Q As _v2_Revised.xlsx

XLSX spreadsheet 10 KB Posted

Attached to
Job Order Contract (JOC)Joint Base Lewis-McChord (JBLM), Washington
Solicitation number
W911S814R0003
Issued by

About this file

Revised Questions Answers v2

View the file

Other files

File Type Posted
Q As _v3.xlsx XLSX spreadsheet
Exhibit_35-4 _10_Nov_15.pdf PDF
Q As _v2.xlsx XLSX spreadsheet
W911S8-14-R-0003-0003.docx DOCX document
Exhibit_35-3 _10_Nov_15.pdf PDF
Exhibit_35 _10_Nov_15_.pdf PDF
W911S8-14-R-0003-0002.docx DOCX document
Site_Visit_Sign-In_Roster.pdf PDF
Exhibit_35-3 _27_Oct_15.pdf PDF
Exhibit_35-4 _27_Oct_15.pdf PDF
Q As _27_Oct_15.pdf PDF
Exhibit_35-5 _27_Oct_15.pdf PDF
W911S8-14-R-0003-0001.docx DOCX document
Exhibit_35 _27_Oct_15.pdf PDF
Exhibit_3 _1_Oct_15.pdf PDF
Exhibit_9 _1_Oct_15.pdf PDF
Exhibit_31 _1_Oct_15.pdf PDF
Exhibit_17 _1_Oct_15.pdf PDF
Exhibit_4 _1_Oct_15.pdf PDF
Exhibit_11 _1_Oct_15.pdf PDF
Exhibit_14 _1_Oct_15.pdf PDF
Exhibit_28 _1_Oct_15.docx DOCX document
Exhibit_29 _1_Oct_15.docx DOCX document
Exhibit_35-3 _1_Oct_15.pdf PDF
Exhibit_22 _1_Oct_15.pdf PDF
Exhibit_30 _1_Oct_15.docx DOCX document
Exhibit_15 _1_Oct_15.pdf PDF
Exhibit_2 _1_Oct_15.pdf PDF
Exhibit_38 _21_Aug_15.pdf PDF
Exhibit_37 _4_Sep_15.pdf PDF
Exhibit_6 _1_Oct_15.pdf PDF
Exhibit_25 _1_Oct_15.pdf PDF
Exhibit_18 _1_Oct_15.pdf PDF
Exhibit_24 _1_Oct_15.pdf PDF
Exhibit_35 _1_Oct_2015.pdf PDF
Exhibit_33 _1_Oct_15.pdf PDF
Exhibit_5 _1_Oct_15.pdf PDF
Exhibit_26 _1_Oct_15.pdf PDF
Exhibit_39 _21_Aug_15.pdf PDF
Exhibit_19 _1_Oct_15.pdf PDF
Exhibit_16 _1_Oct_15.pdf PDF
Exhibit_35-1 _1_Oct_15.pdf PDF
Exhibit_36 _4_Sep_15.pdf PDF
Exhibit_21 _1_Oct_15.pdf PDF
W911S8-14-R-0003.docx DOCX document
Exhibit_40 _1_Oct_15.docx DOCX document
Attachment_1.docx DOCX document
Exhibit_1 _1_Oct_15.pdf PDF
Exhibit_7 _1_Oct_15.pdf PDF
Attachment_2.docx DOCX document
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

#ReferenceQuestionResponse
37Section L, Para 8.1Are you wanting just that section in our proposal to have sanitized/redacted information?Amendment 0003 removed this statement to eliminate any confusion.
38Section L, Para 8.1Wanted to clarify that you do not want the entire volume to be redacted.See response to Question #37
39Can you let me know if the 2 CD’s for Volume III are requiring one of them to have the sanitized/redacted information.See response to Question #37
40Seed Project, Women's Restroom ScopeIs it just the flex duct or are we to include the rigid duct connected to the vertical riser?The only requirement of this contract is to provide the required CFM called out in the seed project SOW. Updated drawings are provided in Amendment 0003. Unfortunately the as-builts provided are the only drawings available. {REVISED RESPONSE} The seed project SOW provides the scope of the project. Each company that wishes to propose this effort provides its approach that will be taken to meet the requirement. As this is evaluation criteria for Factor 1, Subfactor D, the Government cannot provide details on how a company should or should not propose to meet this evaluation criteria.
41Seed Project, Women's Restroom ScopeDoes the owner want the 6x6 duct installed as shown in the Women’s Locker Room which is not there now?The 6x6 ductwork is assumed to be installed. All ductwork is above the ceiling so it can't be determined to be absent from the site visit. Only requirement is to provide the CFM as required per the seed project SOW; whether the contractor deems extra replacement of ductwork is necessary or not. Updated drawings are provided in Amendment 0003. Unfortunately the as-builts provided are the only drawings available. {REVISED RESPONSE} The seed project SOW provides the scope of the project. Each company that wishes to propose this effort provides its approach that will be taken to meet the requirement. As this is evaluation criteria for Factor 1, Subfactor D, the Government cannot provide details on how a company should or should not propose to meet this evaluation criteria.