This is a solicitation for a firm-fixed-price design-bid-build construction contract to build a prefabricated metal training facility in Almaty, Kazakhstan. The facility will be a large conference room that can be divided into three smaller rooms with movable wall panels. The magnitude of construction is estimated between $1 million to $5 million. The North American Industry Classification System code is 236220 for industrial building construction with a size standard of $39.5 million. The period of performance for construction is approximately 270 calendar days after notice to proceed. There is no scheduled site visit. Responses are due in the System for Award Management, which requires an active registration. Performance and payment bonds will be required. The soliciting agency is the U.S. Army Corps of Engineers Transatlantic Expeditionary District.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
KAZCENT CONFERENCE CENTER
Almaty, Kazakhstan
KAZ 2021-001
15 December 2021
Amended 14 April 2022
KAZCENT CONFERENCE CENTER KAZCENT
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 13 SPECIAL PROJECT REQUIREMENTS
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 42 15 METRIC MEASUREMENTS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 20 ENVIRONMENTAL PROTECTION
01 58 00 PROJECT IDENTIFICATION
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SCOPE OF WORK
APPENDIX-CONSTRUCTION DRAWINGS
1.0 GENERAL:
1.1. For the purposes of this document, United States Government (USG) refers to the United States Government and the Contracting Officer or their designated representative. Contractor refers to the Contractor, Sub Contractor, Contractor and Sub Contractor employees, personnel, tools, and equipment. This document provides a general overview of the scope of work to be performed in accordance with US Government (USG) and Kazakhstan administrative codes in addition to local government administration codes and generally accepted engineering and construction practices.
1.2. The Contractor is responsible for all permits and permitting processes required by the local, regional and Country of Kazakhstan. All permit fees shall be paid for by the Contractor and all costs associated with permit fees shall be paid for under mobilization/demobilization bid item.
1.3. The Contractor shall provide all management, tools, equipment, transportation, supervision and labor necessary for construction of a Conference Center for KAZCENT in Almaty, Kazakhstan. To the maximum extent feasible, the Contractor shall employ local national (LN) professionals and shall provide written narrative justification for any non‐LN project labor employed. The Contractor shall perform all work in accordance with this Statement of Work (SOW). The Contractor shall coordinate all work with the Contracting Officer and is subject to the work schedule as stated in this document.
1.4. The Contractor shall construct to Kazakhstan construction-related laws, codes and regulations at a level to take advantage of the Contractor’s local presence in the Kazakhstan and the Kazakhstan Construction Contractors.
1.5. The contractor shall be responsible for obtaining any and all construction related permits. The contractor shall accept the site with the current conditions, prior to construction start. The contractor is solely responsible to understand the local codes, standards, project permits, referenced project documents and furnish, install, test, and complete the entire work according to these regulations.
1.6. The Contractor shall be solely responsible for constructing in compliance with Kazakhstan codes and regulations. Only in areas where Kazakhstan construction codes and regulations do not exist, the Contractor may employ applicable international construction codes, to include the International Building Code and all referenced standards. Fire protection design shall be to Kazakhstan construction codes, and shall ensure facilities have safe egress, detection, and alarms. Full fire suppression system designs are not required unless required by Kazakhstan codes.
1.7. The Contractor shall be solely responsible for maintaining technical supervision of quality and compliance with code and regulations during construction (known as “technadzor” in Russian). Technical supervision should include but is not limited to; inspection of concealed work, mounting work, construction material and equipment, and load carrying structures. Technical supervision will create intermediate acceptance reports for critical structures and maintain a technical supervision log. Technical supervision will ensure compliance with state regulations to ensure endurance, stability, and safety of the load carrying structures and external envelope, and functional qualities of the building. The contractor will maintain documentation of compliance with technical supervision in accordance with Kazakhstan legislation and regulation and will provide such documentation with all technical supervision reports and supervision log prior to building acceptance.
1.8. The Contractor shall be solely responsible for maintaining author’s supervision of compliance with design during construction (known as “avtorskiy nadzor” in Russian). Author’s supervision should include but is not limited to; object of construction, equipment and materials, construction mounting, structural elements and systems of the building, and acquisition documents. The contractor will maintain documentation of compliance with author’s supervision in accordance with Kazakhstan legislation and regulation and will provide such documentation with author’s supervision final inspection report and supervision log prior to building acceptance. In the event the original design company is no longer viable, the Contractor shall employ another entity as the “Author’s supervision” in accordance with Kazakhstan legislation.
1.9. The contractor is responsible for ensuring that the construction meets all current Kazakhstan legislation.
If new legislation goes into effect during construction, it is the Contractor’s responsibility to immediately notify the contracting officer of the change and the effects to the construction.
1.10. Units of measurement shall be metric. Cost estimates shall be provided in U.S. Dollars and local Kazakhstan currency – Tenge (KZT) at the exchange rate on the date of submittal of cost estimate. All coordination with USG shall occur in English and the Contractor shall be responsible for translation of documents and interpretation services during meetings if required.
1.11. Construction shall occur in Kazakhstan. Site visits to perform construction work and in‐country meetings to discuss project requirements are anticipated to support this effort. The Contractor shall coordinate all visits with the Contracting Officer. All access requests for country and site visits, as well as coordination with the end users, or landowners, of the facility such as obtaining landowner signatures, powers of attorney, and other required documents shall take place through the Security Cooperation Office (SCO) at the U.S. Embassy in Nur-Sultan (Astana), Kazakhstan. Coordination with SCO shall take into account U.S.
and Kazakhstan holidays.
1.11.1. In order to arrange for access to the project site to conduct any type of work there, SCO needs the following information provided no less than thirty (30) calendar days in advance of the date such access is required:
Names, job titles and company names of all individuals who require access to the site.
Passport/ID scans of all of these individuals.
Type, model and license plate number of all vehicles that will need to enter the site.
Types and models of any special equipment that will be used during the survey (to include GPS devices, drilling equipment, topographic survey equipment, etc.).
1.11.2. Cellular phones have been outlawed on government premises in Kazakhstan;
Acknowledgment of cell phone prohibition must be included in access requests if required during the site visit.
1.11.3. Failure to adhere to these requirements will result in the Contractor being turned away at the project site. Changes to dates or personnel on the site visit request require submission of a new request and reset the 30-calendar day approval timeline from paragraph 1.8.1.
1.11.4. Below is an example of a request for site access.
Table 1: Sample Site Access Request
Dates for site access Location
Purpose of the visit
Task order/contract
No./ Project name
Name, job title, company name Remarks
From 10 Military Unit To TO 333/ W913-ER- C
1. Mr. John Johnson, P j
Passport scans for h
September 1234 in conduct 0000/ Design Project f
Manager, TTT P d ti I individuals listed to 15 Almaty, initial Site Astana Kennel and 2. Ms. Inna Ivanova, attached.
November Kazakhstan Survey Support Facility Accountant, CCC I i
20xx Visit LLC
3. Mr. Serik Berikov, I t t SSS Translations
1.12. ALL CHANGES to this SOW must be approved by the Contracting Officer. The Contractor shall not perform any work outside the scope of this contract. Any requests to deviate from the scope of this contract by anyone other than the Contracting Officer must be addressed to the Contracting Officer within three (3) business days of their occurrence to permit the USG to address concerns and resolve them as required to allow construction efforts to continue.
1.13. Unless otherwise noted in writing by the Contracting Officer, the Contracting Officer is the only person with the authority to change, modify, deny or approve any part and has the sole authority for all aspects of contract, SOW, contract changes, approvals, payments and project changes.
1.14. The final technical product and associated deliverables shall be the property of the US Government. As such, when technical products are prepared by Contractor personnel, the Contractor shall not, within professional engineering guidelines, copyright or otherwise restrict the US Government from using, distributing, duplicating, or disseminating this product.
2.0 PRE-CONSTRUCTION EFFORT:
2.1. The Contractor responsible for performing the actual construction work shall review the 100% design and notify the Contracting Officer of any required or recommended changes for approval. The purpose is for the Contractor to ensure the constructability of the design. Any deviations from the final approved design shall be coordinated and approved by the Contracting Officer.
2.2. A Pre-Construction (Pre-Con) meeting is required prior to start of construction. A Pre-Construction meeting shall be held no later than seven (7) calendar days following contract award. Topics to be covered are: Show Times, Approved Haul Routes, Approved Contractor Lay down Areas, Period of Performance and any Contractor questions. Pre-Con members include the Contracting Officer and/or the Contracting Officer Representative.
3.0 SCOPE OF WORK:
3.1. KAZCENT Conference Center:
Work will be completed in accordance with 100% design provided as an addendum to this SOW. KazCent Conference Center is a single-story building with a mezzanine floor, which covers approximately 1/ 3 of the total foot area of the building. The building is rectangular in plan with the dimensions of 30.1 5x1 4.55 m, as column grids are 5.85 x 6.825 m.
The design includes a large conference room, which could be divided into 3 smaller conference rooms with movable wall panels. The large conference room has a stage at the north end and mezzanine floor at the south end. The conference rooms are technically and functionally designed as they can be used as merged or separately.
The lobby area is longitudinal extending from cloak room to south (side) entrance. This area will be used as foyer and lounge area, where visitors will be hosted prior to conferences or at interludes. Access to the mezzanine floor will be provided by a decorative round stair, located at the south side of the lobby area.
This longitudinal area also extends to the south entrance and the restroom area.
Conference rooms will be flexible in use with the help of movable (acoustical) wall panels. They could be either merged as a single large room (including mezzanine), or could be used as separate rooms, when the attendees are less. Tables and chairs will be movable so sitting arrangement could be modified with different setups such as theatre sitting, classroom sitting, board room sitting, or hollow square sitting.
The building and all common areas (except the mezzanine) will be accessible by disabled people. Two main entrance doors and three emergency exits will be led by ramps with proper slope. The ramps will be provided with the required dimensions, slopes and features such as handrails and detectible warning tiles as required in SN RK 3.06-01 -2011. All flooring surf ace materials will be non-slippery, in order to provide safety precautions for disabled people. From parking lot to the south entrance, continuous detectable warning tiles will be installed. Likewise, the beginning and ending of all ramps will be indicated by the warning tiles. Please refer to general plan for more information about the location of tiles.
All emergency egresses are designed as complying the minimum required dimensions for disabled people.
There will be a dedicated restroom for disabled people designed according to turning radius and including grab bars and emergency button.
3.2. Demolition:
The plan set shows two existing buildings to be demolished. The Contractor shall demolish both buildings per the drawings. Those buildings have already been demolished; therefore the Contractor is not responsible for demolition of those buildings. The concrete slab and foundations of those two buildings remain; the Contractor is responsible for demolition and removal of the concrete slab and foundations as part of this Scope of Work. There are three existing trees that are shown to be relocated in the plans; these three trees shall be demolished and removed from the site.
In addition, all abandoned utility lines shall be removed by the Contractor if there is a conflict with the new construction.
3.3. Relocations:
There are three existing trees that the Contractor is responsible for relocating prior to construction start.
The Contractor shall relocate those trees to the location within the compound identified by the compound authorities. The Contractor shall utilize the services of an arborist or other specialist to ensure proper care is taken in the relocation process.
Several utility lines which conflict with the new construction need to be re-routed. Please refer to demolition plan and underground utilities plan for more detailed information.
3.4. Utilities:
The Contractor shall install all water, sewer, and electrical utilities per the plans. Any fees, permits or any other costs for construction or connecting to existing utilities shall be paid for by the Contractor and all costs shall be paid for under this bid item.
3.5. Optional Bid Item Furniture and Equipment
As an option for the Government, the Contractor shall procure and install all furniture and equipment shown on the plans. Optional Furniture and Equipment is the following items from "11. 100 Design KACENT-TE" Sheets TE.SO: 1, 2, 3, 4, 5, 7, 7a, 8, 10, 11, 12, 13, 14, 15, 15a, 16,32, 33, 34, 36, 41, 42, 43, 44, 45, 46, 47, 48, 49, 51, 56. 57, 58, 59, 61, 62, 63, 64, 66, 70. All other items shall be included in the base bid.
3.6. Optional Bid Item Landscaping
As an option for the Government, the Contractor shall procure, plant and maintain all landscaping. The Contractor shall maintain all landscaping for a minimum of 60 days after the turnover of the project. Any landscaping features that die, brown or are damaged during the 60 day period shall be replaced by the Contractor at no cost to the Government. "Optional Landscaping" is all items on "8. 100 Design KAZCENT-GP, Sheet GT4" with the exception of Linear Warning Strips, Detectable Warning Tiles, and Handrails. Linear Warning Strips, Detectable Warning Tiles, and Handrails shall be included in the base bid.
*The government reserves the right to exercise Furniture within 60 days, and Landscaping within 240 days of contract award.
4.0 SPECIFICATIONS:
4.1. The Contractor shall submit a full set of English translated Kazakhstan Building Codes and Regulations prior to submittal of the first construction submittal. See Section 01 35 13 for further information.
4.2. All work must meet local Kazakhstan construction standards and, as a minimum baseline, meet the requirements detailed below in this SOW and in the 100% design included as an addendum to this SOW.
Instances where specifications below are not used shall be highlighted to the contracting officer during submittals for approval.
4.3. The Contractor shall be liable for any damage caused to public or private property as a result of negligent acts by the Contractor, Sub Contractor, employee, agent, or representative of the Contractor.
4.4. Any questions or concerns during the construction process regarding these specifications shall be addressed to the Contracting Officer prior to the construction submittal in the phase they are identified.
Concerns shall identify the specification in question and the conflict or concern to be addressed. Any supporting documentation, references or standards provided with the question or concern will assist with providing a prompt response.
4.5. COLD WEATHER CONSTRUCTION: The following are minimum standards for cold weather construction.
4.5.1. All snow and ice shall be removed from construction surfaces prior to starting construction each day.
4.5.2. Cold weather construction is defined as temperatures below 5 degrees Celsius for three
(3) consecutive days or if ambient temperatures are projected to drop below 5 Celsius degrees within the next five (5) calendar days.
4.5.3. If any construction is performed during these weather conditions, a cold weather construction plan must be submitted to the Contracting Officer, to include concrete mixture, curing, and foundation construction plan at a minimum. Plan shall also include measures taken to protect and heat masonry materials including both block and mortar ingredients. Methods such as weather-resistive blankets, heaters, weather-resistive membranes, and heating enclosures shall be utilized as required to keep materials above 4.4 degrees Celsius.
4.5.4. During cold weather construction, contractor shall provide documentation of methods used in accordance with the cold weather construction plan in their weekly reports.
4.6. WET WEATHER CONSTRUCTION: The following are minimum standards for wet weather construction.
4.6.1. CONCRETE/MORTAR: Concrete shall not be placed if it is actively raining. If rain is projected within five (5) calendar days of concrete placement, concrete must be protected from rain while curing. Concrete shall not be placed on a wet surface in which water has affected compaction.
4.6.2. FOUNDATIONS: Foundation work shall not be placed directly on wet soil/engineered fill if there is standing water or if water infiltration is deeper than 1 inch into the soil/engineered fill.
“Muddy” conditions are not appropriate for foundation work, unless excavated or dried.
4.6.3. INTERIOR: Structure must be waterproofed and protected from weather conditions prior to final interior finishes such as drywall, carpet, and ceiling being installed.
4.7. Structure: Structural system of the building will be prefabricated metal facility. The entire steel structure will be located on reinforced concrete foundations consist of stem walls, pedestals, tie columns, footings, and mat foundation (concrete class B25, steel reinforcement A-III). The total depth of the foundation will be 2800 mm from the floor finish level. The foundation walls will be insulated and wrapped with vapor barrier from the exterior side of the stem wall. Thus, there will not be any insulation underlying the slab on grade. Structural elements will not be exposed after the completion of architectural finishing. Slab on grade will be cast-in-place reinforced B-25 concrete with the thickness of 1 25 mm, with the reinforcement of Class A-III. All steel structure will be painted by 2 layers of fire rated primer and 2 layer of fire rated paint, in order to increase the performance of fire resistance of the structures. Please refer to metal structure part of the project for more information.
4.8. Façade: Prefabricated metal facility building will be enveloped by cassette profiles filled with 100 mm thick insulation. There are 3 different facade system installed to these cassette profiles: Composite Aluminum Paneling System, Brick Cladding System, Trapezoidal Paneling System. All transition between windows, doors, and facade will be properly sealed and flashing will be provided if necessary. The entire facade will be illuminated by wall washers. In addition, there will be a hidden exterior lighting at the parapet niche of the facade.
4.9. Partition Walls: Internal partitions will be made of gypsum wall board s with various thickness, which is classified in the wall schedule. Partition systems will be safe enough to carry the own load and any load transferred to them. Any installation on walls require wall blocking inside of the partition. Several partitions will be sound, or fire rated per schedule. Refer to wall schedule for detailed information.
4.10. Roof: It will consist of insulated sandwich panels installed on purlins. Roof slope will be 8% (1:1 2) and the minimum height of the parapet will be one meter and will vary with the roof slope. There will be 6 drains and 4 overflow scuppers on the roof for the discharge of rainwater. Roof will be accessed by roof hatch, which meets the life safety requirements. All roof equipment and devices will be installed on metal support framing, which is directly tied to main structure.
4.11. Electrical: The current project is subject to II category of power supply with the exception of evacuation lighting, electric receivers of fire-fighting devices, fire alarm and notification systems and evacuation management, which belong to the I category of power supply reliability
5.0 CONSTRUCTION SCHEDULING AND PHASING OF WORK:
5.1. These sections are intended to guide construction, cost estimates, and development of the construction deliverables.
5.2. The government reserves the right to start and stop construction at no additional cost to the government if any safety concerns are observed or reported.
5.3. Contractor must attend pre-con prior to construction start.
5.4. The Contractor shall commence construction activities within five (5) calendar days of receiving the Construction Notice to Proceed.
5.5. The Contractor shall complete all specified work within 270 calendar days from Construction Notice to Proceed.
5.6. General Schedule: All products and deliverables are due to the Contracting Officer. US Government will return comments, if any, after review.
Award: Begin scheduling construction activities Award + 7 calendar days: Pre-Con Meeting scheduled
Award + Administrative NTP: Contractor shall submit all preconstruction submittals, foundation submittals, and pre-engineered building submittals
Construction NTP + Total Period of Performance: Contractor must have completed all work
6.0 STORAGE AND DISPOSAL OF CONTRACTOR MATERIALS DURING CONSTRUCTION:
6.1. These sections are intended to guide construction, cost estimates, and development of the construction deliverables.
6.2. The Contractor shall be responsible for the receipt, unloading, security and handling of all equipment and materials required for the completion of this work. The Contractor shall identify storage area requirements and coordinate said location with the Contracting Officer.
6.3. The Contractor shall be responsible to properly dispose of all debris generated by this contract in accordance with all Kazakhstan laws. The Contractor shall ensure all trash and debris is cleaned and removed from the site daily. All trash and debris shall be placed in the appropriate trash receptacles provided by the Contractor at or around the construction site.
6.4. The Contractor shall secure all material and equipment at the end of each working day.
6.5. All materials are the responsibility of the Contractor; Government will not reimburse Contractor for stolen items or delivery related additional incurred costs (such as weather related materials delays).
7.0 CONSTRUCTION CONTRACTOR FURNISHED ITEMS AND SERVICES:
7.1. These sections are intended to guide construction, cost estimates, and development of the construction deliverables.
7.2. The Contractor shall furnish all necessary supplies, fuels, lubricants, solvents, parts, materials, equipment, products, tools, electricity, any other items, and all services that are required to perform this statement of work.
8.0 CONSTRUCTION INSPECTIONS/QUALITY CONTROL:
8.1 Contractor Quality Control
8.1.1 The Contractor shall conduct quality control of all work on site. Quality control includes but is not limited to appropriate material selection, testing, inspections, reporting, identifying and correcting deficiencies without input from the USG.
8.1.2 The Contractor shall comply with the general terms of the overall contract with respect to construction quality control, inspections of the work by the Contracting Officer, and acceptance inspections.
8.1.3 Any concerns regarding clarification of drawings or specifications shall be directed to the Contracting Officer or Contracting Officer Representative for resolution.
8.2 SAFETY:
8.2.1 The Project Engineer, COR or the Contracting Officer may stop work at any time for a potential safety hazard. The Contracting Officer is the only personnel allowed to restart work in writing.
8.2.2 The Contractor shall certify that products do not contain mercury, lead, hexavalent chromium, toluene, chlorinated solvents, hydrolysable chlorine derivatives, ethylene based glycol ethers and their acetates, nor any carcinogen. When tested, the lead content shall not exceed 0.06% by weight of the dry film and the test for chromium content shall be negative.
8.2.3 The Contractor shall ensure on-site safety meets all Kazakhstan requirements.
8.3 SITE INSPECTIONS:
8.3.1 The Contracting Officer or Contracting Officer’s Representative shall conduct regular site inspections for Quality Assurance purposes. This is independent of the Contractor’s internal Quality Control Plan and does not relieve the Contractor of overall responsibility for construction quality.
8.3.2 The Contracting Officer or Contracting Officer’s Representative are the only personnel authorized to direct the contractor to make any changes to ongoing work. The Contracting Officer is the only person with authority to make revisions to the scope of this project.
8.4 Progress Photos:
8.4.1 The Contractor shall upload all progress construction photos and all submittals to the Resident Management System (RMS). See Section 01 45 00.15 10 for RMS information.
9.0 CONSTRUCTION SUBMITTAL REQUIREMENTS:
9.1. These sections are intended to guide construction, cost estimates, and development of the construction deliverables. All submittals shall be reviewed and approved through Author’s Supervision to ensure compliance with Kazakhstan Codes and Laws prior to submittal to the Government. The Author’s Supervisor shall submit a signed statement (in English) for each submittal attesting that the submittal meets Kazakhstan Codes and Laws.
9.2. GENERAL: For each facet of construction, the Contractor shall submit material catalog data, and material samples to the Contracting Officer for approval a minimum of ten (10) calendar days prior to procurement and placement of that particular material and construction respectively. Upon review by the Contracting Officer, the submittals along with any comments will be returned to the Contractor. The Contractor shall modify the submittals per the USG’s comments and resubmit within three (3) calendar days for final approvals. Upon final approval, the Contractor shall commence with the procurement and construction activity accordingly.
9.3. MASTER SCHEDULE: The Contractor shall provide a comprehensive master schedule in support of their proposal. This original schedule shall contain key milestones, critical path, and proposed start/completion dates and shall be considered as the project baseline schedule upon award. The Contractor shall update this master schedule monthly or as critical tasks are exceeded more than 10 calendar days.
9.4. SITE WORK: The Contractor shall submit certified test results via email to the Contracting Officer from compaction, concrete, and any other site tests and receive notification of acceptance from the Contracting Officer prior to moving to next phase. Contracting Officer shall approve test results. Concrete test results are required for seven (7) calendar day and 28 calendar day strength test. If Contractor moves on prior to full strength being attained and the strength tests are not sufficient at the 28 calendar day point, Contractor shall be responsible for replacement of concrete and any additional work affected by concrete at no additional cost to the Government.
9.5. STRUCTURAL: The Contractor shall submit a complete set of structural shop drawings for the proposed concrete foundation and other structural systems. The concrete floor slab shall show block outs for utility points. Construction on structural work shall not commence until approval of the structural shop drawings have been received by the Contractor and all USG comments have been incorporated.
9.6. PLUMBING: The Contractor shall submit a complete set of shop drawings for all plumbing systems.
Calculations shall be provided to substantiate the sizes for all piping, water heaters, water hammer arrestors, valves, etc. The Contractor shall coordinate the connection of the facility plumbing and waste systems with the local site utilities. Catalog cuts for all plumbing equipment and materials proposed for installation shall be submitted.
9.7. EQUIPMENT: The Contractor shall submit catalog cuts for the equipment and materials the Contractor shall install for Contracting Officer approval. The catalog cuts shall include the manufacturer’s name, address, and telephone number. The submittals shall include the physical size of the equipment, performance characteristics at design conditions, ratings (electrical or otherwise), and other pertinent standards. Equipment or devices selected by the Contractor shall be clearly identified especially when the catalog cut lists multiple items.
9.8. STATUS REPORTS: The Contractor shall submit a weekly status report via email and RMS to Contracting Officer Representative (COR) no later than Friday afternoon by 5 PM Kazakhstan time each week until the contract is complete. At a minimum, the weekly report shall include:
Contract number
Name of project manager and contact information
Overall percentage Work In Place (Planned and Actual)
Estimated completion date (Planned and Actual)
Key tasks accomplished during the past week
Work expected to be accomplished during the upcoming week Significant Issues/Events
At least five (5) digital photos of new work accomplished, if applicable
9.9. PROGRESS PAYMENTS: Contractor shall use RMS to submit all progress payment requests.
9.10. FINAL INSPECTION: The Contractor shall provide the Contracting Officer a consolidated inventory of all installed equipment, operations manuals at the final inspection.
9.10.1. The contractor shall be solely responsible for obtaining final approval of any local and state agencies prior to final acceptance and furnishing any required documentation of supervision required for such approvals.
9.10.2. PARTS, SERVICE AND OPERATION & MAINTENANCE MANUALS: Standard Parts, Service and Operation & maintenance manuals shall be submitted to the Contracting Officer in English and Russian, as hard copy in Russian-only, and in English and Russian in electronic PDF format to include the following:
9.10.2.1. Manufacturer’s technical catalogues, dimensional drawings and wiring diagrams for each and every type of equipment installed.
9.10.2.2. Operating instructions for various equipment and systems included in the installation work.
9.10.2.3. Parts, Service and Maintenance manuals for all equipment and systems included in the installation work, which require regular and specialized maintenance. These manuals shall include at a minimum, all scheduled service required and a suggested inventory of parts required for the maintenance of the units for a period of 5 years.
9.10.3. ACCEPTANCE TESTS AND APPROVALS: Acceptance tests shall be performed by the Contractor in the presence of the Contracting Officer or Contracting Officer’s Representative on all systems installed by the Contractor. The Contractor shall give the Contracting Officer at least seven (7) calendar days advance notice prior to testing date of all systems.
9.10.4. FURNISHINGS AND EQUIPMENT LIST: Contractor shall provide a complete list of furnishings and equipment purchased for construction of the project. List shall be numbered and include, name, make, model, dimensions, manufacturer, quantity, item cost and total cost for the item in USD and KZT. List shall be subtotaled for equipment and subtotaled for furnishings with a total cost for both at the bottom of the list. List shall be provided to the Contracting Officer as two electronic PDF copies (Russian and English) prior to the final inspection. Contractor shall be prepared to provide up to three (3) hard copies for government agencies and end users.
9.10.5. AS-BUILT DRAWINGS: Contractor shall provide two electronic PDF copies (Russian and English) of as-built drawings to the Contracting Officer within thirty (30) days of construction completion. Contractor shall be prepared to provide up to three (3) hard copies of as-builts for government agencies and end users.
9.10.6. The Contractor shall ensure compliance with Kazakhstan commissioning and government acceptance requirements, codes, laws and regulations and ensure that all associated documentation is provided at the final inspection and acceptance of built facilities to the end user.
That includes, but not limited to: Conclusion of Working Commission on Facility Readiness for the presentation to the State Acceptance Board; Act of State Acceptance Board for the commissioning of built facility; Updated Technical Conditions Documents for all utilities (if in possession of contractor); Hard copies of As-built drawings for the facilities and all of the utilities and infrastructure in Russian/Kazakh language
9.10.7. Originals/copies of all hardware/equipment operating manuals installed as part of the construction, as well as warranty documentation.
9.11. WARRANTY INFORMATION: The Contractor shall provide a one (1)-year warranty on all equipment, materials and furnishings constructed or installed within the facility. The Contractor shall provide contact information and warranty call procedures in English and Russian, as hard copy in Russian-only, and in English and Russian in electronic PDF format. Disagreements with regard to responsibility for any damages or failures with equipment, furniture or constructed items shall be addressed to the Contracting Officer for resolution.
ATTACHMENTS:
1. Administrative Specifications - Below
2. Complete Design Drawings (PDF) RFP Attachments #7-21.
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 VIEW LOCATION MAP
1.4 PROGRESS AND COMPLETION PICTURES
1.5 SUBCONTRACTORS
1.6 Contractor Team Members
1.6.1 Professional Registration
1.6.2 Geotechnical Engineer Qualifications
1.6.3 Electrical Worker Qualifications
1.7 SUPERVISION
1.7.1 Linguist Requirement
1.7.2 Superintendent Qualifications
1.7.2.1 Duties
1.7.3 Non-Compliance Actions
1.8 PRECONSTRUCTION
1.8.1 Meeting Minutes
1.8.2 Contract Documents
1.9 MUTUAL UNDERSTANDING MEETING
1.10 FACILITY TURNOVER PLANNING MEETINGS (RED ZONE-RZ)
1.10.1 RZ CHECKLIST
1.10.2 MEETINGS
1.11 PARTNERING
1.12 ELECTRONIC MAIL (E-MAIL) ADDRESS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
1.3 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.4 PROGRESS AND COMPLETION PICTURES
The pre-construction and post-construction conditions of permanent roads, streets, driveways, sidewalks, buildings, structures, and above-ground utilities shall be documented by the use of Contractor-furnished photographs or videos. Videos shall be digital format 1080p or higher (DVD) with voice over commentary in English describing all pertinent or unusual conditions. Videos shall have a stamped date. Photographs shall be digital (10 mega pixels or higher), color, and shall have stamped date.
The Contractor shall provide 2 copies of each DVD and 2 copies of photo CDs containing files to the Contracting Officer for the Contract file. Each Contract building/structure/feature shall be on a separate disc. Discs shall be labeled with the contract number, building/structure/feature number and name, and date.
If the Contractor submits video: Each Contract building/structure/feature shall be fully documented for each level and room to show completely all walls, hallways, mechanical, electrical, and other utility rooms, staircases, and any specialty rooms and areas. Supplemental lighting shall
SECTION 01 30 00 Page 2 be provided in areas that have low light levels. All equipment shall be documented to show components, equipment, appurtenances, and other identifying information such as nameplates, tags, and other feature identifiers. The roof (if accessible) and all roof equipment shall be included. The complete outside of the building or structure shall be included. All outdoor features and utilities, to also include substations, shall be documented. Transmission power lines may be documented by vehicle mounted camera. Disc filenames shall include description of video contents.
If the Contractor submits digital photographs: Each Contract building/structure/feature shall be fully documented for each level and room to show completely all walls, hallways, mechanical, electrical, and other utility rooms, staircases, and any specialty rooms and areas.
Supplemental lighting shall be provided in areas that have low light levels. All equipment shall be documented to show components, equipment, appurtenances, and other identifying information such as nameplates, tags, and other feature identifiers. The roof (if accessible) and all roof equipment shall be included. The complete outside of the building or structure shall be included. All outdoor features and utilities, to also include substations, shall be documented. Transmission power lines may be documented by vehicle mounted camera. Photograph filenames shall include a brief description of photo contents, the photo location and orientation, and the room number and name.
The Contractor shall coordinate so that representatives of the Contracting Officer are present during the pre- and post-construction documentation.
Pre-construction documentation shall be completed prior to work and shall be submitted within 20 days. Post-construction documentation shall be performed within 7 days of the beneficial occupancy date or the final inspection for that feature of work, whichever occurs sooner. No measurement will be made for video and photographic documentation. Payment will be made at the contract job price for "Mobilization and Demobilization". Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment for video and photographic documentation as specified herein.
Videos shall be digital format 1080p or higher (DVD) with voice over commentary in English describing all pertinent or unusual conditions.
Videos shall have a stamped date. Photographs shall be digital (10 mega pixels or higher), color, and 4 inch x 6 inch size minimum, and shall have stamped date. The Contractor shall provide two (2) copies of each DVD and two (2) copies of photos CDs containing files to the Contracting Officer for the Contract file. Electronic photos shall be accompanied by a log describing the content of each.
Construction Progress photos: The contractor shall provide to the Contracting Officer Representative (COR) by email at regular intervals (at least weekly) construction progress photos throughout the construction duration. The photos shall document all construction progress. Photos shall be provided which document the overall progress of the job, progress of individual systems and details of each system. The overall progress photos shall be taken from the same location each time. All photos shall be accurately and permanently dated and time stamped on the photo image, shall be approximately 1-megabyte in size and shall be named using the following file naming protocol: What_When_Contract #_Contract title.jpg "What" is a brief description of the photo content and "When" is the date photo was taken.
Each new building/ structure shall be recorded on a separate DVD. Each room
SECTION 01 30 00 Page 3 shall be documented showing all 4 walls. Supplemental lighting shall be provided in areas that have low light levels. Hallways, mechanical, electrical and HVAC rooms, and the roof (if accessible) shall be included in the video to document workmanship, equipment and life safety features.
The complete outside of the building or structure shall be included with video. Outdoor facilities, parking lots, roads, curbs, barriers, and substations shall be documented.
The Contractor shall coordinate so that representatives of the Contracting Officer are present, if possible, during the pre- and post-construction documentation. Pre-construction documentation shall be completed prior to work and shall be submitted within 20 days. Post-construction documentation shall be performed within 7 days of the beneficial occupancy date or the final inspection for that feature of work, whichever occurs sooner. No measurement will be made for video and photographic documentation.
Payment will be made at the contract job price for “Mobilization and Demobilization”. Price and payment shall constitute full compensation for furnishing all plant, labor, materials and equipment for video and photographic documentation as specified herein.
1.5 SUBCONTRACTORS
Compliance by all subcontractors with the provisions of this section shall be the full responsibility of the Contractor.
1.6 Contractor Team Members
1.6.1 Professional Registration
The Contractor may be a single firm or a team of firms that includes registered Architects and Engineers either employed by or subcontracted to the Contractor. Licensing jurisdiction of Architects and Engineers of record shall be verifiable. The Contractor shall be the Architect/Engineer-of-Record for all work not associated with the furnished drawings, whether the contractor utilizes services of licensed architects and engineers employed by its firm or subcontracts with independent architectural and/or engineering firm(s). The Contractor shall be solely liable for design errors and/or omissions and should be insured as the A-E firm against design errors and omissions.
1.6.2 Geotechnical Engineer Qualifications
A geotechnical engineer, qualified by education in geotechnical engineering, or geotechnical firm responsible to the Contractor shall develop all geotechnical engineering design parameters by appropriate field and laboratory investigation and analysis.
1.6.3 Electrical Worker Qualifications
All electrical work shall be performed by Journeymen Electricians and supervised by one Lead Electrician. The Lead electrician must be on site at all times during electrical installations and be capable of installing as well as directing the installation of all electrical work in compliance with the governing Code. Apprentice Electricians are allowed to assist the Journeymen, but the ratio of Apprentices to Journeymen shall not exceed 3:1. Qualifications for each person to perform electrical work shall be as indicated below.
SECTION 01 30 00 Page 4
a. Lead Electrician
(1) Proof of Completion of an Electrical Safety Course AND
(2) Proof of Completion of an Electrical Code Class (NEC or BS 7671)
AND
(3) Graduate of an Approved Trade School AND
(4) 4,000 hours of verifiable commercial/industrial electrical experience
b. Journey Electrician
(1) Proof of Completion of an Electrical Safety Course AND
(2) Proof of Completion of an Electrical Code Class (NEC or BS 7671)
AND
(3) Graduate of an Approved Trade School AND
(4) 2,000 hours of verifiable commercial/industrial electrical experience
c. Apprentice Electrician
(1) Proof of Completion of an Electrical Safety Course AND
(2) Proof of Completion of an Electrical Code Class (NEC or BS 7671)
1.7 SUPERVISION
1.7.1 Linguist Requirement
a. All official communication between the Contractor and the Government shall be presented in English.
b. At all times during the performance of this Contract when a U.S.
Governement representative is scheduled to be on site, and until all work is complete and accepted, the Contractor shall have a minimum of one representative (Linguist) on site that is fluent in both English and the local language.
c. The Linguist shall attend all meetings with the Government.
d. The Contracting Officer's Representative (COR) will approve of whom the Contractor provides as its Linguist. At any time upon the request of the COR, the Contractor shall remove the Linguist from its staff and replace with another until found to be satisfactory for contractual communication as determined by the COR.
e. A satisfactory Linguist shall be defined as a person with the ability to:
(1) Convey verbal information in English to the Government in a clear and concise manner;
(2) Receive and understand verbal information in English from the Government in a clear and concise manner;
SECTION 01 30 00 Page 5
(3) Read and write the English language in a clear and concise manner;
and
(4) Convey, communicate, and interpret information in both English and the local language between all multiple language parties at meetings, site visits, in official letters and e-mails, and all other contractual communications as required.
1.7.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
1.7.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.7.3 Non-Compliance Actions
The Project Superintendent or Project Manager is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.8 PRECONSTRUCTION
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
Within seven (7) days of receipt of Notice to Proceed (NTP), prior to
SECTION 01 30 00 Page 6 commencement of the work, the Contractor and any Subcontractors whose presence is necessary or requested, shall meet in conference with representatives of the Contracting Officer to discuss execution of this Contract, with special emphasis on preconstruction requirements. These discussions will include but not necessarily be limited to the Contractor's Quality Control (CQC) Program, the Contractor’s Accident Prevention Program (APP), submittals, correspondence, schedule, access to the work site, security requirements, interface requirements, temporary facilities and services, hazards and risks, working after normal hours or on weekends or holidays, assignment of inspectors, representations, special requirements, phasing, and other aspects of this project that warrant clarification and understanding.
1.8.1 Meeting Minutes
It shall be the responsibility of the Contractors CQC System Manager to prepare detailed minutes of this meeting and…