ARCF SREL C2 Site Visit 10NOV20.pdf
PDF 8 MB Posted
- Attached to
- Sacramento River East Levee (SREL) Contract 2
- Solicitation number
- W9123821B0001
About this file
This document summarizes a federal solicitation for construction services along the Sacramento River East Levee in California. The U.S. Army Corps of Engineers seeks a firm-fixed price contract to construct approximately 1.8 miles of various seepage cutoff walls along discontinuous reaches of the levee. Work includes relocating and removing utilities, modifying relief wells, replacing a city sump, and handling contaminated soils. Night work is permitted for jet grout cutoff walls only. All work must be completed by December 2021, with levee reconstruction by September 2021. The solicitation will be issued on or around October 30, 2020 via beta.sam.gov, with bids due by November 30, 2020. The construction value is estimated between $25-100 million. The contract will use NAICS code 237990 and Product Service Code Y1LC. The solicitation is unrestricted but contractors must be on the Pre-Qualified Sources List. Small business subcontracting goals include 30% small business, 10% small disadvantaged business, 5% women-owned small business, and 3% service-disabled veteran-owned small business.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMERICAN RIVER COMMON FEATURES
Sacramento River East Levee, Contract 2 Seepage/Stability Levee Improvements Site Visit
November 12, 2020
AGENDA
4/24/20 NM
PROGRAM OVERVIEW
Project Background
TECHNICAL OVERVIEW
Overview
Remaining Efforts
Environmental
REGIONAL OVERVIEW
CONTRACTING
SACRAMENTO AREA PROJECTS
4/24/20 NM
AMERICAN RIVER COMMON FEATURES 2016
Authorized Plan Features
Cutoff walls Up to 13 miles
Bank protection Up to 21 miles
Levee stabilization Up to 5 miles
Levee raises Up to 5 miles
Widen Sacramento Weir and Bypass
Approx. 1500 feet
Environmental Mitigation Up to 680 acres
Replant Shaded Riverine Habitat Up to 15.5 miles
Reduces Risk 500,000 People
125,000 Structures
$62 Billion
SUBSTANTIAL COMPLETION TARGET JAN 2024
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
SACRAMENTO RIVER
EAST LEVEE (SREL)
CONTRACT 2
IMPROVEMENTS
11/10/20 NM
SREL CONTRACT 2 - SCHEDULE
PROCUREMENT PROCESS
30OCT20 Solicitation
12NOV20 – Site Visit
3DEC20 – Bids Due
11JAN21 - Award
CONSTRUCTION
NLT 30 SEPT 2021 – Seepage/Stability Improvements Complete
NLT DEC 2021 – Construction Complete
11/10/20 NM
SREL CONTRACT 2 REMAINING EFFORTS
7/17/19 NM
SREL CONTRACT 2 OVERVIEW
SREL CONTRACT 2 OVERVIEW
REACH 4 JET GROUT CUTOFF WALL
Cutoff Wall
• 108 FT Depth
• 500 FT Length
• No Levee Degrade Levee Crest Railroad
• State Park’s Owned
• Two tracks – Limited Use for
Public Tours. Will run on weekends only.
Utility Conflicts
• Directional Jet Grouting
(Panels) Required
• 120” Pipe – Protect in
Place
• 42” Pipe – Protect in
Place
REACH 4 JET GROUT CUTOFF WALL
120” and 42” Pipe Utility Vault
• Wall Alignment Jogs to Waterside limit of Vault
• Panel Construction Required for Crossing Pipes
12REACH 5 & 6: OPTION 1 JET GROUT CUTOFF
WALL
Cutoff Wall
• 50 FT Depth
• 1,300 FT Length
• No Levee Degrade Levee Crest Railroad
• One Set of Tracks –
Limited Use for Public Tours. Will run on weekends only.
Utility Conflicts
• Various –
Petroleum/Gas/Com/ Water/ Overhead Electrical
REACH 5 & 6: JET GROUT CUTOFF WALL
Various Utility penetrations through out levee within Cutoff Wall Extents
• All are 24” or less in diameter
• 17 to be Abandoned in Place
• 14 to be Protected in Place
REACH 4, 5, & 6 STAGING AREAS
REACH 13 SB CUTOFF WALL
Cutoff Wall
• 63 FT Depth
• 920 FT Length
• ~5 FT of Levee Degrade Utility Conflicts
• 1 Piezometer Removal and Disposal
• 1 Pipe Removal and Disposal
REACH 13 SB CUTOFF WALL
• Tie-in into SREL Contract 1 DMM Wall at U/S end
• 2 Protect in Place penetrations D/S of Wall end
REACH 13 STAGING AREA
REACH 15, 16, & 17 CUTOFF WALL
• Cutoff Wall
• Combined 1.3 Miles of SB(Yellow) / SCCB(Green) / DMM(Blue) Cutoff Wall
• Degrade – approximately 6’
• Wall depths: 72 - 118 ft
Utility Conflicts
• 12 Removal and Disposals – Small diameter
(≤12” Waterlines/Electrical Conduits/Misc)
• Sump 63 Vault and Discharge Pipes (4)
Removal and Replacement
PHASE II CUTOFF WALL TRENCH STABILITY
• Cracking of levee and foundation and loss of slurry occurred at five locations during construction of
USACE Phase II SCB walls in 1992.
• Trench failures occurred while the trenches were supported by bentonite slurry, and prior to or during placement of final backfill material.
• All five sites are located within extents where SREL cutoff wall is proposed.
• Levee and foundation were excavated to about El. 7.5-13.5, followed by placement of geotextile and geogrid layers, reconstruction of levee, and reconstruction of cutoff wall.
REACHES 15-17 SUMP 63
Limit impact to residential communities by traveling on highways, major streets, and levee crown to extent practical.
Highways and major streets include:
• Interstate 5
• Front Street
• Broadway
• Riverside Drive
• Seamas Avenue
• 43rd Avenue
• Riverside Boulevard
• Florin Road
• Pocket Road
SREL C2 - HAUL ROUTES
• Access is limited due to residential areas
• 12 designated access points to levee crown
SREL C2 – LEVEE ACCESS POINTS
Borrow Material (Type 1 Fill)
– Potential Source: Sacramento Regional Wastewater Treatment
Plant
• Echo Water Project Spoil Stockpiles
Reuse of Excavated Materials
– Levee crown degrade is typically a sandier fill that does not meet levee fill (Type 1) requirements
– Unused degrade material can potentially be transported to the Railyards project
POTENTIAL BORROW AND DEGRADE MATERIALS
Borrow Site
SREL
NEEDED: MEET OR EXCEED EXPECTATIONS ON ALL ACCOUNTS
5/5/20 HC
APPROXIMATE QUANTITIES
Levee Degrade
(CY)
Levee Fill (Type 1)
(CY)
SB Cutoff Wall (SF)
SCCB
Cutoff Wall
(SF)
DMM
Cutoff Wall
(SF)
Jet Grout Wall
Jet Grout Option
85,000 85,000 420,000 70,000 140,000 52.500 47,750
• Levee Fill Type 1 is for levee reconstruction
• All NEPA/CEQA/Section 106 documentation is required contractor proposed borrow/disposal
• USACE Environmental Documentation –Covered in Spec
• Commercial Source with Mining Permit
CONSTRAINTS
Impacts to Elderberries: Elderberries in Project Footprint to protect in place
Impacts to Migratory Birds and Raptors
Impacts to Air/Noise Pollution
Impacts to Recreation (Bike/Pedestrian Paths, Boat Launches, Etc.)
WORKING HOURS & WINDOWS
WORK HOURS FLOOD SEASON TREE TRIMMING AND
REMOVAL
Monday – Friday 7am – 7pm
1 November – 15April 1 November – 15 February Saturday 7am – 6pm
Sunday 8am – 6pm
11/10/20 NM
SS&O ENVIRONMENTAL
• Tree Removal will be completed via separate contract starting in Fall 2020.
• SREL Contract 2 will be responsible for tree stump removal.
• Tree Trimming may be necessary
• Elderberries will be transplanted via separate contract starting Fall 2020 authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
Project
Anticipated Construction
Schedule Description
NATOMAS
Reach I Contract 1 2019-2020 ~ 4 miles Levee Improvements - Cut-Off Wall
Reach H 2019-2020 ~ 4 miles Levee Improvements - Cut-Off Wall Reach B 2020-2021 ~ 2 miles Levee Improvements - Seepage berm, Relocation of Riverside Canal Reach E 2021-2022 ~ 3 miles Levee Improvements – possible cut-off wall Reach A 2022-2023 ~ 4 miles Levee Improvements – possible cut-off wall & numerous Utility Relocations
Reach F&G 2023-2024 ~ 4 miles Levee Improvements – possible cut-off wall
FOLSOM DAM RAISE
Dike Raise 2019-2024 ~ 5 miles of 3.5’ Dike Raise and related work in various packages Main Dam 2022-2025 Retrofit of up to 8 gates on the Main Dam
HAMILTON CITY 2019-2020 Mitigation and Planting TULE RIVER 2020-2024 10’ Spillway Raise, utility relocations, environmental mitigation
ARCF 2016
Sac River Levees 2019-2024 Up to 9 miles of cut-off wall and other seepage control features Sac River Erosion 2021-2024 Up to 10 miles of bank protection work Amr River Erosion 2021-2024 Up to 11 miles of bank protection work Sac Weir/Bypass 2022-2024 1,500 lf expansion of existing gated weir at Sac Bypass
Mitigation 2019-2024 Tree cutting, planting, maintenance, etc.
ISABELLA
Dams & Spillways Ongoing Construction of 16’ dam raise, new emergency spillway, and various improvements Site Restoration 2020-2022 Construction of permanent operations building, site restoration and misc. construction
YUBA RIVER BASIN
Phase 2C 2019-2020 ~ 1,000 lf DSM wall construction
Phase 2B/3 2020-2023 ~ 13,000 LF Cut-off wall construction Phase 4B 2022-2023 Rock Slope Protection installation PL 84-99 2018-2020 Various repairs in response to 2017 Flood Event
SUTTER BASIN 2019-2020 ~ 5 miles of Levee Improvements including cut-off wall LOWER SAN JOAQUIN Unknown Project is entering design phase and may have a contract as early as 2021 WEST SACRAMENTO Unknown Project is seeking to enter design phase and may have a contract as early as 2022
11/10/2020 NM
SYSTEMATIC OVERVIEW – CALTRANS PROJECT
I-5 Corridor Enhancement Project/I-5 HOV Lanes
On Interstate 5 (I-5) from 1.1 mile south of Elk Grove Boulevard Over crossing (PM 9.7) to American River Viaduct (PM 24.9) will rehabilitate pavement and other related assets, construct new High Occupancy Vehicle (HOV) lanes, install new fiber optic lines and extend the I-5 northbound #1 lane to improve the on ramp merge and weave movement
Total Project Cost: $370 million
Construction: Summer 2019 – Fall 2022 authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
CONTRACTING
HOW TO OBTAIN SOLICITATIONS
11/10/20 NVRM
HOW TO OBTAIN SOLICITAITONS
SAMbeta – www.Beta.SAM.gov
Search by Solicitation Number – W9123821B0001
View Interested Vendors List and register as an interested vendor
Requirements to download Technical Data Package: Beta.sam.gov
Register to receive notifications and updates/amendments
Technical information will be posted on the BetaSam website
SMALL BUSINESS GOALS GOAL
Small Business (SB) 30%
Small Disadvantaged Business (SDB) 10%
Woman Owned Small Business (WOSB) 5%
Service-Disabled Veteran Owned Small Business (SDVOSB) 3%
Historically Underutilized Business Zone (HUBZone) 5%
Veteran Owned Small Business 5%
CONTRACT ADMINISTRATION
USACE Safety Manual, EM 385-1-1
Quality Assurance Surveillance Plan for Services
USACE Resident Management System (RMS) & Quality Control System (QCS) will be used for construction
Government is committed to partnering process at all levels http://www.beta.sam.gov/
UNIQUE CONTRACT ASPECTS
11/10/20 NM
Production/Productivity Rates (Efficiency/Effectiveness, Constraints, Innovations)
Material/Equipment – Volume in order to meet schedule
Proximity to Residential Neighborhood
Air Quality (Availability of higher tiered equipment/barges, recent model year equipment, innovations)
Schedule – Required completion by 30SEP20 for all levee improvements
Jet grout columns and panel to depths of at least 115 feet around several utilities and contaminated soil
Working hours; allowance and restrictions for working multiple shifts versus multiple rigs working one shift
QUESTIONS/COMMENTS/CONCERNS…
5/5/20 NM
www.sacleveeupgrades.com http://www.sacleveeupgrades.com/
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| AMERICAN RIVER COMMON FEATURES 2016 |
| �SACramento River East Levee (SREL) Contract 2 Improvements |
| sREL Contract 2 - schedule |
| Srel contract 2 REMAINING EFFORTS |
| SREL CONTRACT 2 OVERVIEW |
| SREL CONTRACT 2 OVERVIEW |
| Reach 4 JET GROUT CUTOFF WALL |
| Reach 4 JET GROUT CUTOFF WALL |
| Reach 5 & 6: OPTION 1 JET GROUT Cutoff Wall |
| Reach 5 & 6: JET GROUT Cutoff Wall |
| Reach 4, 5, & 6 STAGING Areas |
| Slide Number 15 |
| Reach 13 SB CUTOFF WALL |
| Reach 13 STAGING Area |
| Reach 15, 16, & 17 CUTOff Wall |
| Phase II Cutoff Wall Trench Stability |
| ReachES 15-17 SUMP 63 |
| Slide Number 21 |
| SREL C2 – LEVEE access points |
| Slide Number 23 |
| Approximate quantities |
| SS&O ENVIRONMENTAL |
| �regional overview |
| REGIONAL OVERVIEW |
| SYSTEMATIC OVERVIEW – CALTRANS PROJECT |
| �Contracting |
| HOW TO OBTAIN SOLICITATIONS |
| UNIQUE CONTRACT ASPECTS |
| Questions/comments/concerns… |