Dexter Fish Facility W9127N23R0005 Amend 0003.pdf

PDF 378 KB Posted

Attached to
Dexter Adult Fish Facility Upgrades
Solicitation number
W9127N23R0005
Issued by

About this file

This amendment to a solicitation extends the response deadline from January 13, 2023 to January 27, 2023. It also increases the period of performance by 40 days to 1,280 days total for the Dexter Adult Fish Facility Upgrades Project. The project scope includes major improvements, replacements, and additions to the Dexter Fish Facility to meet criteria from the National Marine Fisheries Service. The estimated value is between $25 million to $100 million. The solicitation is unrestricted and full and open, with application of the HUBZone 10% price evaluation preference as required. The NAICS code is 237990 for other heavy and civil engineering construction, with a $39.5 million small business size standard. The soliciting agency is the U.S. Army Corps of Engineers Portland District.

View the file

Other files

File Type Posted
Dexter Fish Facility W9127N23R0005 Amend 0005.pdf PDF
Dexter_Pre-Bid and Follow On Site Visit_Attendance List.pdf PDF
ProjectNet Inquiries and Responses - Dexter Fish Facilities.pdf PDF
Section 00 10 00 CLINS Structure AMDT 0004.pdf PDF
Drawings SR701_SR101_AMDT 0004.pdf PDF
Drawings MK502_M-600_M-002_MQ501_AMDT 0004.pdf PDF
DB Wage Rate OR20230057 01.06.2023_AMDT 0004.pdf PDF
Dexter Fish Facility W9127N23R0005 Amend 0004.pdf PDF
Spec 26 42 13.00 25_AMDT 0004.pdf PDF
Specs Attachment 1 - Submittal Register_AMDT 0004.pdf PDF
Drawings SK523_SK516-2_SK516_SK516-1_SK516-3_AMDT 0004.pdf PDF
Spec 33 61 13.19 25_AMDT 0004.pdf PDF
Spec 01 22 00.00 25_AMDT 0004.pdf PDF
Drawings CS103_CU105_CU201_CU102_CU103_AMDT 0004.pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part4.pdf PDF
Clean Sol Package Drawings MECHANICAL_AMDT 0003.pdf PDF
Dexter W9127N23R0005 Clean Solicitation Package.pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part1.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 5 (SP).pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part2.pdf PDF
Clean Sol Package Drawings GENERAL_AMDT 0003.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 3 (SL-SN).pdf PDF
Clean Sol Package Drawings ELECTRICAL_AMDT 0003 Part3.pdf PDF
Clean Sol Package Drawings LANDSCAPE_AMDT 0003.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 4 (SO-ST).pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 1 (S-SJ) - Part2.pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 2 (SK).pdf PDF
Clean Sol Package Drawings STRUCTURAL_AMDT 0003 Set 1 (S-SJ) - Part1.pdf PDF
Clean Sol Package Drawings CIVIL_AMDT 0003.pdf PDF
STRUCTURES_AMDT 0002.pdf PDF
CU502_19DEC22_AMDT 0002.pdf PDF
M-600_AMDT 0002.pdf PDF
MK502_AMDT 0002.pdf PDF
E-603_EL602_EN602_M-601_ML524_AMDT 0002.pdf PDF
MZ101_23DEC22_AMDT 0002.pdf PDF
MW101-MW501-MW502_AMDT 0002.pdf PDF
MY103_AMDT0002.pdf PDF
STRUCTURES_AMDT 0002.pdf PDF
CD501_19DEC22_AMDT 0002.pdf PDF
Dexter Amendment 0002 Spec Changes Package.pdf PDF
W9127N23R0005 Amendment 0002 12.29.22.pdf PDF
Dexter Road Photo Tour.pdf PDF
Dexter Fish Facility Photo Tour.pdf PDF
DXF1.101_ES101-A2 (Electrical_Update_Amend0002).pdf PDF
Attach 8 - Dexter GBR Update Amend0002.pdf PDF
DXF1.101_DEXTER FF UPGRADE_STRUCTURAL UPDATE AMEND 0002.pdf PDF
Attachment 10 - DSL Removal Fill Permit.pdf PDF
W9127N23R0005-Amendment 0001 12.5.2022.pdf PDF
Specs 01 22 00.00 25 M&P Amend 0001.pdf PDF
Site Visit Attendance Sheet - Dexter.pdf PDF
Show 40 more

Latest 50 of 71 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment is to extend the solicitation close date from 13 Jan 2023 at 1000AM PST to 27 Jan 2023 at 1000AM PST, update Block 11 of this SF1442, and incorporate updates to Specifications and Draw ings. All updates are incorporated into a clean Solicitation Package that includes all updates and changes to Specifications and Draw ing through 5 January 2023.

See Summary of Changes for additional details on Draw ing and Specification Changes.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Jan-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9127N23R0005

X 9B. DATED (SEE ITEM 11)

23-Nov-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Jan-2023

CODE

USACE, PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204

W9127N 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9127N23R0005

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been modified:

SUMMARY OF CHANGES

Update Drawing MP518 to fix Floor Elevation Typos.

Updated Drawings MK502, MK503, MK504, and the Valves, Piping, and Equipment in Valve

Manholes Specification 33 61 13.19 25.

Updated Slide Gates and Actuators Specification 35 20 16.54 25, Table 2.2.1, for the 8’x8’ gate.

Pipelines, Liquid Process Piping Specification 40 05 13.00 25 updated to remove unit price references.

Updated Specification 40 05 13, Para 2.2 to only references the contract drawings, added subpart

2.2.1 Pipe Schedule to discuss deliverable pipe schedule, and removed pipe schedule reference from Paragraph 3.14.1.2 and Paragraph and 3.14.3.

Updated Drawing G-007 and CE001 for the boat ramp from Pengra Road.

Updated Plant-Precast Concrete Products For Below Grade Construction Specification 03 42

13.00 25 for appropriate vault sizes.

All updated Drawings and Specification are included in the “Dexter W9127N23R0005 Clean Solicitation Package” incorporating all updates and changes due to Amendments and Bidder Inquiries as of 5 January 2023.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 13-Jan-2023 10:00 AM to 27-Jan-2023 10:00 AM.

The contractor period of performance end date has increased by 40 days from 1240 days to 1280 days.

(End of Summary of Changes)