DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 1 of 31
CONTRACT DATA REQUIREMENTS LIST
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
A
C. CATEGORY TDP TM_______ OTHER __X_
D. SYSTEM/ITEM
Aerosol and Vapor Chemical Agent Detector (AVCAD)
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
Design Review Information Package (DRIP)
3. SUBTITLE
Preliminary Design Review Data Package
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81757A
5. CONTRACT REFERENCE
C.3.1.8.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
No
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
15 calendar days prior to PDR
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
5 calendar days after receipt of Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/. Only include sections 5 and 6.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is included in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract Specialist, Jemel Hogan, jemel.m.hogan.civ@mail.mil and COR, Mobil Kolbon, mobil.w.kolbon.civ@mail.mil .
SFAE-CBD-NBC-S
CCAP-SCE 0 1 0
15. TOTAL
17. PRICE GROUP
18. ESTIMATED TOTAL PRICE
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C. CATEGORY TDP TM_______ OTHER _x__
A002
2. TITLE OF DATA ITEM
Design Review Information Package (DRIP)
3. SUBTITLE
Critical Design Review Data Package
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81757A
5. CONTRACT REFERENCE
C.3.1.8.2
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
15 calendar days prior to CDR
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/. Only include sections 8 and 9.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is included in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 14 Submit in electronic format in Microsoft Office 2013 and PDF to Contract
G. PREPARED BY
Mobil Kolbon
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
J. Date
DRAFT
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 2 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
A003
2. TITLE OF DATA ITEM
Interface Control Document (ICD)
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81248B
5. CONTRACT REFERENCE
C.3.2.5
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
30 Calendar Days Prior to Each Hardware Delivery
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
10 calendar days after receipt of Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is included in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. Revise and re-submit for any changes to the Government approved file or as requested by the Government.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
A. CONTRACT LINE ITEM NO. B. EXHIBIT
A004
2. TITLE OF DATA ITEM
Contractor’s Corrective Action Plan
DI-MGMT-80501
5. CONTRACT REFERENCE
C.10.9.3.4
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
See Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
N/A
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
Additionally, the report shall contain financial expenditures for the current month and cumulatively by work breakdown structure.
9. Distribution guidance is included in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
12. Submit 15 calendar days after Systemic Defect Coverage is invoked per PWS pagragraph C.19.3.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
DCMA 0 1 0
Mobil Kolbon
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
J. DATE
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 3 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
A005
2. TITLE OF DATA ITEM
Vulnerability Scan Compliance (VSC) Report
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81842
5. CONTRACT REFERENCE
C.3.2.6.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
No
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
60 Calendar Days Prior to Each Hardware Delivery
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
See Block 16 Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is included in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
13. Final submission shall be 15 Calendar Days Prior to Each Hardware Delivery.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
A006
2. TITLE OF DATA ITEM
EQUIPMENT FAILURE INFORMATION
REPORT (EFIR)
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80359
5. CONTRACT REFERENCE
C.10.9.2.3
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
No
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is included in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
12. Submit after the warranty repair finish
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
J. Date
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 4 of 31
(1 Data Item)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
B001
2. TITLE OF DATA ITEM
Presentation Material
3. SUBTITLE
Agenda & Read-Ahead Information
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMN-81373
5. CONTRACT REFERENCE
C.3.1.2, C.3.1.6, C.3.1.7, C.3.1.8.1, C.3.1.8.2, C.3.1.9,C.3.2.6, C.5.1.3, C.5.3.2, C.5.7.6, C.16.2
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
No
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
See Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 2 calendar days after receipt.
9. Distribution guidance is included in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. & 12. Meeting agendas and read-ahead information shall be submitted 7 calendar days prior to meetings or reviews. Agendas and read-ahead information for telecons shall be submitted 48 hour in advance.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 5 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B002
2. TITLE OF DATA ITEM
Report, Record of Meeting/Minutes
3. SUBTITLE
Meeting Minutes
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMN-81505
5. CONTRACT REFERENCE
C.3.1.2, C.3.1.6, C.3.1.7, C.3.1.8.1, C.3.1.8.2, C.3.1.9, C.3.2.6, C.5.1.3, C.5.3.2, C.5.7.6, C.16.2
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
See Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. & 12. Meeting minutes shall be submitted within 5 calendar days following a meeting or review. Meeting minutes for telecons shall be submitted 48 hours after.
14 Submit in electronic format in Microsoft Office 2013 and PDF to Contract
B003
2. TITLE OF DATA ITEM
Integrated Program Management Report
(IPMR)
3. SUBTITLE
Integrated Master Schedule
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-81861A
5. CONTRACT REFERENCE
C.3.1.4, C.3.2.9.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
Start of Work Meeting
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
See block 16 Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
Format 6 applies
8. The Government will review and provide comments at Integrated Baseline Reviews and monthly as to reporting level, content, and dependencies. Contractor shall address Government comments in subsequent submissions.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
13. Submit revised drafts 10 Calendar Days receipt of Government comments and as needed.
14 Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 6 of 31
(1 Data Item)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B004
2. TITLE OF DATA ITEM
Status Report
3. SUBTITLE
Monthly Status Report
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80368A
5. CONTRACT REFERENCE
C.3.1.5.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
MONTHLY
12. DATE OF FIRST SUBMISSION
By the 10th of the month following contract award
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil.
Additionally, the report shall contain a monthly spend plan, and financial expenditures for the current month and cumulatively by work breakdown structure.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
Mobil Kolbon
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 7 of 31
(1 Data Item)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B005
2. TITLE OF DATA ITEM
Program Protection Implementation Plan (PPIP)
DI-ADMN-81306
5. CONTRACT REFERENCE
C.3.1.10.1, C3.1.10.2
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
No
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
30 Calendar Days After Contract Award
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. Revise and re-submit for any changes to the Government approved report or as requested by the Government.
14 Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 8 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
1. DATA ITEM NO
B006
2. TITLE OF DATA ITEM
Operation Security (OPSEC) Plan
DI-MGMT-80934C
5. CONTRACT REFERENCE
C.3.1.10.6
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
15 days after receipt of Government comments
Draft Reg Repro
16. REMARKS.
4. The DID may be obtained at: http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 15 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
12. & 13. Submit 90 calendar days after contract award.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
B007
2. TITLE OF DATA ITEM
Systems Engineering Management Plan (SEMP)
DI-SESS-81785A
5. CONTRACT REFERENCE
C.3.2.1, C.3.2.8, C.5.4.4, C.5.5
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
60 calendar days after contract award
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. Revise and re-submit for any changes to the Government approved report or as requested by the Government.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 9 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B008
2. TITLE OF DATA ITEM
Technical Report – Study/Services
3. SUBTITLE
Requirements Compliance Matrix (RCM)
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
C.3.2.2
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
30 calendar days after contract award
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.2.
(http://www.dtic.mil/whs/directives/)
10. Revise and re-submit for any changes to the Government approved matrix or as requested by the Government.
14 Submit in electronic format in Microsoft Office 2013 and PDF to Contract
B009
2. TITLE OF DATA ITEM
Configuration Management Plan
(CMP) (MIL-STD-3046)
DI-SESS-81875
5. CONTRACT REFERENCE
C.3.2.11.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
60 calendar days after contract award
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. Revise and re-submit for any changes to the Government approved report or as requested by the Government.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 10 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C. CATEGORY TDP X TM_______ OTHER ___
B010
2. TITLE OF DATA ITEM
Engineering Change Proposal
(ECP)
DI-SESS-80639D
5. CONTRACT REFERENCE
C.3.2.11.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Resubmission is not required unless requested by the Configurarion Control Board.
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 & 12 Submit immediately when design/process changes that impact the spares and the form, fit and function of the approved AVCAD baseline configuration are proposed.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 11 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C. CATEGORY TDP x TM_______ OTHER ___
B011
2. TITLE OF DATA ITEM
Notice of Revisiion (NOR)
DI-SESS-80642D
5. CONTRACT REFERENCE
C.3.2.11.3,
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Resubmission is not required unless requested by the CCB
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 & 12 Submit immediately when design/process changes that impact the spares and the form, fit and function of the approved AVCAD baseline configuration are proposed.
14 Submit in electronic format in Microsoft Office 2013 and PDF to Contract
B012
2. TITLE OF DATA ITEM
Request for Variance (RFV)
3. SUBTITLE
Request for Deviation (RFD)
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80640D
5. CONTRACT REFERENCE
C.3.2.11.4
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Resubmission not required unless requested by the CCB
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 & 12 Submit immediately when design/process changes that impact the spares and the form, fit and function of the approved AVCAD baseline configuration are proposed.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 12 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C. CATEGORY TDP x TM_______ OTHER ___
B013
2. TITLE OF DATA ITEM
Configuration Status Accounting (CSA) Information
DI-SESS-81253C
5. CONTRACT REFERENCE
C.3.2.11.5
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 & 12 Submit immediately when design/process changes that impact the spares and the form, fit and function of the approved AVCAD baseline configuration are proposed.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 13 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C. CATEGORY TDP TM_______ OTHER __x_
B014
2. TITLE OF DATA ITEM
Safety Assessment Report (SAR)
DI-SAFT-80102C
5. CONTRACT REFERENCE
C.3.2.12.1.2
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
30 calendar days prior to start of Government testing.
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments.
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
B015
2. TITLE OF DATA ITEM
Assessment of Manufacturing Risk and Readiness
3. SUBTITLE
Manufacturing Readiness Assessment (MRA)
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81974
5. CONTRACT REFERENCE
C.3.2.9.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
R/ASR
12. DATE OF FIRST SUBMISSION
See Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
Contractor format.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. Revise and re-submit for any changes to the Government approved matrix or as requested by the Government.
12. Contractor shall submit incremental MRAs 15 calendar days prior to Design Reviews.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 14 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C. CATEGORY TDP TM_______ OTHER x
B016
2. TITLE OF DATA ITEM
Manufacturing Plan
DI-MGMT-81889
5. CONTRACT REFERENCE
C.3.2.892
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 & 12 Submit immediately when design/process changes that impact the spares and the form, fit and function of the approved AVCAD baseline configuration are proposed.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
B017
2. TITLE OF DATA ITEM
Quality Assurance Program Plan
(QAPP)
DI-QCIC-81794 NOT 1
5. CONTRACT REFERENCE
C.3.2.10.2, C.3.2.10.4
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
30 calendar days prior to start of Government testing.
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments.
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 15 of 31
(2 Data Items)
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B018
2. TITLE OF DATA ITEM
Work Breakdown Structure (WBS)
3. SUBTITLE
Work Breakdown Structure
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-80639D
5. CONTRACT REFERENCE
C.3.1.4
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Start of Work Meeting
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
4/5/17
I. APPROVED BY
Lou Kosydar
4/5/17
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B019
2. TITLE OF DATA ITEM
Program management
3. SUBTITLE
Integrated Master Plan (IMP)
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
C.3.1.4
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
60 Days After Contract Award
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
4/5/17
I. APPROVED BY
Lou Kosydar
4/5/17
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 16 of 31
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C
C001
2. TITLE OF DATA ITEM
Technical Report – Study/Services
Interim Allowance List.
DI-MISC-80508B
5. CONTRACT REFERENCE
C.5.6.4.4
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 & 12.The Contractor shall provide the Interim Allowance List 30 calendar days prior to the Provisioning Conference Review. Should this data deliverable require revision after initial delivery, the Contractor shall update and redeliver.
14. Submit in editable electronic format in Microsoft Office 2013 and PDF to Contract
C002
2. TITLE OF DATA ITEM
Provisioning Parts List (PPL)
DI-SESS-81715
5. CONTRACT REFERENCE
C.5.6.3.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments.
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 Submit immediately when design/process changes that impact the spares and the form, fit and function of the approved AVCAD baseline configuration are proposed.
12.The Contractor shall provide a PPL thirty (30) calendar days prior to the Provisioning Conference Review. Should this data deliverable requirerevision after initial delivery, the Contractor shall update and redeliver.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
17. PRICE GROUP 18. ESTIMATED TOTAL PRICE
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 17 of 31
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C003
2. TITLE OF DATA ITEM
Logistics Product Data Summaries
LSA-004, Maintenance Allocation Chart
DI-SESS-81759A
5. CONTRACT REFERENCE
C.5.6.3.1.8
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 Submit immediately when design/process changes affect the current baseline.
12. The Contractor shall provide Logistics Product Data Summaries 60 calendar days before Production Qualification Test (PQT)
14. Contractor format is not acceptable. Submit in electronic format in an editable electronic format, Microsoft Office 2013 and PDF to Submit in electronic format in Microsoft Office 2013 and PDF to Contract Specialist, Jemel Hogan, jemel.m.hogan.civ@mail.mil and COR, Mobil Kolbon, mobil.w.kolbon.civ@mail.mil .
in format prescribed by MIL-STD-40051-2C and supported by approved LPD.
C004
2. TITLE OF DATA ITEM
Logistics Product Data Summaries
3. SUBTITLE
Functional Group Codes (FGC)
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81759A
5. CONTRACT REFERENCE
C.5.6.3.1.9
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments.
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 Submit immediately when design/process changes that impact the current FGC baseline.
12.The Contractor shall provide a FGC thirty (30) calendar days prior to the Provisioning Conference Review. Should this data deliverable requirerevision after initial delivery, the Contractor shall update and redeliver.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 18 of 31
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
C005
2. TITLE OF DATA ITEM
Engineering Data for Provisioning (EDFP)
DI-SESS-81874
5. CONTRACT REFERENCE
C.5.6.3.2
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 Submit immediately when design/process changes the current baseline for SDFP and EDFP.
12.The Contractor shall provide the SDFP and EDFP thirty (30) calendar days prior to the Provisioning Conference Review. Should this data deliverable require revision after initial delivery, the Contractor shall update and redeliver.
14. Submit in editable electronic format in Microsoft Office 2013 and PDF to Contract mobil.w.kolbon.civ@mail.mil .to the COR.
C006
2. TITLE OF DATA ITEM
Technical Report - Study/Services
3. SUBTITLE
Selected Essential Item Stockage to Availability Method (SESAME) report
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
C.5.6.4.3
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments.
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/) 10 & 12.The Contractor shall provide the SESAME report thirty (30) calendar days prior to the Provisioning Conference Review. Should this data deliverable require revision after initial delivery, the Contractor shall update and redeliver.
14. Submit in editable electronic format in Microsoft Office 2013 and PDF to Contract
H. DATE
11/7/16
I. APPROVED BY
Lou Kosydar
DD FORM 1423-2, JUN 90 Previous editions are obsolete Page 19 of 31
FORM APPROVED
OMB No. 0704-0188
Public reporting burden for this collection is estimated to average 330 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to DoD, Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302, and to the Office of Management and Budget, Paperwork Reduction Project (0704-0188), Washington, DC 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government issuing Contracting Officer for the Contract/PR No.
Listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
D
D001
2. TITLE OF DATA ITEM
Technical Report – Study/Services
3. SUBTITLE
Integrated Product Support Plan (IPSP)
4. AUTHORITY (Data Acquisition Document No.)
DI-MISC-80508B
5. CONTRACT REFERENCE
C.5.2.1
6. REQUIRING OFFICE
JPM-NBC-CA (SFAE-CBD-NBC-S)
7. DD 250 REQ
NO
9. DIST
STATEMENT
REQUIRED
C
10. FREQUENCY
ASREQ
12. DATE OF FIRST SUBMISSION
Refer to Block 16
14. DISTRIBUTION
a. Addressee b. COPIES
FINAL
8. APP CODE
Government comments
Draft Reg Repro
16. REMARKS.
4. DID may be obtained from http://quicksearch.dla.mil/.
8. The Government will respond with comments or approval within 10 calendar days after receipt.
9. Distribution guidance is provided in DoDI 5230.24.
(http://www.dtic.mil/whs/directives/)
10. The contractor shall update the IPSP 30 days prior to Critical Design Review
(CDR).
12. The contractor shall prepare and submit original IPSP 30 days after contract award.
14. Submit in electronic format in Microsoft Office 2013 and PDF to Contract
D002
2. TITLE OF DATA ITEM
Logistic Product Data (LPD)
DI-SESS-81758A
5.…