Am_4_-_Attach_16_VOL_3_S-003_26MAY2016.pdf
PDF 64 KB Posted
- Attached to
- AIT Barracks- Phase III, Ft. Lee, Virginia Federal contract opportunity
- Solicitation number
- W91236-16-R-0010
About this file
AM 4 - ATTACH 16 VOL 3_S-003_26MAY2016
View the file
Other files for this federal contract opportunity
Show all 50
AIT Barracks- Phase III, Ft. Lee, Virginia has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STRUCTURAL TESTING AND SPECIAL INSPECTIONS
TABLE 1704.3 A) REQUIRED VERIFICATION AND INSPECTION OF STRUCTURAL STEEL AND COLD FORMED METAL FRAMING CONSTRUCTION
VERIFICATION AND INSPECTION CONTINUOUS PERIODIC REFERENCED STANDARD
IBC
REFERENCE
APPLICABLE ASTM MATERIAL
SPECIFICATIONS; AISC
ASD, SECTION A3.4; AISC
LRFD, SECTION A3.3
X
AISC LRFD
SECTION M2.5 1704.3.3X
ASTM A 6 OR
ASTM A 568
ASTM A 6 OR ASTM A 568 1708.4
X
AISC, ASD,
SECTION A3.6;
AISC LRFD,
SECTION A3.5
X
AWS D1.1 1704.3.1
X
X
1704.3.2
IMPLEMENT AN INSPECTION, TESTING AND QUALITY CONTROL PROGRAM FOR THE CONSTRUCTION PHASE OF THE PROJECT AS OUTLINED ON THIS DRAWING. THE CONTRACTOR WILL ENGAGE AN APPROVED TESTING/INSPECTION AGENCY TO PROVIDE SPECIAL INSPECTION AND TESTING AS REQUIRED. IT IS THE CONTRACTORS RESPONSIBILITY TO COORDINATE AND SCHEDULE WITH THE TESTING/INSPECTION AGENCY DEFINITIONS AND REQUIREMENTS ARE TO BE IN ACCORDANCE WITH SECTION 1701 OF THE INTERNATIONAL BUILDING CODE. FAILURE TO COMPLY WILL RESULT IN REMOVAL AND RECONSTRUCTION OF ANY STRUCTURAL ELEMENTS NOT VERIFIED, TESTED, OR INSPECTED. PROVIDE COPY OF ALL INSPECTION REPORTS TO ENGINEER OF RECORD REFER TO PROJECT SPECIFICATION SECTION 01410, SPECIAL INSPECTIONS AND STRUCTURAL TESTING FOR ADDITIONAL INFORMATION.
1. MATERIAL VERIFICATION OF HIGH-STRENGTH BOLTS, NUTS & WASHERS:
A. IDENTIFICATION MARKINGS TO CONFORM TO ASTM STANDARDS
SPECIFIED IN THE APPROVED CONSTRUCTION DOCUMENTS.
B. MANUFACTURER'S CERTIFICATE OF COMPLIANCE REQUIRED.
2. INSPECTION OF HIGH-STRENGTH BOLTING:
A. BEARING-TYPE CONNECTIONS.
3. MATERIAL VERIFICATION OF STRUCTURAL STEEL:
A. IDENTIFICATION MARKINGS TO CONFORM TO ASTM STANDARDS
SPECIFIED IN THE APPROVED CONSTRUCTION DOCUMENTS.
B. MANUFACTURER'S CERTIFIED MILL TEST REPORTS.
4. MATERIAL VERIFICATION OF WELD FILLER MATERIALS:
A. IDENTIFICATION MARKINGS TO CONFORM TO AWS SPECIFICATION IN
THE APPROVED CONSTRUCTION DOCUMENTS SPECIFICATION IN THE
APPROVED CONSTRUCTION DOCUMENTS
B. MANUFACTURER'S CERTIFICATE OF COMPLIANCE REQUIRED.
5. INSPECTION OF WELDING:
A. STRUCTURAL STEEL:
1. SINGLE-PASS FILLET WELDS 1/4" AND SMALLER
2. WELDING OF ELEMENTS WITHIN SHEAR WALLS
6. INSPECTION OF STEEL FRAME JOINT DETAILS FOR COMPLIANCE WITH APPROVED
CONSTRUCTION DOCUMENTS:
A. DETAILS SUCH AS BRACING AND STIFFENING.
B. MEMBER LOCATIONS.
C. APPLICATION OF JOINT DETAILS AT EACH CONNECTION.
D. SCREW ATTACHMENT, BOLTING, ANCHORING WITHIN SHEAR WALLS.
TABLE 1704.4 REQUIRED VERIFICATION AND INSPECTION OF CONCRETE CONSTRUCTION
1. INSPECTION OF ANCHORS INSTALLED IN HARDENED CONCRETE ACI 318:
3.8.6, 8.1.3, 21.2.8X 1912.1
2. VERIFYING USE OF REQUIRED DESIGN MIX ACI 318: CH. 4,
5.2-5.4X
1904.2.2 1913.2 1913.3
3. AT THE TIME FRESH CONCRETE IS SAMPLED TO FABRICATE SPECIMENS FOR
STRENGTH TESTS, PERFORM SLUMP AND AIR CONTENT TESTS, AND DETERMINE
THE TEMPERATURE OF THE CONCRETE
ASTM C 172
ASTM C 31
ACI 318: 5.6, 5.8
X 1913.10
4. INSPECTION FOR MAINTENANCE OF SPECIFIED CURING
TEMPERATURE AND TECHNIQUES.
X ACI 318: 5.11-5.13 1913.9
5. PROGRESSIVE COLLAPSE
A. SLAB REINFORCING PLACEMENT
B. WELDING OF REINFORCING PRIOR TO CONCRETE PLACEMENT
X X
UFC 4-023-03
14 JULY 2009
TABLE 1704.7 REQUIRED VERIFICATION AND INSPECTION OF SOILS
- 1704.7
1. VERIFY MATERIALS BELOW FOOTINGS ARE ADEQUATE TO ACHIEVE THE
DESIGN BEARING CAPACITY. X
- 1704.7
2. VERIFY EXCAVATIONS ARE EXTENDED TO PROPER DEPTH AND HAVE
REACHED PROPER MATERIAL. X
- 1704.7
3. PERFORM CLASSIFICATION AND TESTING OF CONTROLLED FILL MATERIALS.
X
X 1704.7
4. VERIFY USE OF PROPER MATERIALS, DENSITIES AND LIFT THICKNESSES
DURING PLACEMENT AND COMPACTION OF CONTROLLED FILL. -
- 1704.7
5. PRIOR TO PLACEMENT OF CONTROLLED FILL, OBSERVE SUBGRADE AND
VERIFY THAT SITE HAS BEEN PREPARED PROPERLY. X
X
X
LINTEL SCHEDULE
MAX MASONRY
OPENING
WALL
THICKNESS LINTEL SHAPE
1'-0" BRICK VENEER NO LINTEL NO LINTEL
3'-0" BRICK VENEER L4 X 3 1/2 X 5/16"(LLV)
6'-6" BRICK VENEER L5 X 3 1/2 X 3/8"(LLV)
9'-6" BRICK VENEER L6 X 3 1/2 X 3/8"(LLV)
LINTEL NOTES:
1. BEAR LINTELS 8" MINIMUM
2. PROVIDE LINTELS AT ALL BRICK OPENINGS UON.
3. CLEAN AND PAINT LINTELS WITH 2-PART EPOXY COATING.
4. FOR STORY RELIEF ANGLE SEE PLANS AND SECTIONS
TYPE
REQUIRED STEEL DECK PROPERTIES SCHEDULE
GAUGE
REMARKS
SIDE LAP
FASTENING
ATTACHMENT
MIN I (IN )
MIN S (IN )
RIB SPACING
DEPTH (IN)
D2: ROOF DECK
1.747 P: 0.887 N: 0.752
8" 3"
#12 SDS 36/4
#10 SDS @ 10 PER SPAN
CANOPY
PROVIDE ALL
NECESSARY
CLOSURE PIECES
1.58 P: 1.013 N: 1.013
12" 3"
5/8 PUDDLE 36/4 TRASVERSE, 4" OC PARALLEL
#10 SDS @ 10 PER SPAN, 12" MAX
REINFORCEMENT NOT APPLICABLE
0.169
P: 0.186 N: 0.192 6"
1 1/2"
#12 SDS 36/7
#10 SDS @ 4 PER SPAN
BARRACKS ROOF
PROVIDE ALL NECESSARY
CLOSURE PIECES
NOT APPLICABLE
D1: ROOF DECK
SEE 6/S-302
D3: VAULT CEILING 6" NW CONC (9" TOTAL)
SHORE PER MANUFACTURER
RECOMMENDATIONS
PROVIDE ALL
NECESSARY
CLOSURE PIECES
4000 PSI CONCRETE SLAB
1.58 P: 1.013 N: 1.013
12" 3"
#12 SDS 36/4 TRASVERSE, 4" OC PARALLEL
#10 SDS @ 10 PER SPAN
SEE S-108
D4: ELEVATED SLAB 3 1/2" NW CONC (6" TOTAL)
ALL ELEVATED FLOOR SLABS UON
SHORE PER MANUFACTURER
RECOMMENDATIONS
PROVIDE ALL
NECESSARY
CLOSURE PIECES
4000 PSI CONCRETE SLAB
3 2 3
2 2 2
3 2 3 a a a a a a a
RIDGE
C&C PRESSURES - HI ROOF PARTS A, B, C
GCp
ZONE 2
AREA ≤ 10 +0.5
-1.7
PSF NET UPLIFT
+0.5
-0.9
+0.5
-2.6
+0.3AREA ≥ 100
-1.2
+0.3
-0.8
+0.3
-2.0
C&C PRESSURES - LOW ROOF PARTS B, D
GCp
ZONE 2
AREA ≤ 10 +0.3
-1.8
PSF NET UPLIFT
+0.3
-1.0
+0.3
-2.8
+0.2AREA ≥ 100
-1.1
+0.2
-0.9
+0.2
-1.1 a = 6' - 0"
INTERPOLATE FOR AREA VALUES BETWEEN 10 AND 100.
US Army Corps of Engineers ®
SHEET OF
SHEET ID
U S
A R
M Y
C O
R
PS
O F
EN
G
IN
EE
R S
D R
A W N
B Y:
D
ES
IG
N
ED
B
Y:
SU
B M
IT
TE
D B
Y:
SI
ZE
C H
E C
KE
D B
Y:
AN
S I
'D
FI
LE
N
AM
E:
IS
SU
E D
AT
E :
FI
LE
N U
M
BE
R
1 2 3 4 5
D
C
B
A
28012
S-003
VOLUME 3
SC
H
ED
U
L E S
A
IT
B A
R
RA
CK
S
CO
M
PL
EX
PH
A
SE
3 0
M
A N
N O
R
FO
LK
D
I S
TR
IC
T
N O
R
FO
LK
, V
A
JP
J
C
ES
LW
M
LW
M
A
PR
PR
O
JE
C T
N U
M
BE
R
C O
N
TR
AC
T
N O
S S -
3-
6- 0 2
-0
B a ck ch ec k
F O R
T L E
E, V
I R G
IN
I A
WALL FOOTING SCHEDULE
MARK WIDTH THICKNESS LONGITUDINAL TRANSVERSE NOTES
WF1 3' - 0" 1' - 2" 3 - #5 CONT #4 @ 12" OC
WF2 3' - 0" 0' - 8" 3 - #5 CONT #4 @ 12" OC THICKENED SLAB. INDICATED THICKNESS
BELOW BASE OF SURROUNDING SLAB.
WF3 10' - 0" 0' - 8" 3 - #5 CONT #4 @ 12" OC THICKENED SLAB. INDICATED THICKNESS
BELOW BASE OF SURROUNDING SLAB.
COLUMN SCHEDULE
MARK SIZE BASEPLATE
C1 HSS5-1/2X5-1/2X3/8 BP1
C2 HSS12X12X1/2 BP2
COLUMN FOOTING SCHEDULE
MARK
DIMENSIONS
DEPTH REINFORCEMENT AND NOTESWIDTH LENGTH
F1 6' - 0" 6' - 0" 2' - 0" 12 - #5 EW T&B
F2 12' - 0" 6' - 0" 2' - 0" #5 @ 6" OC EW T&B
F3 36' - 4" 10' - 7" 2' - 0" #5 @ 1'-0" OC EW T&B
F4 18' - 0" 6' - 0" 2' - 0" #5 @ 6" OC EW T&B
1 1/2" = 1'-0"
C&C WIND ROOF DIAGRAM
FOR BASEPLATES SEE S-303
M
AR
K D
ES
C
R
IP
TI
O
N D
AT
E
R
EV
IS
ED
B
Y
AM
EN
D
M
EN
T
M
AY
| Sheets |
| S-003 - SCHEDULES |
File details come from the government source that posted it. Updated .