This document outlines payment terms for a federal construction contract to upgrade the Dexter Fish Facility. Major work includes improving and replacing fishway infrastructure, building new structures for sorting and holding fish, and upgrading mechanical and electrical systems. Payment will be made for 31 separate contract line items for tasks such as mobilization, excavation, building construction, mechanical and hydraulic work. Estimated value is between $25-100 million. The solicitation was issued by the U.S. Army Corps of Engineers Portland District for upgrade work expected to occur from 2023 through 2026. The NAICS code is 237990 and small business size standard is $39.5 million.

View the file

Other files

File Type Posted
Dexter Fish Facility W9127N23R0005 Amend 0005.pdf PDF
Dexter_Pre-Bid and Follow On Site Visit_Attendance List.pdf PDF
ProjectNet Inquiries and Responses - Dexter Fish Facilities.pdf PDF
Section 00 10 00 CLINS Structure AMDT 0004.pdf PDF
Drawings SR701_SR101_AMDT 0004.pdf PDF
Drawings MK502_M-600_M-002_MQ501_AMDT 0004.pdf PDF
DB Wage Rate OR20230057 01.06.2023_AMDT 0004.pdf PDF
Dexter Fish Facility W9127N23R0005 Amend 0004.pdf PDF
Spec 26 42 13.00 25_AMDT 0004.pdf PDF
Specs Attachment 1 - Submittal Register_AMDT 0004.pdf PDF
Drawings SK523_SK516-2_SK516_SK516-1_SK516-3_AMDT 0004.pdf PDF
Spec 33 61 13.19 25_AMDT 0004.pdf PDF
Drawings CS103_CU105_CU201_CU102_CU103_AMDT 0004.pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part4.pdf PDF
Clean Sol Package Drawings MECHANICAL_AMDT 0003.pdf PDF
Dexter W9127N23R0005 Clean Solicitation Package.pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part1.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 5 (SP).pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part2.pdf PDF
Clean Sol Package Drawings GENERAL_AMDT 0003.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 3 (SL-SN).pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part3.pdf PDF
Clean Sol Package Drawings LANDSCAPE_AMDT 0003.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 4 (SO-ST).pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 1 (S-SJ) - Part2.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 2 (SK).pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 1 (S-SJ) - Part1.pdf PDF
Dexter Fish Facility W9127N23R0005 Amend 0003.pdf PDF
Clean Sol Package Drawings CIVIL_AMDT 0003.pdf PDF
STRUCTURES_AMDT 0002.pdf PDF
CU502_19DEC22_AMDT 0002.pdf PDF
M-600_AMDT 0002.pdf PDF
MK502_AMDT 0002.pdf PDF
E-603_EL602_EN602_M-601_ML524_AMDT 0002.pdf PDF
MZ101_23DEC22_AMDT 0002.pdf PDF
MW101-MW501-MW502_AMDT 0002.pdf PDF
MY103_AMDT0002.pdf PDF
STRUCTURES_AMDT 0002.pdf PDF
CD501_19DEC22_AMDT 0002.pdf PDF
Dexter Amendment 0002 Spec Changes Package.pdf PDF
W9127N23R0005 Amendment 0002 12.29.22.pdf PDF
Dexter Road Photo Tour.pdf PDF
Dexter Fish Facility Photo Tour.pdf PDF
DXF1.101_ES101-A2 (Electrical_Update_Amend0002).pdf PDF
Attach 8 - Dexter GBR Update Amend0002.pdf PDF
DXF1.101_DEXTER FF UPGRADE_STRUCTURAL UPDATE AMEND 0002.pdf PDF
Attachment 10 - DSL Removal Fill Permit.pdf PDF
W9127N23R0005-Amendment 0001 12.5.2022.pdf PDF
Specs 01 22 00.00 25 M&P Amend 0001.pdf PDF
Site Visit Attendance Sheet - Dexter.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Dexter Dam Adult Fish Facility Upgrades

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 UNIT PRICE PAYMENT ITEMS

1.3 JOB PAYMENT ITEMS

1.4 1.4 MEASUREMENT AND PAYMENT

1.4.1 Mobilization and Demobilization, CLIN 0001

1.4.2 Care and Diversion of Water, CLIN 0002

1.4.3 Interim Water Supply, CLIN 0003

1.4.4 Common Excavation, CLIN 0004

1.4.4.1 First 14,000 Cubic Yards, CLIN 0004AA

1.4.4.2 Over 14,000 Cubic Yards, CLIN 0004AB

1.4.5 Rock Excavation, CLIN 0005

1.4.5.1 First 1,000 Cubic Yards, CLIN 0005AA

1.4.5.2 Over 1,000 Cubic Yards, CLIN 0005AB

1.4.6 Civil, CLIN 0006

1.4.7 Fishway Water Supply Conduit Trashrack, CLIN 0007

1.4.8 AWS Diffusion Chamber, CLIN 0008

1.4.9 Fish Ladder, CLIN 0009

1.4.10 Pre-Sort Pool Structural, CLIN 0010

1.4.11 Post-Sort Pools, CLIN 0011

1.4.12 Hopper Crane Frame, CLIN 0012

1.4.13 Fish Ladder Crossing, CLIN 0013

1.4.14 Discharge Outlet Structure, CLIN 0014

1.4.15 Discharge Return to River Structure, CLIN 0015

1.4.16 Juvenile Pools Return Water System, CLIN 0016

1.4.17 Fish Ladder Entrance Shade Structure, CLIN 0017

1.4.18 Pre-Sort Pool Shade Structure, CLIN 0018

1.4.19 Sorting Structure, CLIN 0019

1.4.20 Maintenance and Office Building, CLIN 0020

1.4.21 Mechanical and Electrical Building, CLIN 0021

1.4.22 Pre-Sort Finger Weir and False Weir, CLIN 0022

1.4.23 AWS and Fish Ladder Gates, CLIN 0023

1.4.24 Sorting Area Equipment, CLIN 0024

1.4.25 Post-Sort Pool Mechanical, CLIN 0025

1.4.26 Crowders, CLIN 0026

1.4.27 Facility Water Supply Piping, CLIN 0027

1.4.28 Mechanical Control System, CLIN 0028

1.4.29 Electrical and Controls, CLIN 0029

1.4.30 Prestressed Concrete Beams Removal (Optional), CLIN 0030

1.4.31 Temporary Utilities for the Existing Residence (Optional), CLIN 0031

PART 2 PRODUCTS - NOT USED

SECTION 01 22 00.00 25 Page 1

AMD 0004

PART 3 EXECUTION - NOT USED

-- End of Section Table of Contents --

SECTION 01 22 00.00 25 Page 2

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

In each instance, the Contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the Paragraphs MEASUREMENT and PAYMENT, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule. Payment for work activities involving lead based paint will be incidental to the related CLIN.

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, Operation and Maintenance (O&M) manuals, tests and reports, meeting safety requirements; and for performing all work required for each of the unit price items.

1.3 JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment;

performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided. Provide a schedule of values for job items prior to the first pay request. Update with each subsequent payment request.

MANDATORY ITEMS

1.4 1.4 MEASUREMENT AND PAYMENT

1.4.1 Mobilization and Demobilization, CLIN 0001

a. Measurement: Measurement will be made as a job for mobilizing and

SECTION 01 22 00.00 25 Page 3 demobilizing all plant, equipment, fuel, supplies, materials, and personnel to and from the job site. This Contract Line Item Number (CLIN) applies to the Prime Contractor and all subcontractor mobilization and demobilization.

b. Payment: Payment will be made at the Contract amount under CLIN 0001 as stated in Contract Clause 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION (Dec 1991). Submit a schedule of mobilization and demobilization costs prior to submitting the first request for payment.

1.4.2 Care and Diversion of Water, CLIN 0002

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for cofferdam, dewatering for cofferdam, channel and land excavations, and pumps and piping.

b. Payment: Payment will be made in the Contract amount under CLIN 0002.

1.4.3 Interim Water Supply, CLIN 0003

a. Measurement: Measurement will be made as a job item for providing all labor, equipment, materials, parts, and incidentals for construction, operation, and removal of the gravity fed water supply required to temporarily supply water to the fish facility during construction.

b. Payment: Payment will be made in the Contract amount under

CLIN 0003.

1.4.4 Common Excavation, CLIN 0004

1.4.4.1 First 14,000 Cubic Yards, CLIN 0004AA

a. Measurement: The total quantity of excavated material for which payment will be made will be the theoretical quantity between the pre-excavation ground surface as determined by a pre-excavation survey and the post-excavation ground surface as determined by a post excavation survey. Computation of volume shall be made by average-end-area cross-section methods. Unit price shall include providing all labor, plant, equipment, materials, and incidentals required for common excavation and shall include all excavating, trenching, loading, hauling, and disposing of the materials at the designated disposal site shown on the drawings.

b. Payment: Payment will be made in the Contract amount under CLIN

0004AA.

1.4.4.2 Over 14,000 Cubic Yards, CLIN 0004AB

a. Measurement: The total quantity of excavated material for which payment will be made will be the theoretical quantity between the pre-excavation ground surface as determined by a pre-excavation survey and the post excavation ground surface as determined by a post excavation survey. Computation of volume shall be made by average-end-area cross-section methods. Unit price shall include providing all labor, plant, equipment, materials, and incidentals

SECTION 01 22 00.00 25 Page 4 required for common excavation and shall include all excavating, trenching, loading, hauling, and disposing of the materials at the designated disposal site shown on the drawings.

b. Payment: Payment will be made in the Contract amount under CLIN

0004AB.

1.4.5 Rock Excavation, CLIN 0005

1.4.5.1 First 1,000 Cubic Yards, CLIN 0005AA

a. Measurement: The total quantity of excavated material for which payment will be made will be the theoretical quantity between the pre-excavation ground surface as determined by a pre-excavation survey and the post excavation ground surface as determined by a post excavation survey. Computation of volume shall be made by average-end-area cross-section methods. Unit price shall include providing all labor, plant, equipment, materials, and incidentals required for common excavation and shall include all excavating, trenching, loading, hauling, and disposing of the materials at the designated disposal site shown on the drawings.

b. Payment: Payment will be made in the Contract amount under CLIN

0005AA.

1.4.5.2 Over 1,000 Cubic Yards, CLIN 0005AB

a. Measurement: The total quantity of excavated material for which payment will be made will be the theoretical quantity between the pre-excavation ground surface as determined by a pre-excavation survey and the post excavation ground surface as determined by a post excavation survey. Computation of volume shall be made by average-end-area cross-section methods. Unit price shall include providing all labor, plant, equipment, materials, and incidentals required for common excavation and shall include all excavating, trenching, loading, hauling, and disposing of the materials at the designated disposal site shown on the drawings.

b. Payment: Payment will be made in the Contract amount under CLIN

0005AB.

1.4.6 Civil, CLIN 0006

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for civil construction. The intent of this CLIN is to include all work described in the civil drawings, excluding costs for excavation and trenching .

b. Payment: Payment will be made in the Contract amount under CLIN 0006.

1.4.7 Fishway Water Supply Conduit Trashrack, CLIN 0007

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for for demolition and construction of the Fishway Water Supply Conduit Trashrack. The intent of this CLIN is to include all work described on the SJ series of the structural drawings.

SECTION 01 22 00.00 25 Page 5

b. Payment: Payment will be made in the Contract amount under

CLIN 0007.

1.4.8 AWS Diffusion Chamber, CLIN 0008

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the AWS Diffusion Chamber. The intent of this CLIN is to include all structural work not related to the fish ladder as described in the SK series of the structural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0008.

1.4.9 Fish Ladder, CLIN 0009

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Fish Ladder. The intent of this CLIN is to include all work associated with the fish ladder from the fish ladder entrance to station 3+72.39 and the alterations to the existing fish ladder as described in the SK series of the structural drawings. This includes the fish ladder walls and weirs, fish ladder flow vane, occlusion fish exclusion screen and frame, bulkhead, existing fish ladder fish screens and concrete wall plugs, and walkways, railings, and stairs associated with the fish ladder. fish screen, and bulkhead.

b. Payment: Payment will be made in the Contract amount under

CLIN 0009.

1.4.10 Pre-Sort Pool Structural, CLIN 0010

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Pre-Sort Pool. The intent of this CLIN is to include all work described on the SL series of the structural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0010.

1.4.11 Post-Sort Pools, CLIN 0011

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Post-Sort Pools. The intent of this CLIN is to include all work described on the SN series of the structural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0011.

1.4.12 Hopper Crane Frame, CLIN 0012

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Hopper Crane Frame Structure and design and installation of the hopper crane s. . The intent of this CLIN is to include all work described on the SO series of the structural drawings.

SECTION 01 22 00.00 25 Page 6

b. Payment: Payment will be made in the Contract amount under

CLIN 0012.

1.4.13 Fish Ladder Crossing, CLIN 0013

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Fish Ladder Crossing Maintenance Building . The intent of this CLIN is to include all work described on the ST series of the structural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0013.

1.4.14 Discharge Outlet Structure, CLIN 0014

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the discharge outlet. The intent of this CLIN is to include all work described on the SQ series of the structural drawings excluding the return to river outfall structure.

b. Payment: Payment will be made in the Contract amount under

CLIN 0014.

1.4.15 Discharge Return to River Structure, CLIN 0015

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Discharge Return to River Outfall Structure. The intent of this CLIN is to include all work described on the SQ series of the structural drawings excluding the discharge outlet structure.

b. Payment: Payment will be made in the Contract amount under

CLIN 0015.

1.4.16 Juvenile Pools Return Water System, CLIN 0016

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Juvenile Pools Return Water System. The intent of this CLIN is to include all work described on the SR series of the structural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0016.

1.4.17 Fish Ladder Entrance Shade Structure, CLIN 0017

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Fish Ladder Entrance Shade Structure. The intent of this CLIN is to include all work described on the AK series of the architectural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0017.

SECTION 01 22 00.00 25 Page 7

1.4.18 Pre-Sort Pool Shade Structure, CLIN 0018

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Pre-Sort Pool Shade Structure. The intent of this CLIN is to include all work described on the AL series of the architectural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0018.

1.4.19 Sorting Structure, CLIN 0019

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Sorting Structure. The intent of this CLIN is to include all work described in the SM series of the structural drawings and the AM series of the architectural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0011.

1.4.20 Maintenance and Office Building, CLIN 0020

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for demolition and construction of the Maintenance and Office Building. The intent of this CLIN is to include all work described on the AY series of the architectural drawings and the MY series of the mechanical drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0020.

1.4.21 Mechanical and Electrical Building, CLIN 0021

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for construction of the Mechanical and Electrical Building. The intent of this CLIN is to include all work described on the AZ series of the architectural drawings and the MZ series of the mechanical drawings.

b. Payment: Payment will be made in the Contract amount under CLIN 0021.

1.4.22 Pre-Sort Finger Weir and False Weir, CLIN 0022

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for construction of the Pre-Sort Finger Weir and False Weir. The intent of this CLIN is to include all work associated with the pre-sort finger weir and false weir as described in the ML series of the mechanical drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0022.

1.4.23 Fish Exclusion Screen AWS and Fish Ladder Gates , CLIN 0023

a. Measurement: Measurement will be made as a job item for providing all labor, equipment, materials, parts, and incidentals for demolition

SECTION 01 22 00.00 25 Page 8 and construction of the Fish Exclusion Screen AWS and fish ladder gates, including the fish ladder entrance slide gate, diffuser chamber slide gates, and the lift gate constructed in the existing fish ladder .

The intent of this CLIN is to include all work described on the MK series of the mechanical drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0023.

1.4.24 Sorting Area Equipment, CLIN 0024

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for construction of the Sorting Area Equipment and Fish Flume to include the sorting table, anesthetic tank, recovery tank, fish flume, and switchgates. .

The intent of this CLIN is to include all work described on the MM series of the mechanical drawings and the switchgear and fish flume as described in the ML series.

b. Payment: Payment will be made in the Contract amount under

CLIN 0024.

1.4.25 Post-Sort Pool Mechanical, CLIN 0025

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for construction of the Post-Sort Pool Mechanical and associated items. The intent of this CLIN is to include all work described on the MN, MO, and MQ series of the mechanical drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0025.

1.4.26 Crowders, CLIN 0026

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for construction of all of the crowders to include the pre-sort crowder, post-sort crowders, and rails. The intent of this CLIN is to include all work associated with the crowders as described in the ML series of the mechanical drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0026.

1.4.27 Facility Water Supply Piping, CLIN 0027

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for construction of the Facility Water Supply Piping. The intent of this CLIN is to include all work described on the MP series of the mechanical drawings , the piping and valves shown on the MK series of the mechancial drawings, and all work described on the SP series of the structural drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0027.

SECTION 01 22 00.00 25 Page 9

1.4.28 Mechanical Control System, CLIN 0028

a. Measurement: Measurement will be made as a job for providing all labor, equipment, materials, parts, and incidentals for construction of the Mechanical Control System including pneumatic controls and electrical valve controls. . The intent of this CLIN is to include all work described on the MI series of the mechanical drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0028.

1.4.29 Electrical and Controls, CLIN 0029

a. Measurement: Measurement will be made as a job item for providing all labor, equipment, materials, parts, and incidentals for providing and installation of Electrical and Controls to include incidental asbestos. The intent of this CLIN is to include all work described on the electrical drawings.

b. Payment: Payment will be made in the Contract amount under

CLIN 0029.

OPTIONAL ITEMS

1.4.30 Prestressed Concrete Beams Removal (Optional), CLIN 0030

a. Measurement: Measurement will be made as a job item for providing all labor, equipment, materials, parts, and incidentals for demolition and removal of the Prestressed Concrete Beams detailed in appendix A15.

b. Payment: Payment will be made in the Contract amount under CLIN 0030, "Prestressed Concrete Beams Removal."

1.4.31 Temporary Utilities for the Existing Residence (Optional), CLIN 0031

a. Measurement: Measurement will be made as a job item for providing all labor, equipment, materials, parts, and incidentals to provide temporary utilities to the existing residence.

b. Payment: Payment will be made in the Contract amount under

CLIN 0031.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

-- End of Section --

SECTION 01 22 00.00 25 Page 10

PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 22 00.00 25 - MEASUREMENT AND PAYMENT
01 22 00.00 25 - MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 GENERAL INFORMATION
1.2 UNIT PRICE PAYMENT ITEMS
1.3 JOB PAYMENT ITEMS
1.4 1.4 MEASUREMENT AND PAYMENT
1.4.1 Mobilization and Demobilization, CLIN 0001
1.4.2 Care and Diversion of Water, CLIN 0002
1.4.3 Interim Water Supply, CLIN 0003
1.4.4 Common Excavation, CLIN 0004
1.4.4.1 First 14,000 Cubic Yards, CLIN 0004AA
1.4.4.2 Over 14,000 Cubic Yards, CLIN 0004AB
1.4.5 Rock Excavation, CLIN 0005
1.4.5.1 First 1,000 Cubic Yards, CLIN 0005AA
1.4.5.2 Over 1,000 Cubic Yards, CLIN 0005AB
1.4.6 Civil, CLIN 0006
1.4.7 Fishway Water Supply Conduit Trashrack, CLIN 0007
1.4.8 AWS Diffusion Chamber, CLIN 0008
1.4.9 Fish Ladder, CLIN 0009
1.4.10 Pre-Sort Pool Structural, CLIN 0010
1.4.11 Post-Sort Pools, CLIN 0011
1.4.12 Hopper Crane Frame, CLIN 0012
1.4.13 Fish Ladder Crossing, CLIN 0013
1.4.14 Discharge Outlet Structure, CLIN 0014
1.4.15 Discharge Return to River Structure, CLIN 0015
1.4.16 Juvenile Pools Return Water System, CLIN 0016
1.4.17 Fish Ladder Entrance Shade Structure, CLIN 0017
1.4.18 Pre-Sort Pool Shade Structure, CLIN 0018
1.4.19 Sorting Structure, CLIN 0019
1.4.20 Maintenance and Office Building, CLIN 0020
1.4.21 Mechanical and Electrical Building, CLIN 0021
1.4.22 Pre-Sort Finger Weir and False Weir, CLIN 0022
1.4.23 Fish Exclusion ScreenAWS and Fish Ladder Gates, CLIN 0023
1.4.24 Sorting Area Equipment, CLIN 0024
1.4.25 Post-Sort Pool Mechanical, CLIN 0025
1.4.26 Crowders, CLIN 0026
1.4.27 Facility Water Supply Piping, CLIN 0027
1.4.28 Mechanical Control System, CLIN 0028
1.4.29 Electrical and Controls, CLIN 0029
1.4.30 Prestressed Concrete Beams Removal Optional, CLIN 0030
1.4.31 Temporary Utilities for the Existing Residence Optional, CLIN 0031
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED