This document provides details on Amendment 0003 to a federal solicitation for construction services. The amendment extends the bid response date from December 10th to December 15th for a project to construct approximately 1.8 miles of seepage cutoff walls along the Sacramento River East Levee. Work will include installation of soil-bentonite, slag cement-cement-bentonite, and jet grout cutoff walls using both open-trench and deep soil-mixing methods. Additional scope involves relocating utilities, modifying relief wells, replacing a sump, and removing contaminated soils. Nighttime work is authorized for jet grout cutoff walls only. All construction must be completed by December 2021 with levee reconstruction finished by September 30th. The solicitation is valued between $25-100 million and will proceed unrestricted using contractors from the Pre-Qualified Sources List. The U.S. Army Corps of Engineers District Sacramento office will issue the invitation for bids on or around October 30th.

View the file

Other files

File Type Posted
Bid Abstract.pdf PDF
Amendment 0004 - Pricing Schedule.pdf PDF
Amendment 0004 - Summary of Changes.pdf PDF
Amendment 0004 - Specification Revision.pdf PDF
Amendment 0004.pdf PDF
Amendment 0004 - Revised Drawing.pdf PDF
Amendment 0003 - Specification ATTACHMENTS.pdf PDF
Amendment 0003 - Specifications.pdf PDF
Amendment 0003 - Summary.pdf PDF
Amendment 0003 - Drawings.pdf PDF
Amendment 0002 - Revised Drawings.pdf PDF
Amendment 0002.pdf PDF
Amendment 0002 - Specifications ATTACHMENTS.pdf PDF
Amendment 0002 - Revised 2342 Specifications.pdf PDF
Amendment 0002 - Revised Pricing_Schedule.pdf PDF
Amendment 0002 - Summary.pdf PDF
Site Visit Sign-In Sheet.pdf PDF
ARCF SREL C2 Site Visit 10NOV20.pdf PDF
Solicitation W9123821B0001.pdf PDF
Amendment 1.pdf PDF
Site Visit Map.pdf PDF
Attachment 3 - Drawings.10.29.2020.pdf PDF
Attachment 2 - Specifications_ATTACHMENTS_Part 5 of 5.pdf PDF
Attachment 2 - Specifications_ATTACHMENTS_Part 1 of 5.pdf PDF
Attachment 1 - Specifications_10.23.2020.pdf PDF
Attachment 7 - Pre-Award Survey.pdf PDF
Attachment 2 - Specifications_ATTACHMENTS_Part 2 of 5.pdf PDF
Attachment 6 - Past Performance Questionnaire.pdf PDF
Attachment 5 - Pricing Schedule.pdf PDF
Attachment 2 - Specifications_ATTACHMENTS_Part 4 of 5.pdf PDF
Attachment 4 - Wage Determination.CA20200007.10.9.2020.pdf PDF
Solicitation W9123821B0001.pdf PDF
Attachment 2 - Specifications_ATTACHMENTS_Part 3 of 5.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Extend the bid opening

2) Post revisions of the specif ications

3) Post revisions to the draw ings

4) Post additional specification attachments

5) One final question/answ er All changes are listed on the summary page for this amendment.

No other changes are made or implied.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Dec-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123821B0001

X 9B. DATED (SEE ITEM 11)

30-Oct-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Dec-2020

CODE

US ARMY CORPS OF ENGINEERS, SACRAMENTO

CONTRACTING DIVISION

1325 J STREET

SACRAMENTO CA 95814-2922

W91238 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123821B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

ADDITIONAL QUESTION & ANSWER

Question: Sheet S-005, Detail B has a note that calls for HDPE wall sleeves which we are told are unavailable. Would PVC sleeves be an acceptable alternative?

Answer: The use of PVC sleeves as an alternative to HDPE is considered acceptable and we recommend the Contractor plan on requesting a variance at time of submittal for the subject feature.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 10-Dec-2020 10:00 AM to 15-Dec-2020 10:00 AM.

(End of Summary of Changes)