Exhibit 5 Technical Specification Division 05 Metals

View the file

Other files

File Type Posted
Q As _v2_Revised.xlsx XLSX spreadsheet
Q As _v3.xlsx XLSX spreadsheet
Exhibit_35-4 _10_Nov_15.pdf PDF
Q As _v2.xlsx XLSX spreadsheet
W911S8-14-R-0003-0003.docx DOCX document
Exhibit_35-3 _10_Nov_15.pdf PDF
Exhibit_35 _10_Nov_15_.pdf PDF
W911S8-14-R-0003-0002.docx DOCX document
Site_Visit_Sign-In_Roster.pdf PDF
Exhibit_35-3 _27_Oct_15.pdf PDF
Exhibit_35-4 _27_Oct_15.pdf PDF
Q As _27_Oct_15.pdf PDF
Exhibit_35-5 _27_Oct_15.pdf PDF
W911S8-14-R-0003-0001.docx DOCX document
Exhibit_35 _27_Oct_15.pdf PDF
Exhibit_3 _1_Oct_15.pdf PDF
Exhibit_9 _1_Oct_15.pdf PDF
Exhibit_31 _1_Oct_15.pdf PDF
Exhibit_17 _1_Oct_15.pdf PDF
Exhibit_4 _1_Oct_15.pdf PDF
Exhibit_11 _1_Oct_15.pdf PDF
Exhibit_14 _1_Oct_15.pdf PDF
Exhibit_28 _1_Oct_15.docx DOCX document
Exhibit_29 _1_Oct_15.docx DOCX document
Exhibit_35-3 _1_Oct_15.pdf PDF
Exhibit_22 _1_Oct_15.pdf PDF
Exhibit_30 _1_Oct_15.docx DOCX document
Exhibit_15 _1_Oct_15.pdf PDF
Exhibit_2 _1_Oct_15.pdf PDF
Exhibit_38 _21_Aug_15.pdf PDF
Exhibit_37 _4_Sep_15.pdf PDF
Exhibit_6 _1_Oct_15.pdf PDF
Exhibit_25 _1_Oct_15.pdf PDF
Exhibit_18 _1_Oct_15.pdf PDF
Exhibit_24 _1_Oct_15.pdf PDF
Exhibit_35 _1_Oct_2015.pdf PDF
Exhibit_33 _1_Oct_15.pdf PDF
Exhibit_26 _1_Oct_15.pdf PDF
Exhibit_39 _21_Aug_15.pdf PDF
Exhibit_19 _1_Oct_15.pdf PDF
Exhibit_16 _1_Oct_15.pdf PDF
Exhibit_35-1 _1_Oct_15.pdf PDF
Exhibit_36 _4_Sep_15.pdf PDF
Exhibit_21 _1_Oct_15.pdf PDF
W911S8-14-R-0003.docx DOCX document
Exhibit_40 _1_Oct_15.docx DOCX document
Attachment_1.docx DOCX document
Exhibit_1 _1_Oct_15.pdf PDF
Exhibit_7 _1_Oct_15.pdf PDF
Attachment_2.docx DOCX document
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 05 05 23 Page 1

SECTION 05 05 23

WELDING, STRUCTURAL

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 360 (2005) Specification for Structural Steel Buildings, with Commentary

AMERICAN SOCIETY FOR NONDESTRUCTIVE TESTING (ASNT)

ASNT RP SNT-TC-1A (2006) Recommended Practice

AMERICAN WELDING SOCIETY (AWS)

AWS A2.4 (2007) Standard Symbols for Welding, Brazing and Nondestructive Examination

AWS A3.0 (2001) Standard Welding Terms and Definitions Including

Terms for Adhesive Bonding, Brazing, Soldering, Thermal Cutting and Thermal Spraying

AWS D1.1/D1.1M (2008) Structural Welding Code - Steel

AWS D1.3/D1.3M (2008) Structural Welding Code - Sheet Steel

AWS D1.4/D1.4M (2005; Errata 2005) Structural Welding Code -

Reinforcing Steel

AWS D14.1/D14.1M (2005) Welding Industrial and Mill Cranes and Other

Material Handling Equipment

AWS D14.4/D14.4M (2005) Welded Joints for Machinery and Equipment

AWS Z49.1 (2005) Safety in Welding, Cutting and Allied Processes

ASTM INTERNATIONAL (ASTM)

ASTM E 165 (2002) Standard Test Method for Liquid Penetrant

Examination

ASTM E 709 (2008) Standard Guide for Magnetic Particle Examination

1.2 DEFINITIONS

Definitions of welding terms are in accordance with AWS A3.0. The following classifications Class 1 (highest class) to Class 6 (lowest class) indicate the project's class(es) of weld joints.

SECTION 05 05 23 Page 2

1.2.1 Class 1 Weld Joints

This covers complete penetration weld joints only. These weld joints apply where failure would cause a loss of the system and/or be hazardous to personnel. Class 1 weld joints are highly stressed (dynamic and cyclic loading) and characterized as a single point of failure with no redundancy for the redistribution of stress into another member.

1.2.2 Class 2 Weld Joints

This covers both complete and partial penetration groove weld joints and fillet weld joints. These weld joints apply where failure would reduce the overall efficiency of a system but loss of the system or a hazard to personnel would not be experienced.

1.2.3 Class 3 Weld Joints

This covers both complete and partial penetration groove weld joints and fillet weld joints. These weld joints apply where failure would not affect the efficiency of a system nor create a hazard to personnel. Class 3 weld joints are connections of secondary members not subject to dynamic action and/or low stressed miscellaneous applications.

1.2.4 Class 4 Weld Joints

This covers weld joints applicable to welding reinforcing steel to primary structural members.

1.2.5 Class 5 Weld Joints

This covers weld joints applicable to welding concrete reinforcing steel splices (prestressing steel excepted), steel connection devices, and inserts and anchors required in concrete construction.

1.2.6 Class 6 Weld Joints

This covers plug and slot weld joints as applicable to the requirements of the project's code(s).

1.3 SYSTEM DESCRIPTION

Conform the design of welded connections to AISC 360, unless otherwise indicated or specified. Material with welds will not be accepted unless the welding is specified or indicated on the drawings or otherwise approved.

Perform welding as specified in this section, except where additional requirements are shown on the drawings or are specified in other sections.

Do not commence welding until welding procedures, inspectors, nondestructive testing personnel, welders, welding operators, and tackers have been qualified and the submittals approved by the Contracting Officer. Perform all testing at or near the work site. Each contractor performing welding shall maintain records of the test results obtained in welding procedure, welder, welding operator, and tacker performance qualifications.

1.3.1 Pre-erection Conference

Hold a pre-erection conference prior to the start of the field welding, to bring all affected parties together and to gain a naturally clear

SECTION 05 05 23 Page 3 understanding of the project and the Welding Procedure Specifications (WPS) (which the contractor shall develop and submit for all welding, including welding done using pre-qualified procedures). Mandatory attendance is required by all contractor's welding production and inspection personnel and appropriate Government personnel. Include as items for discussion:

responsibilities of various parties; welding procedures and processes to be followed; welding sequence (both within a joint and joint sequence within the building); inspection requirements and procedures, both visual and ultrasonic; welding schedule; fabrication of mock-up model; and other items deemed necessary by the attendees.

1.3.2 Mock-up Model

Perform first the field-welded connection designated as the mock-up model on the drawings. All welders qualified and designated to perform field-welded groove joints must be present during the welding of the mock-up model connections and each one shall perform a part of the welding. Simulate with the mock-up test all physical and environmental conditions that will be encountered during the welding of all groove joints. Execute all inspection procedures required for groove welded joints, including NDE tests, on the mock-up model. All contractor inspection and testing personnel designated to perform QC of groove welded joints must be present during the welding of the mock-up model and each one shall perform the inspection procedures to be performed on production welding of these joints. This mock-up model connection represents the standard of performance, both for the welding and inspection procedures used and the results to be achieved in the production welding for these groove welded joints.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Welding Procedure Qualifications; G Welder, Welding Operator, and Tacker Qualification Inspector Qualification Previous Qualifications Pre-qualified Procedures

Copies of the welding procedure specifications; the procedure qualification test records; and the welder, welding operator, or tacker qualification test records.

SD-06 Test Reports

Quality Control

A quality assurance plan and records of tests and inspections.

Submit all records of nondestructive examination in accordance with paragraph "Acceptance Requirements".

SECTION 05 05 23 Page 4

SD-07 Certificates

Certified Welding Procedure Specifications (WPS) Certified Brazing Procedure Specifications (BPS) Certified Procedure Qualification Records (PQR) Certified Welder Performance Qualifications (WPQ) Certified Brazer Performance Qualifications (BPQ)

Certificates in accordance with paragraph "Other Applications".

1.5 QUALITY ASSURANCE

Except for pre-qualified (in accordance with AWS D1.1/D1.1M) and previously qualified procedures, each contractor performing welding shall record in detail and qualify the welding procedure specification for any welding procedure followed in the fabrication of weldments. Conform welding procedure qualifications to AWS D1.1/D1.1M and to the specifications in this section. Submit for approval copies of the welding procedure specification and the results of the procedure qualification test for each type of welding which requires procedure qualification. Approval of any procedure, however, does not relieve the contractor of the sole responsibility for producing a finished structure meeting all the specified requirements. Submit this information on the forms in Annex M of AWS D1.1/D1.1M. Individually identify and clearly reference on the detail drawings and erection drawings all welding procedure specifications, or suitably key them to the contract drawings. In case of conflict between this specification and AWS D1.1/D1.1M, this specification governs.

1.5.1 General Requirements

The organization performing this work must be certified in the following:

American Institute of Steel Construction (AISC) Quality Certification Standard for Steel Building Structures.

a. For Structural Projects, provide documentation of the following:

1) Component Thickness 1/8 inch and greater: Qualification documents

(WPS, PQR, and WPQ) in accordance with AWS D1.1/D1.1M.

2) Component Thickness Less than 1/8 inch: Qualification documents

(WPS, PQR, and WPQ) in accordance with AWS D1.3/D1.3M.

3) Reinforcing Steel: Qualification documents (WPS, PWR, and WPQ) in accordance with AWS D1.4/D1.4M.

b. For other applications, provide documentation of the following:

1) Submit for review to the Contracting Officer two copies of Certified Welding Procedure Specifications (WPS), Certified Brazing Procedure Specifications (BPS) and Certified Procedure Qualification Records (PQR) within fifteen calendar days after receipt of Notice to Proceed.

2) Cranes: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D14.1/D14.1M.

SECTION 05 05 23 Page 5

3) Submit for review to the Contracting Officer two copies of Certified Welder Performance Qualifications (WPQ)and Certified Brazer Performance Qualifications (BPQ) within fifteen calendar days prior to any employee welding on the project material.

4) Machinery: Qualification documents (WPS, PQR, and WPQ) in accordance with AWS D14.4/D14.4M.

1.5.2 Previous Qualifications

Welding procedures previously qualified by test may be accepted for this contract without re-qualification if the following conditions are met:

a. Testing was performed by an approved testing laboratory, technical consultant, or the contractor's approved quality control organization.

b. The qualified welding procedure conforms to the requirements of this specification and is applicable to welding conditions encountered under this contract.

c. The welder, welding operator, and tacker qualification tests conform to the requirements of this specification and are applicable to welding conditions encountered under this contract.

1.5.3 Pre-qualified Procedures

Welding procedures which are considered pre-qualified as specified in AWS D1.1/D1.1M will be accepted without further qualification. Submit for approval a listing or an annotated drawing to indicate the joints not pre-qualified. Procedure qualification is mandatory for these joints.

1.5.4 Retests

If welding procedure fails to meet the requirements of AWS D1.1/D1.1M, revise and re-qualify the procedure specification, or at the contractor's option, welding procedure may be retested in accordance with AWS D1.1/D1.1M.

If the welding procedure is qualified through retesting, all test results, including those of test welds that failed to meet the requirements, shall be submitted with the welding procedure.

1.5.5 Welder, Welding Operator, and Tacker Qualification

Each welder, welding operator, and tacker assigned to work on this contract shall be qualified in accordance with the applicable requirements of AWS D1.1/D1.1M and as specified in this section. Welders, welding operators, and tackers who make acceptable procedure qualification test welds will be considered qualified for the welding procedure used.

1.5.5.1 Previous Personnel Qualifications

At the discretion of the Contracting Officer, welders, welding operators, and tackers qualified by test within the previous 6 months may be accepted for this contract without re-qualification if all the following conditions are met:

a. Copies of the welding procedure specifications, the procedure qualification test records, and the welder, welding operator, and

SECTION 05 05 23 Page 6 tacker qualification test records are submitted and approved in accordance with the specified requirements for detail drawings.

b. Testing was performed by an approved testing laboratory, technical consultant, or the contractor's approved quality control organization.

c. The previously qualified welding procedure conforms to the requirements of this specification and is applicable to welding conditions encountered under this contract.

d. The welder, welding operator, and tacker qualification tests conform to the requirements of this specification and are applicable to welding conditions encountered under this contract.

1.5.5.2 Certificates

Before assigning any welder, welding operator, or tacker to work under this contract, submit the names of the welders, welding operators, and tackers to be employed, and certification that each individual is qualified as specified. The certification must state the type of welding and positions for which the welder, welding operator, or tacker is qualified, the code and procedure under which the individual is qualified, the date qualified, and the name of the firm and person certifying the qualification tests. Keep the certification current, on file, and furnish 3 copies.

1.5.5.3 Renewal of Qualification

Re-qualification of a welder or welding operator is required under any of the following conditions:

a. It has been more than 6 months since the welder or welding operator has used the specific welding process for which he is qualified.

b. There is specific reason to question the welder or welding operator's ability to make welds that meet the requirements of these specifications.

c. The welder or welding operator was qualified by an employer other than those firms performing work under this contract, and a qualification test has not been taken within the past 12 months. Submit as evidence of conformance all records showing periods of employment, name of employer where welder, or welding operator, was last employed, and the process for which qualified.

d. A tacker who passes the qualification test is considered eligible to perform tack welding indefinitely in the positions and with the processes for which he is qualified, unless there is some specific reason to question the tacker's ability. In such a case, the tacker is required to pass the prescribed tack welding test.

1.5.6 Inspector Qualification

Inspector qualifications shall be in accordance with AWS D1.1/D1.1M. Qualify all nondestructive testing personnel in accordance with the requirements of ASNT RP SNT-TC-1A for Levels I or II in the applicable nondestructive testing method. The inspector may be supported by assistant welding inspectors who are not qualified to ASNT RP SNT-TC-1A, and assistant

SECTION 05 05 23 Page 7 inspectors may perform specific inspection functions under the supervision of the qualified inspector.

1.5.7 Symbols and Safety

Symbols shall be in accordance with AWS A2.4, unless otherwise indicated.

Safe welding practices and safety precautions during welding shall conform to AWS Z49.1.

PART 2 PRODUCTS

2.1 WELDING EQUIPMENT AND MATERIALS

Provide all welding equipment, electrodes, welding wire, and fluxes capable of producing satisfactory welds when used by a qualified welder or welding operator performing qualified welding procedures. All welding equipment and materials shall comply with the applicable requirements of AWS D1.1/D1.1M.

PART 3 EXECUTION

3.1 WELDING OPERATIONS

3.1.1 Requirements

Conform workmanship and techniques for welded construction to the requirements of AWS D1.1/D1.1M and AISC 360. When AWS D1.1/D1.1M and the AISC 360 specification conflict, the requirements of AWS D1.1/D1.1M govern.

3.1.2 Identification

Identify all welds in one of the following ways:

a. Submit written records to indicate the location of welds made by each welder, welding operator, or tacker.

b. Identify all work performed by each welder, welding operator, or tacker with an assigned number, letter, or symbol to identify welds made by that individual. The Contracting Officer may require welders, welding operators, and tackers to apply their symbol next to the weld by means of rubber stamp, felt-tipped marker with waterproof ink, or other methods that do not cause an indentation in the metal. Place the identification mark for seam welds adjacent to the weld at 3 foot intervals. Identification with die stamps or electric etchers is not allowed.

3.2 QUALITY CONTROL

Perform testing using an approved inspection or testing laboratory or technical consultant; or if approved, the contractor's inspection and testing personnel may be used instead of the commercial inspection or testing laboratory or technical consultant. Perform visual to determine conformance with paragraph STANDARDS OF ACCEPTANCE. Conform procedures and techniques for inspection with applicable requirements of AWS D1.1/D1.1M, ASTM E 165, ASTM E 709, except that in radiographic inspection only film types designated as "fine grain," or "extra fine," are acceptable.

SECTION 05 05 23 Page 8

3.3 STANDARDS OF ACCEPTANCE

Conform dimensional tolerances for welded construction, details of welds, and quality of welds with the applicable requirements of AWS D1.1/D1.1M and the contract drawings. Perform nondestructive testing by visual inspection methods. The minimum extent of nondestructive testing must be a random percentage of welds or joints, as indicated on the drawings.

3.3.1 Nondestructive Examination

The welding is subject to inspection and tests in the mill, shop, and field.

Inspection and tests in the mill or shop do not relieve the contractor of the responsibility to furnish weldments of satisfactory quality. When materials or workmanship do not conform to the specification requirements, the Government reserves the right to reject material or workmanship or both at any time before final acceptance of the structure containing the weldment.

3.3.2 Destructive Tests

Make all repairs when metallographic specimens are removed from any part of a structure. Employ only qualified welders or welding operators, and use the proper joints and welding procedures, including peening or heat treatment if required, to develop the full strength of the members and joints cut and to relieve residual stress.

3.4 GOVERNMENT INSPECTION AND TESTING

In addition to the inspection and tests performed by the contractor for quality control, the Government will perform inspection and testing for acceptance to the extent determined by the Contracting Officer. The costs of such inspection and testing will be borne by the contractor if unsatisfactory welds are discovered, or by the Government if the welds are satisfactory. The work may be performed by the Government's own forces or under a separate contract for inspection and testing. The Government reserves the right to perform supplemental nondestructive and destructive tests to determine compliance with paragraph STANDARDS OF ACCEPTANCE.

3.5 CORRECTIONS AND REPAIRS

If inspection or testing indicates defects in the weld joints, repair defective welds using a qualified welder or welding operator as applicable.

Conduct corrections in accordance with the requirements of AWS D1.1/D1.1M and the specifications. Repair all defects in accordance with the approved procedures. Repair defects discovered between passes before additional weld material is deposited. Wherever a defect is removed and repair by welding is not required, blend the affected area into the surrounding surface to eliminate sharp notches, crevices, or corners. After a defect is thought to have been removed, and before re-welding, examine the area by suitable methods to ensure that the defect has been eliminated. Repaired welds shall meet the inspection requirements for the original welds. Any indication of a defect is regarded as a defect, unless re-evaluation by nondestructive methods or by surface conditioning shows that no unacceptable defect is present.

-- End of Section --

SECTION 05 12 00 Page 1

SECTION 05 12 00

STRUCTURAL STEEL

1.1 GENERAL REQUIREMENTS

Structural steel fabrication and erection shall be performed by an organization experienced in structural steel work of equivalent magnitude.

The contractor shall be responsible for correctness of detailing, fabrication, and for the correct fitting of structural members. Connections, for any part of the structure not shown on the contract drawings, shall be considered simple shear connections and shall be designed and detailed in accordance with pertinent provisions of AISC 317 and AISC 325. Substitution of sections or modification of connection details will not be accepted unless approved by the Contracting Officer. AISC 317 and AISC 325 shall govern the work. Welding shall be in accordance with AWS D1.1/D1.1M; except that welding for critical applications shall be in accordance with Section 05 05 23 WELDING, STRUCTURAL or paragraph WELDING. High-strength bolting shall be in accordance with AISC 317 or AISC 325.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)

AASHTO HB-17 (2002; Errata 2003; Errata 2005) Standard

Specifications for Highway Bridges

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

AISC 303 (2005) Code of Standard Practice for Steel Buildings and Bridges

AISC 317 (1992; Reprint 1999) ASD Manual of Steel

Construction, Vol II: Connections

AISC 325 (2005) Manual of Steel Construction

AISC 326 (2002) Detailing for Steel Construction

AISC 341 (2005; Supp 2001) Seismic Provisions for Structural

Steel Buildings

AISC 348 (2000) Structural Joints Using ASTM A325 or A490

Bolts

AISC 350 (2005) Load and Resistance Factor Design

(LRFD)Specification for Structural Steel Buildings

SECTION 05 12 00 Page 2

AISC 810 (1997) Erection Bracing of Low-Rise Structural Steel Frames/Fisher and West

AISC FCD (1995a) Quality Certification Program Description

AWS A2.4 (2007) Standard Symbols for Welding, Brazing and

ASME INTERNATIONAL (ASME)

ASME B46.1 (2002) Surface Texture (Surface Roughness, Waviness and Lay)

ASTM INTERNATIONAL (ASTM)

ASTM A 108 (2007) Standard Specification for Steel Bar, Carbon and Alloy, Cold-Finished

ASTM A 123/A 123M (2008) Standard Specification for Zinc (Hot-Dip

Galvanized) Coatings on Iron and Steel Products

ASTM A 143/A 143M (2007) Standard Practice for Safeguarding Against

Embrittlement of Hot-Dip Galvanized Structural Steel Products and Procedure for Detecting Embrittlement

ASTM A 153/A 153M (2005) Standard Specification for Zinc Coating (Hot-

Dip) on Iron and Steel Hardware

ASTM A 242/A 242M (2004e1) Standard Specification for High-Strength

Low-Alloy Structural Steel

ASTM A 325 (2007a) Standard Specification for Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength

ASTM A 36/A 36M (2008) Standard Specification for Carbon Structural

Steel

ASTM A 490 (2008a) Standard Specification for Structural Bolts, Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength

ASTM A 500/A 500M (2007) Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes

ASTM A 502 (2003) Standard Specification for Rivets, Steel, Structural

ASTM A 501 (2007) Standard Specification for Hot-Formed Welded and Seamless Carbon Steel Structural Tubing

SECTION 05 12 00 Page 3

ASTM A 514/A 514M (2005) Standard Specification for High-Yield- Strength, Quenched and Tempered Alloy Steel Plate, Suitable for Welding

ASTM A 529/A 529M (2005) Standard Specification for High-Strength

Carbon-Manganese Steel of Structural Quality

ASTM A 53/A 53M (2007) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

ASTM A 563 (2007a) Standard Specification for Carbon and Alloy

Steel Nuts

ASTM A 572/A 572M (2007) Standard Specification for High-Strength Low-

Alloy Columbium-Vanadium Structural Steel

ASTM A 588/A 588M (2005) Standard Specification for High-Strength Low-

Alloy Structural Steel with 50 ksi (345 MPa) Minimum Yield Point, with Atmospheric Corrosion Resistance

ASTM A 6/A 6M (2007) Standard Specification for General

Requirements for Rolled Structural Steel Bars, Plates, Shapes, and Sheet Piling

ASTM A 618/A 618M (2004) Standard Specification for Hot-Formed Welded and Seamless High-Strength Low-Alloy Structural Tubing

ASTM A 668/A 668M (2004) Standard Specification for Steel Forgings, Carbon and Alloy, for General Industrial Use

ASTM A 709/A 709M (2007) Standard Specification for Structural Steel for Bridges

ASTM A 780 (2001; R 2006) Standard Practice for Repair of

Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings

ASTM A 852/A 852M (2003; R 2007) Standard Specification for Quenched and Tempered Low-Alloy Structural Steel Plate with 70 ksi (485 MPa) Minimum Yield Strength to 4 in. (100

mm) Thick

ASTM A 992/A 992M (2006a) Standard Specification for Structural Steel

Shapes

ASTM B 695 (2004) Standard Specification for Coatings of Zinc

Mechanically Deposited on Iron and Steel

ASTM C 1107/C 1107M (2007a) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)

ASTM C 827 (2001a; R 2005) Change in Height at Early Ages of

Cylindrical Specimens from Cementitious Mixtures

ASTM F 436 (2007a) Hardened Steel Washers

SECTION 05 12 00 Page 4

ASTM F 844 (2007a) Washers, Steel, Plain (Flat), Unhardened for General Use

ASTM F 959 (2007a) Compressible-Washer-Type Direct Tension

Indicators for Use with Structural Fasteners

ASTM F 1554 (2007a)Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi Yield Strength

CRANE MANUFACTURERS ASSOCIATION OF AMERICA (CMAA)

CMAA 70 (2004) EnviroTop Running and Bridge and Gantry Type

Multiple Girder Electric Overhead Traveling Cranes, No. 70

THE SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC PA 1 (2000; E 2004) Shop, Field, and Maintenance Painting

SSPC PS 13.01 (1982; E 2004) Epoxy-Polyamide Painting System

SSPC Paint 25 (1997; E 2004) Paint Specification No. 25Zinc Oxide, Alkyd, Linseed Oil Primer for Use Over Hand Cleaned Steel Type I and Type II

SSPC SP 3 (2004; E 2004) Power Tool Cleaning

SSPC SP 6 (2000; E 2004) Commercial Blast Cleaning

1.3 SYSTEM DESCRIPTION

Provide the structural steel system, including shop primer, galvanizing, complete and ready for use. Structural steel systems including design, materials, installation, workmanship, fabrication, assembly, erection, inspection, quality control, and testing shall be provided in accordance with AISC 325 and AISC 317 except as modified in this contract.

1.4 MODIFICATIONS TO REFERENCES

Conform to AISC 325, AISC 317, AISC 360, AISC 303, AISC 348, and AISC 350, except as modified in this section.

1.5 SUBMITTALS

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will

SD-02 Shop Drawings

Erection Plan, including description of temporary supports; G

Prior to erection, erection plan of the structural steel framing describing all necessary temporary supports, including the sequence of installation and removal.

SECTION 05 12 00 Page 5

Fabrication drawings including description of connections; G

Shop and erection details including members (with their connections) not shown on the contract drawings. Welds shall be indicated by standard welding symbols in accordance with AWS A2.4.

SD-03 Product Data

Shop primer Welding electrodes and rods Load indicator washers Non-Shrink Grout Load indicator bolts

Include test report for Class B primer.

SD-06 Test Reports

Class B coating Bolts, nuts, and washers

Supply the certified manufacturer's mill reports which clearly show the applicable ASTM mechanical and chemical requirements together with the actual test results for the supplied fasteners. Random samples of bolts, nuts, and washers as delivered to the job site if requested, taken in the presence of the Contracting Officer and provided to the Contracting Officer for testing to establish compliance with specified requirements.

SD-07 Certificates

Steel

Certified copies of mill test reports for structural steel, structural bolts, nuts, washers and other related structural steel items, including attesting that the structural steel furnished contains no less than 25 percent recycled scrap steel and meets the requirements specified, prior to the installation.

Bolts, nuts, and washers Galvanizing Pins and rollers AISC Quality Certification

A copy of the AISC certificate indicating that the fabrication plant meets the specified structural steelwork category.

Overhead, top running crane rail beam Welding procedures and qualifications

Certified copies of welder and welding inspector qualifications test records showing qualification in accordance with AWS D1.1/D1.1M.

1.6 AISC QUALITY CERTIFICATION

Fabrication plant shall be AISC certified, meeting the Standard for Steel Building Structures.

SECTION 05 12 00 Page 6

1.7 SEISMIC PROVISIONS

The structural steel system shall be provided in accordance with AISC 341.

1.8 QUALITY ASSURANCE

1.8.1 Drawing Requirements

Submit fabrication drawings for approval prior to fabrication. Prepare in accordance with AISC 326, AISC 325 and AISC 317. Fabrication drawings shall not be reproductions of contract drawings. Sign and seal fabrication drawings by a professional engineer registered in the State where the project is located. Include complete information for the fabrication and erection of the structure's components, including the location, type, and size of bolts, welds, member sizes and lengths, connection details, blocks, copes, and cuts. Use AWS A2.4 standard welding symbols. Shoring and temporary bracing shall be designed and sealed by a registered professional engineer and submitted for record purposes, with calculations, as part of the drawings. Member substitutions of details shown on the contract drawings shall be clearly highlighted on the fabrication drawings. Explain the reasons for any deviations from the contract drawings.

1.8.2 Certifications

1.8.2.1 Overhead, Top Running Crane Rail Beam

Submit written field survey results for overhead, top running crane rail beam verifying tolerance requirements, area out of tolerance and proposed corrective measures.

1.8.2.2 Erection Plan

Submit for record purposes. Indicate the sequence of erection, temporary shoring and bracing, and a detailed sequence of welding, including each welding procedure required.

1.8.2.3 Welding Procedures and Qualifications

Prior to welding, submit certification for each welder stating the type of welding and positions qualified for, the code and procedure qualified under, date qualified, and the firm and individual certifying the qualification tests. If the qualification date of the welding operator is more than one-year old, the welding operator's qualification certificate shall be accompanied by a current certificate by the welder attesting to the fact that he has been engaged in welding since the date of certification, with no break in welding service greater than 6 months.

Conform to all requirements specified in AWS D1.1/D1.1M.

1.9 STORAGE

Material shall be stored out of contact with the ground in such manner and location as will minimize deterioration.

SECTION 05 12 00 Page 7

2.1 STEEL

2.1.1 Structural Steel

ASTM A 36/A 36M.

2.1.2 High-Strength Structural Steel

2.1.2.1 Low-Alloy Steel

ASTM A 572/A 572M, ASTM A 992/A 992M, or ASTM A 709/A 709M, Grade as indicated on the Delivery Order.

2.1.2.2 Quenched and Tempered Alloy Steel

ASTM A 514/A 514M, Grade as indicated on the Delivery Order.

2.1.2.3 Quenched and Tempered Low-Alloy Steel

ASTM A 852/A 852M, 70 ksi.

2.1.3 Weathering Structural Steel

ASTM A 242/A 242M, Type 1; ASTM A 588/A 588M.

2.1.4 Structural Grade Carbon-Manganese Steel

ASTM A 529/A 529M, high strength carbon-manganese steel of structural quality.

2.1.5 Structural Shapes for Use in Building Framing

Wide flange shapes, ASTM A 992/A 992M.

2.1.6 Structural Steel Tubing

ASTM A 500/A 500M, ASTM A 501; ASTM A 618/A 618M, Grade as indicated on the Delivery Order.

2.1.7 Steel Pipe

ASTM A 53/A 53M, Type E or S, Grade B, weight class as indicated on the Delivery Order.

2.2 BOLTS, NUTS, AND WASHERS

Provide the following unless indicated otherwise.

2.2.1 Structural Steel, Steel Pipe

2.2.1.1 Bolts

ASTM A 325, Type 1, or ASTM A 490, Type 1, as indicated on the Delivery Order. The bolt heads and the nuts of the supplied fasteners must be marked

SECTION 05 12 00 Page 8 with the manufacturer's identification mark, the strength grade and type specified by ASTM specifications.

2.2.1.2 Nuts

ASTM A 563, Grade and Style for applicable ASTM bolt standard recommended.

2.2.1.3 Washers

ASTM F 436 washers for ASTM A 325 and ASTM A 490 bolts.

2.2.2 High-Strength Structural Steel and Structural Steel Tubing

2.2.2.1 Bolts

ASTM A 325, Type 1 ASTM A 490, Type 1 or 2.

2.2.2.2 Nuts

ASTM A 563, Grade and Style as specified in the applicable ASTM bolt standard.

2.2.2.3 Washers

ASTM F 436, plain carbon steel.

2.2.3 Weathering Structural Steel

2.2.3.1 Bolts

ASTM A 325, Type 3; ASTM A 490, Type 3.

2.2.3.2 Nuts

ASTM A 563, heavy hex style, Grade DH3, except Grade C3 may be furnished for ASTM A 325 bolts.

2.2.3.3 Washers

ASTM F 436, weathering steel.

2.2.4 Foundation Anchorage

2.2.4.1 Anchor Bolts

ASTM F 1554, as indicated on the Delivery Order.

2.2.4.2 Anchor Nuts

ASTM A 563, Grade A, hex style.

2.2.4.3 Anchor Washers

ASTM F 844.

2.2.5 Load Indicator Washers

SECTION 05 12 00 Page 9

ASTM F 959. Provide ASTM B 695, Class 50, Type 1 galvanizing where indicated.

2.2.6 Load Indicator Bolts

ASTM A 325, Type 1; ASTM A 490, Type 1, with a manufactured notch between the bolt tip and threads. The bolt shall be designed to react to the opposing rotational torques applied by the installation wrench, with the bolt tip automatically shearing off when the proper tension is obtained.

2.2.7 Self-Locking Nuts

Provide nuts with a locking pin set in the nut. The locking pin shall slide along the bolt threads, and by reversing the direction of the locking pin, the nut shall be removed without damaging the nut or bolt. Provide stainless steel locking pins.

2.2.8 RIVETS

Rivets shall conform to ASTM A 502.

2.3 STRUCTURAL STEEL ACCESSORIES

2.3.1 Welding Electrodes and Rods

AWS D1.1/D1.1M.

2.3.2 Non-Shrink Grout

ASTM C 1107/C 1107M, with no ASTM C 827 shrinkage. Grout shall be nonmetallic.

2.3.3 Welded Shear Stud Connectors

AWS D1.1/D1.1M.

2.3.4 Pins and Rollers

ASTM A 668/A 668M, Class C, D, F, or G; ASTM A 108, Grades 1016 to 1030.

Provide as specified in AASHTO HB-17, Division II, Sections 10.26 and 10.27, except provide pins in lengths to extend a minimum of 0.25 inch beyond the outside faces of the connected parts.

2.4 SHOP PRIMER

SSPC Paint 25, (alkyd primer) or SSPC PS 13.01 epoxy-polyamide, green primer (Form 150) type 1, except provide a Class B coating in accordance with AISC 325 and AISC 317 for slip critical joints. Primer shall conform to Federal, State, and local VOC regulations. If flash rusting occurs, re-clean the surface prior to application of primer.

2.5 GALVANIZING

ASTM A 123/A 123M or ASTM A 153/A 153M, as applicable, unless specified otherwise galvanize after fabrication where practicable.

SECTION 05 12 00 Page 10

2.6 OVERHEAD, TOP RUNNING CRANE RAIL

AISC 325 and AISC 317, AREMA Eng Man, with crane rail section as indicated on the Delivery Order. Joints shall be bolted or welded. Provide rail fasteners and a minimum rail length of 10 feet.

2.7 FABRICATION

2.7.1 Markings

Prior to erection, members shall be identified by a painted erection mark.

Connecting parts assembled in the shop for reaming holes in field connections shall be match marked with scratch and notch marks. Do not locate erection markings on areas to be welded or on surfaces of weathering steels that will be exposed in the completed structure. Do not locate match markings in areas that will decrease member strength or cause stress concentrations. Affix embossed tags to hot-dipped galvanized members.

2.7.2 Shop Primer

Shop prime structural steel, except as modified herein, in accordance with SSPC PA 1. Do not prime steel surfaces embedded in concrete, galvanized surfaces, surfaces to receive sprayed-on fireproofing, surfaces to receive epoxy coatings, surfaces designed as part of a composite steel concrete section, or surfaces within 0.5 inch of the toe of the welds prior to welding (except surfaces on which metal decking is to be welded). Slip critical surfaces shall be primed with a Class B coating. Prior to assembly, prime surfaces this will be concealed or inaccessible after assembly. Do not apply primer in foggy or rainy weather; when the ambient temperature is below 45 degrees F or over 95 degrees F; or when the primer may be exposed to temperatures below 40 degrees F within 48 hours after application, unless approved otherwise by the Contracting Officer.

2.7.2.1 Cleaning

SSPC SP 6, except steel exposed in spaces above ceilings, attic spaces, furred spaces, and chases that will be hidden to view in finished construction may be cleaned to SSPC SP 3 when recommended by the shop primer manufacturer. Maintain steel surfaces free from rust, dirt, oil, grease, and other contaminants through final assembly.

2.7.2.2 Primer

Apply primer to a minimum dry film thickness of 2.0 mil except provide the Class B coating for slip critical joints in accordance with the coating manufacturer's recommendations. Repair damaged primed surfaces with an additional coat of primer.

2.7.3 Fireproofing and Epoxy Coated Surfaces

Surfaces to receive sprayed-on fireproofing or epoxy coatings shall be cleaned and prepared in accordance with the manufacturer's recommendations, and as specified in Section 07 81 00 SPRAY-APPLIED FIREPROOFING.

SECTION 05 12 00 Page 11

2.7.4 Surface Finishes

ASME B46.1 maximum surface roughness of 125 for pin, pinholes, and sliding bearings, unless indicated otherwise.

2.8 DRAINAGE HOLES

Adequate drainage holes shall be drilled to eliminate water traps. Hole diameter shall be 1/2 inch and location shall be indicated on the detail drawings. Hole size and location shall not affect the structural integrity.

3.1 FABRICATION

Fabrication shall be in accordance with the applicable provisions of AISC

325. Fabrication and assembly shall be done in the shop to the greatest extent possible. The fabricating plant shall be certified under the AISC FCD Category Standard for Steel Building Structures for structural steelwork.

Compression joints depending on contact bearing shall have a surface roughness not in excess of 500 micro inch as determined by ASME B46.1, and ends shall be square within the tolerances for milled ends specified in ASTM A 6/A 6M.

Structural steelwork, except surfaces of steel to be encased in concrete, surfaces to be field welded, surfaces to be fireproofed, and contact surfaces of friction-type high-strength bolted connections shall be prepared for painting in accordance with endorsement "P" of AISC FCD and primed with the specified paint.

Shop splices of members between field splices will be permitted only where indicated on the Contract Drawings. Splices not indicated require the approval of the Contracting Officer.

3.2 INSTALLATION

3.2.1 Overhead, Top Running Cranes

Do not splice truss top and bottom chords except as approved by the Contracting Officer. Chord splices shall occur at panel joints at approximately the third point of the span. The center of gravity lines of truss members shall intersect at panel points unless otherwise approved by the Contracting Officer. When the center of gravity lines do not intersect at a panel point, provisions shall be made for the stresses due to eccentricity. Cumber of trusses shall be 1/8 inch in 10 feet unless otherwise indicated.

Runway rails and beams shall be provided in accordance with AISC 325 and AISC 317 and CMAA 70, except that in case of conflict, the requirements of CMAA 70 shall govern. In addition, provide a maximum vertical difference of0.03 inch in the elevation between adjacent runway rail tops and adjacent runway beam tops at joints. Provide adjustable runway support connections to allow placement of the crane rails and beams to the tolerances specified.

Stagger runway rail joints a minimum of one foot, except that the stagger shall not be the same as the crane wheel spacing.

SECTION 05 12 00 Page 12

3.3 ERECTION

a. Erection of structural steel, except as indicated in item b. below, shall be in accordance with the applicable provisions of AISC 325 or endorsement F of AISC FCD. Erection plan shall be reviewed, stamped and sealed by a licensed structural engineer.

b. For low-rise structural steel buildings (60 feet tall or less and a maximum of 2 stories), the erection plan shall conform to AISC 303 and the structure shall be erected in accordance with AISC 810.

Provide for drainage in structural steel. After final positioning of steel members, provide full bearing under base plates and bearing plates using nonshrink grout. Place nonshrink grout in accordance with the manufacturer's instructions.

3.3.1 Structural Connections

Anchor bolts and other connections between the structural steel and foundations shall be provided and shall be properly located and built into connecting work. Field welded structural connections shall be completed before load is applied.

3.3.2 Base Plates and Bearing Plates

Column base plates for columns and bearing plates for beams, girders, and similar members shall be provided. Base plates and bearing plates shall be provided with full bearing after the supported members have been plumbed and properly positioned, but prior to placing superimposed loads. Separate setting plates under column base plates will not be permitted. The area under the plate shall be damp-packed solidly with bedding mortar, except where nonshrink grout is indicated on the drawings.

3.3.3 STORAGE

Material shall be stored out of contact with the ground in such manner and location as will minimize deterioration.

3.4 CONNECTIONS

Except as modified in this section, connections not detailed shall be designed in accordance with AISC 360 or AISC 350. Build connections into existing work. Do not tighten anchor bolts set in concrete with impact torque wrenches. Punch, subpunch and ream, or drill bolt and pin holes perpendicular to the surface of the member. Holes shall not be cut or enlarged by burning. Bolts, nuts, and washers shall be clean of dirt and rust, and lubricated immediately prior to installation.

3.4.1 High-Strength Bolts

ASTM A 325 and ASTM A 490 bolts shall be fully tensioned to 70 percent of their minimum tensile strength. Load indicator bolts or washers may be used in ASTM A 325 or ASTM A 490 bolted connections, except provide only load indicator washers for slip critical connections. Direct tension indicator tightening shall be the only acceptable tightening methods. Use only direct tension indicator tightening for slip critical connections. Bolts shall be installed in connection holes and initially brought to a snug tight fit.

SECTION 05 12 00 Page 13

After the initial tightening procedure, bolts shall then be fully tensioned, progressing from the most rigid part of a connection to the free edges.

3.4.1.1 Installation of Load Indicator Washers (LIW)

ASTM F 959. Where possible, the LIW shall be installed under the bolt head and the nut shall be tightened. If the LIW is installed adjacent to the turned element, provide a flat ASTM F 436 washer between the LIW and nut when the nut is turned for tightening, and between the LIW and bolt head when the bolt head is turned for tightening. In addition to the LIW, provide flat ASTM F 436 washers under both the bolt head and nut when ASTM A 490 bolts are used.

3.5 GAS CUTTING

Use of gas-cutting torch in the field for correcting fabrication errors will not be permitted on any major member in the structural framing. Use of a gas cutting torch will be permitted on minor members not under stress only after approval has been obtained from the Contracting Officers.

3.6 WELDING

AWS D1.1/D1.1M, except use only shielded metal arc welding and low hydrogen electrodes for ASTM A 514/A 514M steel. Do not stress relieve ASTM A 514/A 514M steel by heat treatment. Grind exposed welds smooth as indicated.

Provide AWS D1.1/D1.1M qualified welders, welding operators, and tackers.

The contractor shall develop and submit the Welding Procedure Specifications (WPS) for all welding, including welding done using prequalified procedures.

Prequalified procedures may be submitted for information only; however, procedures that are not prequalified shall be submitted for approval.

3.6.1 Removal of Temporary Welds, Run-Off Plates, and Backing Strips

Remove only from finished areas or as indicated.

3.7 SHOP PRIMER REPAIR

Repair shop primer in accordance with the paint manufacturer's recommendation for surfaces damaged by handling, transporting, cutting, welding, or bolting.

3.7.1 Field Priming

Field priming of steel exposed to the weather, or located in building areas without HVAC for control of relative humidity. After erection, the field bolt heads and nuts, field welds, and any abrasions in the shop coat shall be cleaned and primed with paint of the same quality as that used for the shop coat.

3.8 GALVANIZING REPAIR

Provide as indicated or specified. Galvanize after fabrication where practicable. Repair damage to galvanized coatings using ASTM A 780 zinc rich paint for galvanizing damaged by handling, transporting, cutting, welding, or bolting. Do not heat surfaces to which repair paint has been applied.

SECTION 05 12 00 Page 14

3.9 FIELD QUALITY CONTROL

Perform field tests, and provide labor, equipment, and incidentals required for testing, except that electric power for field tests will be furnished as set forth in Division 1. The Contracting Officer shall be notified in writing of defective welds, bolts, nuts, and washers within 7 working days of the date of weld inspection.

3.9.1 Welds

3.9.1.1 Visual Inspection

AWS D1.1/D1.1M. Furnish the services of AWS-certified welding inspectors for fabrication and erection inspection and testing and verification inspections. Welding inspectors shall visually inspect and mark welds, including fillet weld end returns.

3.9.1.2 Nondestructive Testing

AWS D1.1/D1.1M. Test locations shall be as indicated or selected by the Contracting Officer. If more than 10 percent of welds made by a welder contain defects identified by testing, then all welds made by that welder shall be tested by radiographic or ultrasonic testing, as approved by the Contracting Officer. When all welds made by an individual welder are required to be tested, magnetic particle testing shall be used only in areas inaccessible to either radiographic or ultrasonic testing. Retest defective areas after repair. Testing frequency shall be as described on the Delivery Order.

3.9.2 Load Indicator Washers

3.9.2.1 Load Indicator Washer Compression

Load indicator washers shall be tested in place to verify that they have been compressed sufficiently to provide the 0.015 inch gap when the load indicator washer is placed under the bolt head and the nut is tightened, and to provide the 0.005 inch gap when the load indicator washer is placed under the turned element, as required by ASTM F 959.

3.9.2.2 Load Indicator Gaps

In addition to the above testing, an independent testing agency as approved by the Contracting Officer, shall test in place the load indicator gaps on 20 percent of the installed load indicator washers to verify that the ASTM F 959 load indicator gaps have been achieved. If more than 10 percent of the load indicators tested have not been compressed sufficiently to provide the average gaps required by ASTM F 959, then all in place load indicator washers shall be tested to verify that the ASTM F 959 load indicator gaps have been achieved. Test locations shall be selected by the Contracting Officer.

3.9.3 Overhead, Top Running Crane Rails and Beams

Runway rails and beams shall be surveyed (horizontally and vertically) after installation to verify compliance with the tolerance requirements of CMAA 70 and the additional tolerance requirements specified in this section. After each survey, submit a written report to the Contracting Officer with the

SECTION 05 12 00 Page 15 following information: field survey results, tolerance requirements, areas out of tolerance, and proposed corrective measures. Proposed corrective measures shall be approved by the Contracting Officer. Following completion of corrective measures, areas that were previously out of tolerance shall be re-surveyed and another written report shall be furnished to the Contracting Officer. Field surveys shall be performed and sealed by a registered land surveyor.

3.9.4 High-Strength Bolts

3.9.4.1 Testing Bolt, Nut, and Washer Assemblies

Test a minimum of 3 bolt, nut, and washer assemblies from each mill certificate batch in a tension measuring device at the job site prior to the beginning of bolting start-up. Demonstrate that the bolts and nuts, when used together, can develop tension not less than the provisions specified in AISC 348, Table 4, depending on bolt size and grade. The bolt tension shall be developed by tightening the nut. A representative of the manufacturer or supplier shall be present to ensure that the fasteners are properly used, and to demonstrate that the fastener assemblies supplied satisfy the specified requirements.

3.9.4.2 Inspection

Inspection procedures shall be in accordance with AISC 348, Section 9.

Confirm and report to the Contracting Officer that the materials meet the project specification and that they are properly stored. Confirm that the faying surfaces have been properly prepared before the connections are assembled. Observe the specified job site testing and calibration, and confirm that the procedure to be used provides the required tension. Monitor the work to ensure the testing procedures are routinely followed on joints that are specified to be fully tensioned.

The contractor shall inspect proper preparation, size, gaging location, and acceptability of welds; identification marking; operation and current characteristics of welding sets in use; and calibration of torque wrenches for high-strength bolts.

The contractor shall inspect high-strength bolted connections in accordance with AISC 317.

3.9.4.3 Testing

The Government has the option to perform nondestructive tests on a select percentage of the installed bolts to verify compliance with preload bolt tension requirements.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .