Exhibit 30 SOW Appendix C Liquidated Damages Breakdown
View the file
Other files
Show 40 more
Latest 50 of 61 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of the Army
JOINT BASE GARRISON
BOX 339500, MAIL STOP 17
JOINT BASE LEWIS-MCCHORD, WA 98433-9500
REPLY TO
ATTENTION OF:
IMLM-PWF
IMLM-PWF Date: ________
MEMORANDUM FOR: Mission and Installation Contracting Command – JBLM McChord Field
FROM: Directorate of Public Works (Project Manager, ________)
| SUBJECT: | Liquidated Damages Computation – Engineering Costs | |
| FY 2016: “IJO – Project Title” |
| ________________ |
| DPW ESD Project Manager |
The above breakdown of engineering costs is to be used to capture the impact to the government personnel with regard to managing all aspects of a task order after the legal completion date. Each day a project extends past the legal completion date, the government must expend resources to manage and track the task order. Therefore, this is not punitive but simply a tool to recoup the costs of project management which would have been allocated towards new task orders. The inability to meet the contractual obligation of a period of performance decreases the capacity of the both MICC and DPW due to the managing of a workload without the ability to take on new projects; without increased costs to personnel. This increases the cost to Joint Base Lewis-McChord and is therefore not the proper use of tax payer dollars.
Justification for Estimated Daily Costs:
| Position |
| Duty |
| Average Time/Day |
| Contracting Officer |
| · Approval of specific submittals |
· Managing of contract
· Project Tracking 15 minutes
| Engineering Supervisor/COR |
| · Approval of specific submittals |
· Briefing of upper management
· Project tracking 15 minutes
| Contract Administrator |
| · Monitoring of Contract |
· Additional payrolls to process 30 minutes
| Procurement Technician |
| · Task order official file management. |
· Daily report aggregation and distribution 15 minutes
| Project Manager |
| · Daily report reviews |
· Coordination with occupants and MICC 30 minutes
| Quality Assurance Representative |
| · Daily Inspections |
· Acceptance of daily reports 60 minutes
*All rates based on Step 5 of the corresponding GS level per the hourly locality pay of the Seattle-Tacoma-Olympia GS pay scale (21.81% over base).
**Table of Engineering costs only represents the base liquidated damage impacts to the government. Additional task order specific costs may be added in addition.
Microsoft_Excel_Worksheet1.xlsx Sheet1
1. Estimated Actual Daily Costs:
Office/Section Hours Rate* Amount
Contracting Officer (GS-13) 0.25 $48.36 $12.09
Engineering Supervisor (GS-12) 0.25 $40.67 $10.17
Contract Administrator (GS11) 0.5 $33.93 $16.97
Procurement Technician (GS-9) 0.25 $28.05 $7.01
Project Manager (GS-11) 0.5 $33.93 $16.97
QAR (GS-9) 1 $28.05 $28.05
2. Transportation and Travel:
Vehicle Costs Hours/Mile Cost Amount
Per Hour 1 $3.53 $3.53
Per Mile 25 $0.550 $13.75
3. Other Applicable Costs:
Amount
Cost of Substitute Facilities $0.00
Rental of Building/Equipment $0.00
Continued Payment of BAQ/BAS $0.00
Loss of Sales or Revenue $0.00
Idle Housing $0.00
4. Total Liquidated Damages Costs: $108.53 image1.png image2.emf