This document contains a draft performance work statement and sources sought synopsis for an optimized remediation contract at Hill Air Force Base in Utah. The Army Corps of Engineers is seeking information from businesses interested in a potential ten-year firm-fixed-price contract to conduct environmental remediation activities at 23 Installation Restoration Program sites and two Military Munitions Response Program sites. Services will include environmental services, minor construction, and architecture and engineering. Responses are requested by March 29, 2019 to provide company information, capability statements, and example project details. The resulting contract is expected to be awarded using best value tradeoff procedures.
3. Optimization Benefit Template_190520_MD_190710
View the file
Other files for this federal contract opportunity
Show all 50
Optimized Remediation Contract for Hill AFB, UT has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPTIMIZATION EXAMPLES
AFIID_SITEID_CPSMR##_OB##-MMMYYYY
(e.g., MOODY_OT012_CPSMR12_OB01-DEC2020) Installation Name: (e.g., Moody AFB) Site ID: (e.g., OT012) Reporting Period: (e.g., 1 May 2020 – 30 April 2021)
Site Performance Objective at the Time of Contract Award:
| Reduce LCC & RA-O | |
| ☐ | Reduce LCC & LTM |
| ☐ | OES |
| ☐ | Alternate Objective |
| ☐ | Other Site Categories |
| ☐ |
Optimization activities are defined as any remedial activities and performance monitoring above and beyond what is required to maintain compliance in accordance with an approved decision document. Comment by Sam Yoon: Peaches will find O&M language from PWS.
Optimization Activities Implemented:
1. Describe specific details of optimization activities (see Key Optimization Elements)
Optimization Outcome(s):
1. Results in: a) reduction in contaminant mass, b) reduction in contaminant concentrations,
c) reduction in LCC, or d) any combination of any activities prompting acceleration to RC.
2. Provide supporting information for optimization activities using tables, plots or figures, and/or photos.
3. Identify the need for changes to decision document (e.g., Explanation of Significant Differences [ESD], ROD Amendment [RODA]) to improve the remedy efficiency and/or shorten remedy duration to achieve endpoint.
Issues/Obstacles Encountered:
1. Describe issues that could impact schedule.
Planned Optimization Activities for Next Reporting Period (including Potential Issues):
1. Describe planned optimization activities (see Key Optimization Elements)
2. Identify activities that would shorten restoration life cycle.
Key Optimization Elements:
· Site Understanding – Updating conceptual site model (CSM) to better understand site conditions
· Design Optimization Review – Reviewing design of selected remedies to effectively target contaminant source(s) and contaminant plume based on site conditions
· Remedy Process Optimization – Enhancing remedy effectiveness or efficiency to accelerate remediation timeline; i.e., Operations & Maintenance
· Monitoring Optimization – Optimizing number and location of monitoring wells and/or minimizing sampling frequency
OPTIMIZATION EXAMPLES
Site Understanding:
· Identify data gaps
· Use real-time measurements
· Sequence activities focusing on source control first
· Conduct strategic sampling
Design Optimization Review
· Conduct design optimization reviews to evaluate remedy selected and ensure streamlined remedial action operations
· Address challenges associated with source uncertainties and/or plume uncertainties by the selected remedy as designed
· Add new nested wells with shortened well screens
Remedial Process Optimization
| Operations |
| In Situ Treatments (e.g., Enhanced Reductive Dechlorination [ERD], Monitored Natural Attenuation [MNA], Permeable Reactive Barrier [PRB], In Situ Chemical Oxidation [ISCO]) |
· Contaminant footprint reductions
· Recirculation of treated extracted groundwater through in situ bioreactors with treated water
· Application of phytoremediation where appropriate (regulatory agency approval is required for new remedial alternative(s))
Ex Situ Treatments (e.g., Pump and Treat [P&T], Air Sparging [AS], Soil Vapor Extraction [SVE])
· >90% uptime with 99.99% off-gas treatment before discharge to the atmosphere
· Change from energy-intensive thermal/catalytic converter to carbon adsorption to treat off-gas
· Transition of low mass recovery for an existing P&T system to passive management systems (regulatory agency approval is required for new remedial alternative[s])
Ex Situ Treatment (e.g., Light Non-Aqueous Phase Liquid [LNAPL] Recovery)
· Evaluation for point-of-termination for product recovery when reaching to asymptotic recovery
· Use of LNAPL transmissivity data to evaluate LNAPL recoverability
· Evaluation of Natural Source Zone depletion (NSZD) rates
| Maintenance |
| In Situ Treatments (e.g., ERD, MNA, PRB, ISCO) |
· Few optimization opportunities
Ex Situ Treatments (e.g., P&T, AS, SVE)
· Appropriate process monitoring (e.g., pressure, flowrates, O2/CO2, energy consumptions) to minimize downtimes and prevent system failure
· Maintain uninterrupted system operation
· Maintain and replace aging infrastructure to improve remedy efficiency, avoiding well fouling, pump and filter replacements as appropriate
· Modification of extraction operations from steady rates to pulsed operation or variable frequency/adjustable speed driver use Ex Situ Treatment (e.g., LNAPL Recovery)
· Maintain aging infrastructure to improve remedy efficiency, avoiding well fouling, pump and filter replacements as appropriate
· Review process monitoring (operation) performance and identify the source that is less efficient
· Make necessary changes, as appropriate and required, to overcome site-specific conditions that affected performance
Monitoring Optimization
| Performance Monitoring |
| · Use decision logic and decision support tools to manage and track remedy progress (e.g., Monitoring and Remediation Optimization System [MAROS]) |
· Progress may be on track, but evaluate chlorinated compound degradation pathways or Edible Vegetable Oil partitioning by Compound-specific Isotope Analysis
· Progress may be on track, but evaluate a potential contaminant rebound after injectant is depleted
· Review performance monitoring data to evaluate the effectiveness and appropriateness of key performance metrics/standards
· Change from active remediation to natural attenuation
| Compliance |
| · Document decision to comply with alternative performance expectations and goals, if all remedial alternatives fail to achieve performance expectations and if remedial technologies are more harmful than the site conditions |
· Revisit Applicable or Relevant and Appropriate Requirements (ARARs), Remedial Action Objectives (RAOs), and the selected remedy in the context of updated information and performance monitoring data
| Data Management |
| · Improved data management including improving data management planning, data acquisition, data processing, data analysis (using 3-D visualization analysis), data preservation and storage, and data publication and sharing. |
References AFCEC. 2014. Optimizing Remedies with Performance-Based Contracts. Presented by. Dr. Kent Glover. AFCEC/CZTE. Presented at FRTR Meeting. November.
ITRC. 2004. Remediation Process Optimization: Identifying Opportunities for Enhanced and More Efficient Site Remediation NAVFAC. 2017. Portfolio Optimization (P-OPT) Review of the Navy’s IRP Site- Phase I Overview and Findings. Open Environmental Restoration Resource (OER2) Webinar. Presented by NAVFAC Environmental Restoration Program. August 23.
U.S. EPA. 2017. Superfund Optimization Progress Report 2011-2015. Office of Land and Emergency Management. EPA-542-R-17-002. June.