STORAGE &

SHOP & PESTICIDE

(8) Sheet A-302-B4, BUILDING LONGITUDINAL CROSS SECTIONS - AREA B4 -

MILKING PARLOR

(9) Sheet A-302-B5, BUILDING LONGITUDINAL CROSS SECTIONS - AREA B5 -

SPECIAL NEEDS AND MATERNITY

(10) Sheet A-303-B6, BUILDING CROSS SECTION-CENTER - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(11) Sheet S-301-B3, FOUNDATION SECTIONS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(12) Sheet S-301-B4, FOUNDATION SECTIONS - AREA B4 - MILKING PARLOR

(13) Sheet S-301-B5, FOUNDATION SECTIONS - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(14) Sheet S-301-B6, FOUNDATION SECTIONS - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(15) Sheet S-301-B7, FOUNDATION SECTIONS - AREA B7 - CALF BARN

(16) Sheet S-301-B8, FOUNDATION SECTIONS - AREA B8 – AGRONOMY

(17) Sheet S-301-B11, FOUNDATION SECTIONS - AREA B11 - MACHINE STORAGE &

SHOP & PESTICIDE

(18) Sheet S-301-B12.1, FOUNDATION SECTIONS - AREA B12.1 – CONNECTOR

(19) Sheet S-301-B12.2, FOUNDATION SECTIONS - AREA B12.2 - CONNECTOR AND

SORTING

(20) Sheet S-301-B13, FOUNDATION SECTIONS - AREA B13 - MILK HOUSE

(21) Sheet S-301-B14, FOUNDATION SECTIONS - AREA B14 - FUEL STORAGE

(22) Sheet S-302-B4, FOUNDATION SECTIONS - AREA B4 - MILKING PARLOR

(23) Sheet S-302-B5, FOUNDATION SECTIONS-LONGITUDINAL - AREA B5 - SPECIAL

NEEDS AND MATERNITY

(24) Sheet S-302-B6, FOUNDATION SECTIONS - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(25) Sheet S-302-B12.1, FOUNDATION SECTIONS-LONGITUDINAL - AREA B12.1 –

CONNECTOR

(26) Sheet S-302-B13, FOUNDATION SECTIONS-LONGITUDINAL - AREA B13 - MILK

HOUSE

(27) Sheet S-303-B4, FOUNDATION SECTIONS-LONGITUDINAL - AREA B4 - MILKING

PARLOR

(28) Sheet S-303-B6, FOUNDATION SECTIONS - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(29) Sheet S-501-B2, STRUCTRUAL DETAILS - AREA B2 - ADVANCED ANIMAL

NUTRITION

(30) Sheet S-502-B3, STRUCTURAL DETAILS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(31) Sheet S-502-B4, STRUCTURAL DETAILS - AREA B4 - MILKING PARLOR

(32) Sheet S-503-B3, STRUCTURAL DETAILS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(33) Sheet P-501-B1, PLUMBING DETAILS - AREA B1 - AIR EMISSIONS

(34) Sheet P-601-B1, PLUMBING SCHEDULES - AREA B1 - AIR EMISSIONS

(35) Sheet A-310-B12.1, WALL SECTIONS - AREA 12.1 – CONNECTOR

(36) Sheet A-501-B8, DETAILS - AREA B8 – AGRONOMY

(37) Sheet A-502-B8, DETAILS - AREA B8 – AGRONOMY

(38) Sheet E-101-B9, FIRST FLOOR ELECTRICAL PLAN - AREA B9 - FEED MIXING

CENTER

(39) Sheet Q-101-B9, EQUIPMENT PLAN - AREA B9 - FEED MIXING CENTER

(40) Sheet S-103-B9, SCALE DETAILS - AREA B9 - FEED MIXING AREA

(41) Sheet S-107-B3, STRUCTURAL CONCRETE PLAN - MIDDLE - AREA B3

- CONVENTIONAL FREESTALL AREA & DRY COW

(42) Sheet S-301-B3, FOUNDATION SECTIONS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

ADDENDUM 8

(1) Sheet Q-501-B7, EQUIPMENT DETAILS - AREA B7 - CALF BARN

(2) Sheet Q-601-B7, EQUIPMENT SCHEDULES - AREA B7 - CALF BARN

(3) Sheet Q-602-B7, EQUIPMENT DETAILS - AREA B7 - CALF BARN

(4) Sheet E-501-B9, LIGHTING SCHEDULE AND DETAILS - AREA B9 - FEED MIXING

CENTER

(5) Sheet E-601-B9, ONE LINE DIAGRAM AND PANEL SCHEDULES - AREA B9 - FEED

MIXING CENTER

(6) Sheet Q-601-B1, EQUIPMENT SCHEDULES - AREA B1 - AIR EMISSIONS

(7) Sheet Q-501-B2, EQIUIPMENT DETAILS - AREA B2 - ADVANCED ANIMAL

NUTRITION

(8) Sheet Q-501-B2, EQIUIPMENT DETAILS - AREA B2 - ADVANCED ANIMAL

NUTRITION

(9) Sheet Q-603-B3, EQUIPMENT SCHEDULES - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(10) Sheet Q-501-B4, EQUIPMENT SCHEDULE AND DETAILS - AREA B4 - MILKING

PARLOR

(11) Sheet Q-501-B5, EQUIPMENT DETAILS - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(12) Sheet Q-601-B6, GATE SCHEDULE AND DETAILS - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(13) Sheet Q-602-B6, GATE DETAILS - AREA B6 - ROBOTIC MILKING FREESTALL AREA

(14) Sheet Q-601-B12.2, EQUIPMENT SCHEDULE AND DETAILS - AREA B12.2 -

CONNECTOR AND SORTING

(15) Sheet E-102-B5, ELECTRICAL POWER PLAN-WEST - AREA B5 - SPECIAL NEEDS

AND MATERNITY

(16) Sheet E-601-B5, ELECTRICAL SCHEDULES - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(17) Sheet M-601-B5, MECHANICAL SCHEDULES - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(18) Sheet E-102-B5, ELECTRICAL POWER PLAN-WEST - AREA B5 - SPECIAL NEEDS

AND MATERNITY

(19) Sheet E-103-B5, ELECTRICAL POWER PLAN-EAST - AREA B5 - SPECIAL NEEDS

AND MATERNITY

(20) Sheet E-102-B2, ELECTRICAL LIGHTING SECTION - AREA B2 - ADVANCED ANIMAL

NUTRITION

(21) Sheet E-102-B3, ELECTRICAL LIGHTING PLAN - AREA B3 - CONVENTIONAL

FREESTALL

(22) Sheet E-102-B7, ELECTRICAL LIGHTING PLAN - AREA B7 - CALF BARN

(23) Sheet E-105-B5, ELECTRICAL LIGHTING PLAN-WEST - AREA B5 - SPECIAL NEEDS

AND MATERNITY

(24) Sheet E-106-B5, ELECTRICAL LIGHTING PLAN-EAST - AREA B5 - SPECIAL NEEDS

AND MATERNITY

(25) Sheet E-106-B6, ELECTRICAL LIGHTING PLAN-WEST - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(26) Sheet E-107-B6, ELECTRICAL LIGHTING PLAN-CENTER - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(27) Sheet E-108-B6, ELECTRICAL LIGHTING PLAN-EAST - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(28) Sheet E-601-B1, ELECTRICAL SCHEDULES - AREA B1 - AIR EMISSIONS

(29) Sheet E-601-B2, ELECTRICAL SCHEDULES - AREA B2 - ADVANCED ANIMAL

NUTRITION

(30) Sheet E-601-B3, ELECTRICAL SCHEDULES - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(31) Sheet E-601-B5, ELECTRICAL SCHEDULES - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(32) Sheet E-601-B7, ELECTRICAL SCHEDULES - AREA B7 - CALF BARN

(33) Sheet E-501-B9, LIGHTING SCHEDULE AND DETAILS - AREA B9 - FEED MIXING

CENTER

(34) Sheet E-601-B9, ONE LINE DIAGRAM AND PANEL SCHEDULES - AREA B9 - FEED

MIXING CENTER

(35) Sheet E-601-B14, ELECTRICAL SCHEDULES - AREA B14 - FUEL STORAGE

ADDENDUM 9

(1) Sheet A-301-B4, BUILDING CROSS SECTIONS - AREA B4 - MILKING PARLOR

(2) Sheet E-601-B2, ELECTRICAL SCHEDULES - AREA B2 - ADVANCED ANIMAL

NUTRITION

(3) Sheet E-601-B3, ELECTRICAL SCHEDULES - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(4) Sheet E-603-B4, ELECTRICAL SCHEDULES - AREA B4 - MILKING PARLOR

(5) Sheet I-101-B4, ROOM FINISH SCHEDULE - AREA B4 - MILKING PARLOR

(6) Sheet P-101-B2, SANITARY PLUMBING PLAN - AREA B2 - ADVANCED ANIMAL

NUTRITION

(7) Sheet Q-302-B9, EQUIPMENT SECTIONS - AREA B9 - FEED MIXING CENTER

(8) Sheet Q-601-B3, EQUIPMENT SCHEDULES - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(9) Sheet S-501-B8, STRUCTURAL DETAILS - AREA B8 – AGRONOMY

(10) Sheet S-503-B3, STRUCTURAL DETAILS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(11) Sheet S-102-B12.1, STRUCTURAL CONCRETE PLAN - AREA B12.1 – CONNECTOR

(12) Sheet S-501-B12.1, STRUCTURAL DETAILS - AREA B12.1 – CONNECTOR

(13) Sheet S-102-B13, STRUCTURAL CONCRETE PLAN - AREA B13 - MILK HOUSE

(14) Sheet S-501-B13, STRUCTURAL DETAILS - AREA B13 - MILK HOUSE

(15) Sheet P-101-B13, SANITARY PLUMBING PLAN - AREA B13 - MILK HOUSE

(16) Sheet P-501-B13, PLUMBING DETAILS - AREA B13 - MILK HOUSE

(17) Sheet P-601-B13, PLUMBING SCHEDULES - AREA B13 - MILK HOUSE

(18) Sheet E-101-B13, ELECTRICAL POWER PLAN - AREA B13 - MILK HOUSE

(19) Sheet S-101-B8, STRUCTURAL FOUNDATION PLAN - AREA B8 – AGRONOMY

(20) Sheet S-102-B8, STRUCTURAL CONCRETE PLAN - AREA B8 – AGRONOMY

(21) Sheet S-301-B8, FOUNDATION SECTIONS - AREA B8 - AGRONOMY

ADDENDUM 10

(1) Sheet A-101-B8, ARCHITECTUAL FLOOR PLAN - AREA B8 – AGRONOMY

(2) Sheet A-301-B1, BUILDING CROSS SECTIONS - AREA B1 - AIR EMISSIONS

(3) Sheet C-103, SITE LAYOUT PLAN

(4) Sheet C-104, UTILITY PLAN

(5) Sheet C-105, SITE ROAD PLAN SHEET 1

(6) Sheet C-106, SITE ROAD PLAN SHEET 2

(7) Sheet C-107, SITE ROAD PLAN SHEET 3

(8) Sheet C-108, SITE ROAD PLAN SHEET 4

(9) Sheet C-109, PARKING LOT SITE PLAN

(10) Sheet C-301, WATER DISTRIBUTION AND SEWAGE COLLECTION SYSTEMS

(11) Sheet C-303, WATER MAINS

(12) Sheet C-313, PLAN & PROFILE SHEET 7 BLUFFVIEW SUPPLY

(13) Sheet C-315, PLAN & PROFILE BADGER WELL 5 SUPPLY

(14) Sheet C-316, PLAN & PROFILE SHEET 1 BADGER 5 MAIN

(15) Sheet C-317, PLAN & PROFILE SHEET 2 BADGER 5 MAIN

(16) Sheet C-318, PLAN & PROFILE SHEET 3 BADGER 5 MAIN

(17) Sheet C-319, PLAN & PROFILE SHEET 4 BADGER 5 MAIN

(18) Sheet C-320, PLAN & PROFILE SHEET 5 BADGER 5 MAIN

(19) Sheet C-321, PLAN & PROFILE BAADGER 5 MAIN – AGRON

(20) Sheet C-322, PLAN & PROFILE BADGER 5 SERVICE - B13

(21) Sheet C-323, PLAN & PROFILE BADGER 5 SERVICE - B4 - C2

(22) Sheet C-324, PLAN & PROFILE BADGER 5 SERVICE - B9 - B11

(23) Sheet C-325, PLAN & PROFILE SHEET 1 SAN MAIN

(24) Sheet C-326, PLAN & PROFILE SHEET 2 SAN MAIN

(25) Sheet C-327, PLAN & PROFILE SHEET 3 SAN MAIN

(26) Sheet C-352, PLAN & PROFILE SHEET 1 FLUME PIPE

(27) Sheet C-353, PLAN & PROFILE SHEET 2 FLUME PIPE

(28) Sheet C-354, PLAN & PROFILE SHEET 3 FLUME PIPE

(29) Sheet C-355, PLAN & PROFILE FEED STORAGE AREA GRAVITY PIPE

(30) Sheet C-356, PLAN & PROFILE C2 GRAVITY PIPE

(31) Sheet C-357, PLAN & PROFILE C1 FORCE MAIN SHEET 1

(32) Sheet C-358, PLAN & PROFILE C1 FORCE MAIN SHEET 2

(33) Sheet C-359, PLAN & PROFILE C3 FORCE MAIN

(34) Sheet C-360, PLAN & PROFILE B4 FORCE MAIN

(35) Sheet C-361, PLAN & PROFILE B7 GRAVITY MANURE PIPE

(36) Sheet C-362, PLAN & PROFILE B11 GRAVITY MANURE PIPE

(37) Sheet C-400, STORMWATER DRAINAGE PLAN - SHEET 1

(38) Sheet C-402, STORMWATER DRAINAGE PLAN - SHEET 3

(39) Sheet C-405, STORMWATER AND EROSION SEDIMENT CONTROL PLAN

(40) Sheet C-409, PLAN & PROFILE SHEET STORM DRAIN

(41) Sheet C-410, PLAN & PROFILE SD2

(42) Sheet C-411, PLAN & PROFILE STORM DRAIN 3

(43) Sheet C-412, PLAN & PROFILE STORM DRAIN 3

(44) Sheet C-413, PLAN & PROFILE STORM DRAIN 5 FORCEMAIN

(45) Sheet C-414, PLAN & PROFILE STORM DRAIN 5

(46) Sheet C-415, PLAN & PROFILE STORM DRAIN 6

(47) Sheet C-416, PLAN & PROFILE STORM DRAIN 7

(48) Sheet C-417, PLAN & PROFILE STORM DRAIN 8

(49) Sheet C-418, PLAN & PROFILE STORM DRAINS 11

(50) Sheet C-419, PLAN & PROFILE CULVERT 1-2

(51) Sheet C-420, PLAN & PROFILE CULVER 4 & 7

(52) Sheet C-421, PLAN & PROFILE CULVERT 5-6

(53) Sheet C-422, PLAN & PROFILE STORM DRAIN 14-15

(54) Sheet C-423, PLAN & PROFILE SHEET SD4, RT13 & CP9

(55) Sheet C-426, PLAN & PROFILE CULVER 15-16

(56) Sheet C-427, PLAN & PROFILE CULVERT 17 – 18

(57) Sheet C-428, PLAN & PROFILE CULVERT 19 – 20

(58) Sheet C-429, PLAN & PROFILE ROCK TRENCH DRAINS 1-2

(59) Sheet C-430, PLAN & PROFILE ROCK TRENCH DRAINS 3-4-C-430

(60) Sheet C-431, PLAN & PROFILE ROCK TRENCH DRAINS 5

(61) Sheet C-432, PLAN & PROFILE ROCK TRENCH DRAINS 6

(62) Sheet C-433, PLAN & PROFILE ROCK TRENCH DRAINS 9

(63) Sheet C-435, PLAN & PROFILE ROCK TRENCH DRAINS 11-12

(64) Sheet C-436, PLAN & PROFILE EXISTING CULVERT 1

(65) Sheet C-437, PLAN & PROFILE SHEET 1 WEST STORMWATER SPILLWAY

(66) Sheet C-438, PLAN & PROFILE SHEET 2 WEST STORMWATER SPILLWAY

(67) Sheet C-523, GENERATOR PAD DETAILS

(68) Sheet E-101-C3, C3 POWER PLAN

(69) Sheet E-601-C3, C3 ONE-LINE DIAGRAM & SCHEDULES

(70) Sheet E-501-B8, ELECTRICAL DETAILS - AREA B8 – AGRONOMY

(71) Sheet E-502-B6, LIGHTING SCHEDULE AND DETAILS - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(72) Sheet E-601-A, ELECTRICAL SINGLE LINE DIAGRAM - AREA A -LAB & ADMIN

(73) Sheet E-601-B1, ELECTRICAL SCHEDULES - AREA B1 - AIR EMISSIONS

(74) Sheet E-601-B11, ELECTRICAL SCHEDULES AND DETAILS - AREA B11 - MACHINE

STORAGE & SHOP & PESTICIDE

(75) Sheet E-601-B13, ELECTRICAL SCHEDULES - AREA B13 - MILK HOUSE

(76) Sheet E-601-B2, ELECTRICAL SCHEDULES - AREA B2 - ADVANCED ANIMAL

NUTRITION

(77) Sheet E-601-B3, ELECTRICAL SCHEDULES - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(78) Sheet E-601-B4, ELECTRICAL SCHEDULES - AREA B4 - MILKING PARLOR

(79) Sheet E-601-B5, ELECTRICAL SCHEDULES - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(80) Sheet E-601-B6, ELECTRICAL SCHEDULES - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(81) Sheet E-601-B7, ELECTRICAL SCHEDULES - AREA B7 - CALF BARN

(82) Sheet E-601-B8, ELECTRICAL SCHEDULES - AREA B8 – AGRONOMY

(83) Sheet E-601-B9, ONE LINE DIAGRAM AND PANEL SCHEDULES - AREA B9 - FEED

MIXING CENTER

(84) Sheet E-602-B1, ELECTRICAL SCHEDULES - AREA B1 - AIR EMISSIONS

(85) Sheet E-602-B11, ELECTRICAL SCHEDULES AND DETAILS - AREA B11 - MACHINE

STORAGE & SHOP & PESTICIDE

(86) Sheet E-602-B13, ELECTRICAL DIAGRAMS - AREA B13 - MILK HOUSE

(87) Sheet E-602-B3, ELECTRICAL DIAGRAMS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(88) Sheet E-602-B3, ELECTRICAL DIAGRAMS - AREA B3 - CONVENTIONAL FREESTALL

AREA & DRY COW

(89) Sheet E-602-B4, ELECTRICAL DIAGRAMS - AREA B4 - MILKING PARLOR

(90) Sheet E-602-B5, ELECTRICAL DIAGRAMS - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(91) Sheet E-602-B6, ELECTRICAL SCHEDULES - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(92) Sheet E-602-B7, ELECTRICAL DIAGRAMS - AREA B7 - CALF BARN

(93) Sheet E-603-B1, ELECTRICAL DIAGRAMS - AREA B1 - AIR EMISSIONS

(94) Sheet E-603-B4, ELECTRICAL SCHEDULES - AREA B4 - MILKING PARLOR

(95) Sheet E-603-B6, ELECTRICAL SCHEDULES - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(96) Sheet ES-101, ELECTRICAL SITE PLAN

(97) Sheet ES-103, BADGER WELL 5 - WELL PUMP DIAGRAM AND FIRE PUMP HOUSE

SCHEDULES

(98) Sheet P-100-A, UNDERGROUND PLUMBING PLAN - AREA A - LAB & ADMIN

(99) Sheet P-101-B12.1, PLUMBING PLAN - AREA B12.1 – CONNECTOR

(100) Sheet P-101-B12.2, PLUMBING PLAN - AREA B12.2 - CONNECTOR AND SORTING

(101) Sheet P-101-B13, SANITARY PLUMBING PLAN - AREA B13 - MILK HOUSE

(102) Sheet P-101-B3, SANITARY PLUMBING PLAN - AREA B3 - CONVENTIONAL

FREESTALL AREA & DRY COW

(103) Sheet P-101-B6, PLUMBING PLAN - AREA B6 - ROBOTIC MILKING FREESTALL

AREA

(104) Sheet P-103-B4, PLUMBING PLAN-EAST - AREA B4 - MILKING PARLOR

(105) Sheet P-704-A, PLUMBING NATURAL GAS RISER DIAGRAM - AREA A - LAB &

ADMIN

(106) Sheet PS-101, PLUMBING SITE PLAN - NATURAL GAS

(107) Sheet Q-601-B5, EQUIPMENT SCHEDULES - AREA B5 - SPECIAL NEEDS AND

MATERNITY

(108) Sheet A-101-B2, ARCHITECTURAL FLOOR PLAN - AREA B2 - ADVANCED ANIMAL

NUTRITION

(109) Sheet A-310-B2, WALL SECTIONS (TYPICAL) - AREA B2 - ADVANCED ANIMAL

NUTRITION

(110) Sheet A-310-B1, SECTION DETAILS - AREA B1 - AIR EMISSIONS

(111) Sheet A-310-B2, WALL SECTIONS (TYPICAL) - AREA B2 - ADVANCED ANIMAL

NUTRITION

(112) Sheet A-202-B3, EAST ELEVATION - AREA B3 - CONVENTIONAL FREESTALL AREA

& DRY COW

(113) Sheet A-310-B3, WALL SECTIONS - AREA B3 - CONVENTIONAL FREESTALL AREA &

DRY COW

(114) Sheet A-301-B4, BUILDING CROSS SECTIONS - AREA B4 - MILKING PARLOR

(115) Sheet A-310-B5, WALL SECTIONS - AREA B5 - SPECIAL NEEDS AND MATERNITY

(116) Sheet A-301-B6, BUILDING CROSS SECTION - AREA B6 - ROBOTIC MILKING

FREESTALL AREA

(117) Sheet A-310-B6, WALL SECTIONS - AREA B6 - ROBOTIC MILKING FREESTALL

AREA

(118) Sheet A-501-B6, DETAILS - AREA B6 - ROBOTIC MILKING FREESTALL AREA

(119) Sheet A-310-B7, WALL SECTIONS - AREA B7 - CALF BARN

(120) Sheet A-310-B8, WALL SECTIONS - AREA B8 – AGRONOMY

(121) Sheet A-310-B9, WALL SECTIONS - AREA B9 - FEED MIXING CENTER

(122) Sheet A-301-B11, BUILDING CROSS SECTION - AREA B11 - MACHINE STORAGE &

SHOP & PESTICIDE

(123) Sheet A-310-B11, WALL SECTIONS - AREA B11 - MACHINE STORAGE & SHOP &

PESTICIDE

(124) Sheet A-310-B12.1, WALL SECTIONS - AREA 12.1 – CONNECTOR

(125) Sheet A-301-B12.2, BUILDING CROSS SECTIONS - B12.2 - CONNECTOR AND

SORTING

(126) Sheet A-310-B12.2, WALL SECTIONS - AREA B12.2 - CONNECTOR AND SORTING

(127) Sheet A-302-B13, BUILDING CROSS SECTIONS - AREA B13 - MILK HOUSE

(128) Sheet A-201-B15, NORTH AND SOUTH ELEVATIONS - AREA B15 - COMMODITY

STORAGE

(129) Sheet A-202-B15, EAST AND WEST ELEVATIONS - AREA B15 - COMMODITY

STORAGE

(130) Sheet A-301-B15, BUILDING CROSS SECTION - AREA B15 - COMMODITY STORAGE

(131) Sheet A-310-B15, WALL SECTIONS - AREA B15 - COMMODITY STORAGE

(132) Sheet S-301-B8, FOUNDATION SECTIONS - AREA B8 – AGRONOMY

(133) Sheet A-201-B8, ELEVATIONS - AREA B8 – AGRONOMY

(134) Sheet S-101-B8, STRUCTURAL FOUNDATION PLAN - AREA B8 – AGRONOMY

(135) Sheet M-101-B8, MECHANICAL PLAN - AREA B8 – AGRONOMY

(136) Sheet M-501-B8, MECHANICAL DETAILS - AREA B8 – AGRONOMY

(137) Sheet M-502-B8, MECHANICAL DETAILS - AREA B8 – AGRONOMY

(138) Sheet E-601-B4, ELECTRICAL SCHEDULES - AREA B4 - MILKING PARLOR

(139) Sheet E-602-B4, ELECTRICAL DIAGRAMS - AREA B4 - MILKING PARLOR

(140) Sheet S-101-B8, STRUCTURAL FOUNDATION PLAN - AREA B8 – AGRONOMY

(141) Sheet M-501-B8, MECHANICAL DETAILS - AREA B8 - AGRONOMY

ADDENDUM 11

(1) Sheet G-002.2, SHEET INDEX

(2) Sheet G-101-B1, LIFE SAFETY PLAN - AREA B1 - ANIMAL METABOLIC CHAMBERS

(3) Sheet S-001-B1, GENERAL NOTES, ABBREVIATIONS - AREA B1 - AIR METABOLISM

(4) Sheet S-101-B1, STRUCTURAL FOOTING AND FOUNDATION PLAN - AREA B1 - AIR

METABOLISM

(5) Sheet B-102-B1, STRUCTURAL CONCRETE PLAN - AREA B1 - AIR METABOLISM

(6) Sheet S-301-B1, FOUNDATION SECTIONS - AREA B1 - AIR METABOLISM

(7) Sheet S-302-B1, FOUNDATION SECTIONS - AREA B1 - AIR METABOLISM

(8) Sheet S-303-B1, FOUNDATION SECTIONS - LONGITUDINAL - AREA B1 - AIR

METABOLISM

(9) Sheet S-401-B1, ENLARGED STRUCTURAL PLANS - AREA B1 - AIR METABOLISM

(10) Sheet S-501-B1, STRUCTURAL DETAILS - AREA B1 - AIR METABOLISM

(11) Sheet S-502-B1, STRUCTURAL DETAILS - AREA B1 - AIR METABOLISM

(12) Sheet A-001-B1, GENERAL NOTES, ABBREVIATIONS - AREA B1 - AIR METABOLISM

(13) Sheet A-101-B1, ARCHITECTURAL FLOOR PLAN - AREA B1 - AIR METABOLISM

(14) Sheet A-102-B1, ROOF AREA PLAN - AIR METABOLISM

(15) Sheet A-103-B1, REFLECTED CEILING PLAN - AREA B1 - AIR METABOLISM

(16) Sheet A-201-B1, NORTH AND SOUTH ELEVATIONS - AREA B1 - AIR METABOLISM

(17) Sheet A-202-B1, EAST AND WEST ELEVATIONS - AREA B1 - AIR METABOLISM

(18) Sheet A-203-B1, INTERIOR ELEVATIONS - AREA B1 - AIR METABOLISM

(19) Sheet A-301-B1, BUILDING CROSS SECTIONS - AREA B1 - AIR METABOLISM

(20) Sheet A-310-B1, SECTION DETAILS - AIR METABOLISM

(21) Sheet A-401-B1, ENLARGED FLOOR PLANS - AREA B1 - AIR METABOLISM

(22) Sheet A-501-B1, ARCHITECTURAL DETAILS - AREA B1 - AIR METABOLISM

(23) Sheet A-601-B1, DOOR SCHEDULE AND DETAILS - AREA B1 - AIR METABOLISM

(24) Sheet A-602-B1, DOOR DETAILS - AREA B1 - AIR METABOLISM

(25) Sheet I-101-B1, ROOM FINISH SCHEDULE - AREA B1 - AIR METABOLISM

(26) Sheet Q-101-B1, EQUIPMENT FLOOR PLAN - AREA B1 - AIR METABOLISM

(27) Sheet Q-501-B1, EQUIPMENT DETAILS - AREA B1 - AIR METABOLISM

(28) Sheet Q-601-B1, EQUIPMENT SCHEDULES - AREA B1 - AIR METABOLISM

(29) Sheet AG-101-B1, WAYFINDING PLAN - AREA B1 - ANIMAL METABOLIC CHAMBERS

(30) Sheet FA-101-B1, FIRE ALARM PLAN - AREA B1 - ANIMAL METABOLIC CHAMBERS

(31) Sheet P-101-B1, SANITARY PLUMBING PLAN - AREA B1 - AIR METABOLISM

(32) Sheet P-501-B1, PLUMBING DETAILS - AREA B1 - AIR METABOLISM

(33) Sheet P-502-B1, PLUMBING DETAILS - AREA B1 - AIR METABOLISM

(34) Sheet P-601-B1, PLUMBING SCHEDULES - AREA B1 - AIR METABOLISM

(35) Sheet M-101-B1, MECHANICAL PLAN - AREA B1 - AIR METABOLISM

(36) Sheet M-102-B1, MECHANICAL PLAN 2 - AREA B1 - AIR METABOLISM

(37) Sheet M-501-B1, MECHANICAL DETAILS - AREA B1 - AIR METABOLISM

(38) Sheet M-601-B1, MECHANICAL SCHEDULES - AREA B1 - AIR METABOLISM

(39) Sheet E-001-B1, ELECTRICAL GENERAL NOTES, SYMBOLS LIST, AND

ABBREVIATIONS - AREA B1 - AIR METABOLISM

(40) Sheet E-002-B1, ELECTRICAL SYMBOLS LIST - AREA B1 - AIR METABOLISM

(41) Sheet E-101-B1, ELECTRICAL POWER PLAN - AREA B1 - AIR METABOLISM

(42) Sheet E-102-B1, ELECTRICAL LIGHTING PLAN - AREA B1 - AIR METABOLISM

(43) Sheet E-501-B1, ELECTRICAL DETAILS - AREA B1 - AIR METABOLISM

(44) Sheet E-601-B1, ELECTRICAL SCHEDULES - AREA B1 - AIR METABOLISM

(45) Sheet E-602-B1, ELECTRICAL SCHEDULES - AREA B1 - AIR METABOLISM

(46) Sheet E-603-B1, ELECTRICAL DIAGRAM - AREA B1 - AIR METABOLISM

(47) Sheet T-101-B1, TELECOMMUNICATIONS FLOOR PLAN - AREA B1 - ANIMAL

METABOLISM

(48) Sheet TY-101-B1, SECURITY FLOOR PLAN - AREA B1 - ANIMAL METABOLISM

(49) Sheet G-101-B2, LIFE SAFETY PLAN - AREA B2 - ADVANCED ANIMAL NUTRITION

(50) Sheet A-201-B2, NORTH AND SOUTH ELEVATIONS - AREA B2 - ADVANCED ANIMAL

NUTRITION

(51) Sheet S-001-B1, GENERAL NOTES, ABBREVIATIONS - AREA B1 - AIR METABOLISM

(52) Sheet S-001-B2, GENERAL NOTES, ABBREVIATIONS - AREA B2 - ADVANCED

ANIMAL NUTRITION

(53) Sheet S-001-B3, GENERAL NOTES, ABBREVIATIONS - AREA B3 - CONVENTIONAL

FREESTALL AREA & DRY COW

(54) Sheet S-001-B4, GENERAL NOTES, ABBREVIATIONS - AREA B4 - MILKING PARLOR

(55) Sheet S-001-B5, GENERAL NOTES, ABBREVIATIONS - AREA B5 - SPECIAL NEEDS

AND MATERNITY

(56) Sheet S-001-B6, GENERAL NOTES, ABBREVIATIONS - AREA B6 - ROBOTIC

MILKING FREESTALL AREA

(57) Sheet S-001-B7, GENERAL NOTES, ABBREVIATIONS - AREA B7 - CALF BARN

(58) Sheet S-001-B8, GENERAL NOTES, ABBREVIATIONS - AREA B8 – AGRONOMY

(59) Sheet S-001-B9, GENERAL NOTES, ABBREVIATIONS - AREA B9 - FEED MIXING

CENTER

(60) Sheet S-001-B11, GENERAL NOTES, ABBREVIATIONS - AREA B11 - MACHINE

STORAGE & SHOP & PESTICIDE

(61) Sheet S-001-B12.1, SYMBOLS LEGEND AND NOTES - AREA B12.1 – CONNECTOR

(62) Sheet S-001-B12.2, GENERAL NOTES, ABBREVIATIONS - AREA B12.2 -

CONNECTOR AND SORTING

(63) Sheet S-001-B113, GENERAL NOTES, ABBREVIATIONS - AREA B13 - MILK HOUSE

2. This amendment is a part of the proposing papers and its receipt shall be acknowledged. All other conditions and requirements of the request for proposal remain unchanged.

3. Electronic Proposal/Email. See section 00 22 00 for how to submit electronic proposals.

4. Electric Offers will be received until 2:00 p.m., local time at place of receiving proposals, 27 MAY 2025, as stated in the Request For Proposal.

Attachments:

Spec Pages listed in 1.a. above Dwgs. listed in 1.b. above

SECTION 00 10 00 - SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE

The offer guarantee has changed from is required to is not required.

The required response date/time has changed from 18-Apr-2025 02:00 PM to 27-May-2025 02:00 PM.

The offeror acceptance period has decreased by 90 from 180 to 90.

The performance period code has changed from Negotiable to Mandatory.

CLIN 0006

The CLIN description has changed from B1 - Animal Emission Chambers to B1 - Animal Metabolic Chambers.

The CLIN extended description has changed from:

B1 - Animal Emission Chambers

To:

B1 - Animal Metabolic Chambers

CLIN 0020

The CLIN description has changed from Increase Structural Load to DELETED- DO NOT PRICE.

The CLIN extended description has changed from:

Increase structural load capacity of the pre-engineering animal buildings (additional 5 pounds per SF) for potential future installation of solar panels. Buildings B 1, 2, 3, 4, 5, 6, and 11. The Government reserves the right to exercise the options within 240 days after issuance of Notice to Proceed. No additional time will be added if option is exercised.

DELETED IN AMENDMENT 0007 - Requirement to Increase structural load capacity of the pre-engineering animal buildings has been removed.

The cost constraint NTE has been deleted.

CLIN 0021

The CLIN extended description has changed from:

Pavement: add concrete/ asphalt to the parking area and driveway and certain driveways on the base gravel including around the feed center B9, B10 and going in-out of buildings B1, B2, B3, B4, B5, B6, B7, B11, and C2, see sheet C-103. The Government reserves the right to exercise the options within 240 days after issuance of Notice to Proceed.No additional time will be added if option is exercised.

Concrete or asphalt. Sheet C-002 presents the typical pavement sections for multiple types. Refer to Detail 4 for 3.5" HMA, and Detail 1 6" P.C.C. pavement, or a combination of 3.5" HMA and 6" P.C.C. pavement to cover the areas denoted in bid option 2. Detail 02 for base contract gravel. Propose option for concrete details 1 on sheets C-002 and C-003. option for HMA as shown on detail 4 on sheets C-002 and C-003 The Government reserves the right to exercise the options within 90 days after issuance of Notice to Proceed. No additional time will be added to the schedule if option is exercised.

CLIN 0022

B11: Upgrade gravel flooring in Machine storage area to concrete. The Government reserves the right to exercise the options within 240 days after issuance of Notice to Proceed.No additional time will be added if option is exercised.

B11: Upgrade gravel flooring in Machine storage area to concrete. The The Government reserves the right to exercise the options within 90 days after issuance of Notice to Proceed. No additional time will be added to the schedule if option is exercised.

CLIN 0023

B8 - Agronomy Building. The Government reserves the right to exercise the options within 240 days after issuance of Notice to Proceed.No additional time will be added if option is exercised.

B8 - Agronomy Building. The Government reserves the right to exercise the options within 90 days after issuance of Notice to Proceed. No additional time will be added to the schedule if option is exercised.

CLIN 0024

The CLIN extended description has changed from:

B11 - Shop, Machine Storage & Pesticide. The Government reserves the right to exercise the options within 240 days after issuance of Notice to Proceed.No additional time will be added if option is exercised.

B11 - Shop, Machine Storage & Pesticide. The Government reserves the right to exercise the options within 90 days after issuance of Notice to Proceed. No additional time will be added to the schedule if option is exercised.

CLIN 0025

B14 - Fuel Storage. The Government reserves the right to exercise the options within 240 days after issuance of Notice to Proceed.No additional time will be added if option is exercised.

B14 - Fuel Storage. The Government reserves the right to exercise the options within 90 days after issuance of Notice to Proceed. No additional time will be added to the schedule if option is exercised.

CLIN 0026

B15 - Commodity. The Government reserves the right to exercise the options within 240 days after issuance of Notice to Proceed.No additional time will be added if option is exercised.

B15 - Commodity. The Government reserves the right to exercise the options within 90 days after issuance of Notice to Proceed. No additional time will be added to the schedule if option is exercised.

CLIN 0027

The CLIN description has changed from OPTION 0004 – B8 - Agronomy to DELETED - DO NOT

PRICE.

The CLIN extended description has changed from:

OPTION 0004 – B8 - Agronomy building including all utilities, parking and driveway serving the facility, see sheets C-103, C-303. No additional time will be added if option is exercised.

DELETED - ALL UTILITY WORK IS INCLUDED IN CLIN 0001 - The OPTION 0004 – B8 - Agronomy building including all utilities, parking and driveway serving the facility, see sheets C-103, C-303 has been removed from the requirement.

SECTION 00 21 00 - INSTRUCTIONS

INSTRUCTIONS TO OFFERORS

SECTION 00 21 00

INSTRUCTIONS TO OFFERORS (RFP)

1. SOLICITATION RESTRUCTIONS

1.1. GENERAL CONTRACTOR

This Solicitation is Unrestricted.

1.2. ESTIMATED CONSTRUCTION COST

The estimated construction cost of this project is between $25,000,000 and $100,000,000.

1.3 SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS

See FAR 52.215-1 INSTRUCTIONS TO OFFERORS-COMPETITIVE ACQUISTION, subparagraph "(c) Submission, modification, revision, and withdrawal of proposals."

Offers must be submitted electronically. Offerors may utilize email or coordinate with the Contracting Officer a different method of dropping off files. The burden for timely submission rests with the offeror, and no part of this solicitation allows for the acceptance of untimely submissions.

Please send proposals to the Contract Specialist, Nicole Parker, at nicole.l.parker@usace.army.mil and to the Contracting Officer, Jeffrey Wyant, at jeffrey.w.wyant@usace.army.mil.

1.4 SUBMISSION DEADLINE

Offers shall be submitted at the location stated and by the time and date as specified in Block 13 of the Standard Form (SF) 1442, Page 1.

Submit proposals via the instructions below and in Section 00 22 00.

1.4.1 FILE DESCRIPTION

Include a "File Description" for each file(s) you upload. The "File Description" will be included in the email notice to each of the recipients you choose to have access your file(s). Do NOT enter Privacy Act Data (Personal Identification Information (PII)) in the File Description.) Offerors shall use the following example for file descriptions:

Volume I, Technical Proposal, shall be submitted as the following separate files:

W9128F23R0019_FIRMNAME_REQD_DOCS

W9128F23R0019_FIRMNAME_FACTORS1_thru_4

Volume II, Price Proposal, shall be submitted as the following separate files:

W9128F23R0019_FIRMNAME_FACTOR5

W9128F23R0019_FIRMNAME_PRICE

(Note: Company name may be abbreviated) Proposal Format Reference Section 00 22 00 EVALUATION CRITERIA for page limitations and format.

1.4.2 RETURN ADDRESS REQUIREMENTS

Offeror(s) must ensure that ALL mail sent to the Omaha District, U.S. Army Corps of Engineers, either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc. ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to bids, modifications to bids, proposals, revised proposals, bid guarantees, bonds, correspondence, etc., will be REJECTED by the US Army Corps of Engineers mail room facility located at 1616 Capitol Avenue, Omaha, Nebraska 68102-4901 if it does not contain a return mailing address. THERE

WILL BE NO EXCEPTIONS.

2. COPIES OF SOLICITATION DOCUMENT AND AMENDMENTS

Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the U.S. General Services Administration website at:

https://sam.gov/.

It shall be the Contractor's responsibility to check the website for any amendments. The offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation. A list of interested vendors (potential offerors and subcontractors) is available on the sam.gov website listed above (registration required).

3. OFFEROR’S QUESTIONS AND COMMENTS

Questions and/or comments relative to these documents should be submitted via Bidder Inquiry as indicated below. Question and/or comments relative to these bidding (proposal) documents that is proprietary in nature or if Bidder Inquiry system (See Below) is out of service should be submitted to the Contract Specialist:

Contract Specialist – Primary POC: Nicole Parker Nicole.l.parker@usace.army.mil 402-995-2210

3.1. BIDDER INQUIRY

Technical inquiries and questions relating to technical requirements, proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projenet/ no later than 5:00PM (CST) on 29 April 2025, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answer to all non-proprietary questions.

To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team.

All timely questions and approved answers will be made available through ProjNet.

The Solicitation Number is: W9128F25R0014

The Bidder Inquiry Key is: ZIXVB2-FYHF6E

3.1.1. BIDDER INQUIRIES INSTRUCTIONS

a) Offerors are requested to review the specification in its entirety.

b) Offerors are requested to review submitted bidder system for answers to questions prior to submission of a new inquiry.

c) The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago).

The telephone number for the Call Center is 800-428-HELP.

d) Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.

3.1.2. REGISTRATION FOR PROJNET BIDDER INQUIRY ACCESS

If you are already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.

a) From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

b) Identify the Agency. This should be marked as USACE.

c) Key. Enter the Bidder Inquiry Key listed above.

d) Email. Enter the email address you would like to use for communication.

e) Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.

f) Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.

g) Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.

3.1.3. ENTERING BIDDER INQUIRIES IN PROJNET BIDDER INQUIRY SYSTEM

(a) For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.

(b) From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.

(c) Identify the Agency. This should be marked as USACE.

(d) Key. Enter the Bidder Inquiry Key listed above.

(e) Email. Enter the email address you used to register previously in ProjNet.

(f) Click Continue. A page will then open asking you to enter the answer to your Secret Question.

(g) Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.

(h) Follow online screen instructions to enter specific bidder inquiries for the project.

4. PLAN HOLDERS LIST

For viewing a list of interested vendors (i.e. Plan Holders List) and receiving notifications or email of changes regarding a solicitation, U.S. General Services Administration has these features available (https://sam.gov/). For this solicitation, go to https://sam.gov/ and register as a vendor or enter username and password to login. If you wish for General Contractors, Subcontractors, Suppliers, Plan Rooms, or Print Shops to have the ability to contact you, click on "Add me to Interested Vendors" for the solicitation.

5. GENERAL DESCRIPTION OF WORK

See Section 00 22 00 Evaluation Criteria.

6. SOURCE SELECTION EVALUATION BOARD

The Contracting Officer has established a Source Selection Evaluation Board (SSEB) to conduct an evaluation of each proposal received in response to this solicitation. The evaluation will be based exclusively on the merits and content of the proposal and any subsequent discussion required. The identities of the SSEB personnel are confidential, and any attempt by the proposers to contact these individuals is prohibited.

7. FEDERAL, STATE, AND LOCAL TAXES, AND OTHER TAXES

It is the Contractor's responsibility to investigate applicable federal, state, and local taxes as well as any specific exemptions that may exist. This includes any applicable Value-Added Taxes (VAT), sales, use, and excise taxes. See General Conditions (Contract Clause) 52.229-3

FEDERAL, STATE, AND LOCAL TAXES.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

24 April 2025 at 10:00AM, Local

(c) Participants will meet at—

Bluffview, WI on Highway 12 east of County Road “C” https://maps.app.goo.gl/KUTV9rTNvbxkaMPn7 Directions from Madison: https://maps.app.goo.gl/Z8ezVd63Kprnv83g7

Please Contact Jason Harre at Jason.M.Harre@usace.army.mil and provide the following information.

Name Of Company:

POC Attending:

POC Phone Number:

(End of provision)

The following have been deleted:

PROJNET INFORMATION

SITE VISIT

SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS

SUBMISSION/EVALUATION CRITERIA

SECTION 00 22 00

EVALUATION CRITERIA

1. GENERAL SCOPE OF WORK

Construct a new Dairy Forage Research Center (DFRC) at the United States Department of Agriculture (USDA) Agricultural Research Service (ARS) site in Prairie du Sac, Wisconsin. This project will be executed using a design-bid-build (DBB) project delivery method, which will require the contractor to provide the government with a complete facility and warranty based on the Request for Proposal (RFP).

In accordance with Defense Federal Acquisition Regulation Supplement (DFARS) 236.204(ii), the Government currently estimates the magnitude of construction for this project to be between $25,000,000 and $100,000,000.

The USDA DFRC will be located on an approximately 75-acre site on the recently acquired Badger Army Ammunition Plant (BAAP) in Prairie Du Sac, Wisconsin. The Center includes 18 buildings and support structures interconnected by manure collection, transport, and digester system; the approximate combined gross square footage of construction is 642,000 Gross Square Foot (GSF).

Construction of approximately 254,003 Building Gross Square Foot (BGSF) of new production, research, operations, and maintenance facilities and supporting infrastructure. Most of the center's construction will be comprised of pre-framed, pre-engineered metal buildings supported on concrete spread footings with the exception of the Lab and Administration Building which will have a laminated wood building structure supported on spread…