Exhibit_C_-_Contract_Data_Requirements_List_-_.50_Caliber.pdf

PDF 261 KB Posted

Attached to
Lake City Army Ammunition Plant (LCAAP) - Draft RFP
Solicitation number
W52P1J-17-R-0141
Issued by

About this file

This exhibit outlines data requirements for a .50 caliber ammunition production contract. Key requirements include submission of an ammunition data card with each lot shipped and loaded into the Munitions History Program database. A quality program plan must be submitted prior to first article testing or production start and updated annually. A measurement system evaluation plan is due 60 days prior to first article testing to ensure inspection and testing equipment is validated. Statistical process controls must be implemented and documented in a plan submitted 60 days prior to first article testing. Critical quality characteristics must be defined and controlled according to a plan submitted 60 days prior to testing. First article testing plans are due 60 days prior to testing for review and approval. Test reports and failure analyses will be submitted for government review.

Exhibit C - Contract Data Requirements List - .50 Caliber

View the file

Other files

File Type Posted
LCAAP_Draft_RFP_Q&As__1_Rev_1.pdf PDF
LCAAP_Draft_RFP_Q&As__2.pdf PDF
LCAAP_Draft_RFP_Q&As.pdf PDF
W52P1J-17-R-0141_-_DRAFT_Rev_1_-_19JUL18.pdf PDF
Attachment_0037_-_Price_Matrix_-_Summary_Evaluation_Matrix.xlsx XLSX spreadsheet
Attachment_0046_-_Component_Suppliers_Template.xlsx XLSX spreadsheet
Attachment_0011_-_PWS_11_-_Occupational_Health_and_Industrial_Hygiene.pdf PDF
Attachment_0016_-_PWS_16-_On-Site_Government_Personnel_Support.pdf PDF
Attachment_0029_-_Price_Matrix__7.62mm_Family.xlsx XLSX spreadsheet
Exhibit_B_-_Contract_Data_Requirements_List_-_7.62mm.pdf PDF
Exhibit_E_-_Contract_Data_Requirements_List_-_Caliber_.22.pdf PDF
Attachment_0040__-_Price_Matrix_(INDEMNIFIED)_-_5.56mm_Family.xlsx XLSX spreadsheet
Attachment_0017_-_PWS_17_-_Armament_Retooling_and_Manufacturing_Support.pdf PDF
Attachment_0007_-_PWS_7_-_Government_Property_in_Possession_of_the_Contractor.pdf PDF
Attachment_0027_-_Award_Term_Plan.pdf PDF
Attachment_0002_-_PWS_2_-_Safety.pdf PDF
Attachment_0050_-_Example_Order_-_7.62mm.pdf PDF
Attachment_0024_-_DD254_-_Contract_Security_Classification_Specification_(FOR_POSTING).pdf PDF
Attachment_0034_-_FAAT_Price_Matrix_-_.50_Caliber.xlsx XLSX spreadsheet
Attachment_0009_-_PWS_9_-_Contract_Production_and_Delivery_Reporting.pdf PDF
Exhibit_A_-_Contract_Data_Requirements_List_-_5.56mm.pdf PDF
Attachment_0003_-_PWS_3_-_Security_and_Antiterrorism_(FOR_POSTING).pdf PDF
Attachment_0025_-_Hazardous_Material_Classification.pdf PDF
Attachment_0001_-_PWS_1_-_Maintenance.pdf PDF
Exhibit_F_-_Contract_Data_Requirements_List_-_PWS.pdf PDF
Attachment_0012_-_PWS_12_-_Support_of_Onsite_Government_BSO_and_NATO_North_American_Regional_Test_Center.pdf PDF
Attachment_0039_-_Currency_Fluctuation_Worksheet.xlsx XLSX spreadsheet
Attachment_0047_-_Small_Business_Participation_Plan.pdf PDF
Attachment_0030_-_Price_Matrix__.50_Caliber_Family.xlsx XLSX spreadsheet
Attachment_0033_-_FAAT_Price_Matrix_-_7.62mm.XLSX XLSX spreadsheet
Attachment_0010_-_PWS_10_-_Contract_Start-Up_and_Transition.pdf PDF
Attachment_0013_-_PWS_13_-_Mowing_(FOR_POSTING).pdf PDF
Attachment_0020_-_EPR_NDA_-_Corporate.pdf PDF
Attachment_0008_-_PWS_8_-_Ammunition_Materiel_Management.pdf PDF
Attachment_0049_-_Example_Order_-_5.56mm.pdf PDF
Attachment_0044_-_Virtual_Techncial_Library_-_On-Site_Library_Contents_(FOR_POSTING).pdf PDF
Attachment_0043_-_Price_Matrix_(INDEMNIFIED)_-_.22_Caliber.xlsx XLSX spreadsheet
Attachment_0028_-_Price_Matrix_-_5.56mm_Family.xlsx XLSX spreadsheet
Attachment_0045_-_SAIC_Non-Disclosure_Agreement.pdf PDF
Attachment_0023_-_Government_Owned_Equipment_(FOR_POSTING).pdf PDF
Attachment_0041_-_Price_Matrix_(INDEMNIFIED)_-_7.62mm_Family.xlsx XLSX spreadsheet
Attachment_0022_-_Sample_OPSEC_Plan.pdf PDF
Attachment_0018_-_PWS_18_-_Facility_Plans,_Strategies,_and_Analyses.pdf PDF
Attachment_0048_-_Past_Performance_Questionnaire.pdf PDF
W52P1J-17-R-0141_-_DRAFT_29JUN18.pdf PDF
Attachment_0031_-_Price_Matrix_-_.22_Caliber_Family.xlsx XLSX spreadsheet
Attachment_0006_-_PWS_6_-_Fire_and_Emergency_Services.pdf PDF
Attachment_0035_-_FAAT_Price_Matrix_-_.22_Caliber.xlsx XLSX spreadsheet
Attachment_0038_-_EPA_Material_Content_Factors.pdf PDF
Exhibit_D_-_Contract_Data_Requirements_List_-_.30_Caliber.pdf PDF
Show 40 more

Latest 50 of 64 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit C June 20, 2018

Contract Data Requirements List .50 Caliber Family Production Items

A001

Title:

Ammunition Data Card

(ADC)

App Code: A

Subtitle: Data Input Dist Statement Required: B

Data Item Number: DI-MISC-80043B Frequency: ASREQ

Contract Reference: Section C As of Date: N/A

Requiring Office: AMSJM-QAO/P Date of 1st Submission: ASREQ

DD 250: XX Date of Subsequent Submission: ASREQ

Distribution Draft Reg Repro

WARP 0 1 0

Lot Shipment 0 1 0

REMARKS

Sample ADC shall be submitted into the Munitions History Program (MHP) system and approved prior to First Article Test (FAT) or initiation of production if FAT is not required. ADCs shall be prepared IAW MIL-STD-1168 by accessing the Worldwide Ammunition Repository Program (WARP) on the Munitions History Program website at https://mhp.redstone.army.mil/.

An ADC shall be submitted with each lot. Any failed lot still requires an ADC to be submitted.

Hard copy ADC provided with lot shipments shall be generated from the WARP and signed/dated by the Government Agency Responsible for Acceptance (GARA).

A002

Quality Program Plan

(QPP)

App Code: A

Subtitle: N/A Dist Statement Required: B

Data Item Number: DI-QCIC-81722 Frequency: ONE/R

Contract Reference: Section E As of Date: N/A

DD 250: LT Date of Subsequent Submission: ASREQ

PCO 0 1 0

PQM 0 1 0

AQE 0 1 0

APO 0 1 0

QAR 0 1 0

The Quality Program Plan (QPP) shall be submitted prior to First Article Test (FAT) or initiation of production if FAT is not required. The Government shall provide response within 30 calendar days of initial submission. If further revisions are necessary, the Contractor shall have 15 calendar days to provide revisions and the Government shall provide response within 15 calendar days. Approval is required prior to FAT or prior to initiation of production. Disposition will be provided by the PCO.

Submit updates/revisions for review and approval prior to implementation.

Submit via email or AMRDEC SAFE: https://safe.amrdec.army.mil/safe/Welcome.aspx Specific email addresses for the distribution list will be provided after contract award.

A003

Title:

Statistical Process Control (SPC) Plan

App Code: A

Subtitle: N/A Dist Statement Required: B

Data Item Number: DI-MGMT-81987 Frequency: ONE/R

Contract Reference: Section E As of Date: N/A

PQM 0 1 0

AQE 0 1 0

The General and Detailed Plan shall be submitted no later than 60 days prior to First Article Test (FAT) or initiation of production if FAT is not required. Approval is required prior to FAT or initiation of production. The Government requires 30 days for review. Disposition of the General and Detailed Plans will be provided through the PCO.

If further revisions are necessary, the Contractor shall have 15 calendar days to provide revisions and the Government shall review and provide disposition within 15 calendar days of receipt.

Submit via email or AMRDEC Safe: https://safe.amrdec.army.mil/safe/Welcome.aspx.

A004

Measurement System Evaluation (MSE) – Measurement and Inspection Equipment System Design Documentation for Acceptance of Product

App Code: A

Subtitle:

Measurement System Evaluation/Acceptance Inspection Equipment

(MSE/AIE)

Dist Statement Required: B

Data Item Number: DI-QCIC-81960 Frequency: ONE/R

Contract Reference: Section E As of Date: N/A

DD 250: DD Date of Subsequent Submission: ASREQ

PQM 0 1 0

AQE 0 1 0

The Contractor shall submit a completed AIE package no later than 60 days prior to First Article Test (FAT) or initial production if FAT is not required. The AIE shall be approved prior to FAT, initiation of production, and/or all acceptance of product under the contract. The PCO will provide disposition within (45) calendar days of final AIE package receipt.

If further revisions are necessary, the Contractor shall have 30 calendar days to generate them and the Government shall have 30 calendar days to review and respond to them. The approved AIE shall be available for FAT, production, and/or all acceptance of product under the contract. If Contractor revises a previously Government accepted AIE for this contract, the revised AIE must be submitted to the Government for review and approval. Approval must be granted before AIE is used for acceptance of product. The Government will respond within 30 calendar days.

The Contractor shall notify the responsible Government technical agency a minimum of 30 calendar days prior to acceptance (prove out) testing for AAIE.

Submit via email or AMRDEC SAFE https://safe.amrdec.army.mil/safe/Welcome.aspx.

Specific email addresses for the distribution list will be provided after contract award.

An MSE Review Guide is available on the ARDEC Public Website (http://www.ardec.army.mil/organizations/QESA/) to assist Contractors in the application of the MSE Clause. The MSE Review Guide's content, in its entirety, is provided solely for REFERENCE and GUIDANCE PURPOSES ONLY- it is not, nor is it intended to be, contractually binding.

Accordingly, the information contained within the MSE Review Guide is expressly not, nor shall it be construed to be, incorporated either directly or by reference into the terms of the MSE clause itself nor into the terms and conditions of any underlying contract which contains the MSE clause.

A005

Critical Characteristics Control Plan (CCCP)

App Code: A

Subtitle: N/A Dist Statement Required: B

Data Item Number: DI-MGMT-81986 Frequency: ANNLY

Contract Reference: Section E As of Date: N/A

PQM 0 1 0

AQE 0 1 0

The CCCP shall be submitted 60 days prior to First Article Test (FAT) or initiation of production if FAT is not required.

Government shall provide response within 45 calendar days of initial submission. Disposition of the CCCP will be provided by the PCO. If further revisions are necessary, the contractor shall have 15 calendar days to provide revisions and the Government shall provide a response within 15 calendar days. The CCCP shall be approved prior to FAT or the initiation of production.

Submit updates/revisions for review and approval prior to implementation. Government shall provide a response within 15 calendar days of receipt and contractor shall response to any comments within 15 calendar days.

Submit via email or AMDEC SAFE: https://safe.amrdec.army.mil/safe/Welcome.aspx Specific email addresses for the distribution list will be provided after contract award.

A CCCP Review Guide is available on the ARDEC Public Website (http://www.ardec.army.mil/organizations/QESA/) to assist Contractors in the application of the CCCP requirement. The CCCP Review Guide's content, in its entirety, is provided solely for REFERENCE and GUIDANCE PURPOSES ONLY- it is not, nor is it intended to be, contractually binding. Accordingly, the information contained within the CCCP Review Guide is expressly not, nor shall it be construed to be, incorporated either directly or by reference into the terms of the CCCP requirement itself nor into the terms and conditions of any underlying contract which contains the CCCP requirement.

A006

Title:

Critical Plan Of Action

(CPOA)

App Code: A

Subtitle: N/A Dist Statement Required: B

Data Item Number: DI-MGMT-81996 Frequency: ASREQ

Contract Reference: Section E As of Date: N/A

PQM 0 1 0

AQE 0 1 0

The Contractor may voluntarily submit a CPOA for all critical characteristics as specified in the critical characteristic requirement. If contractor chooses to utilize the CPOA, it shall be updated and resubmitted on an annual basis from the date that the CPOA is approved.

The Contractor shall submit the CPOA for approval prior to use. The Government requires 45 calendar days for review.

Disposition of the CPOA will be provided through the Procuring Contracting Officer (PCO). CPOA shall be approved prior to implementation. If further revisions are necessary, the Contractor shall provide revision within 15 calendar days and the Government will provide disposition within 15 calendar days of receipt.

Submit via email or AMRDEC SAFE: https://safe.amrdec.army.mil/safe/Welcome.aspx.

Specific email addresses for the distribution list will be provided after contract award.

A CPOA Review Guide is available on the ARDEC Public Website (http://www.ardec.army.mil/organizations/QESA/) to assist Contractors in the application of the CPOA requirement. The CPOA Review Guide's content, in its entirety, is provided solely for REFERENCE and GUIDANCE PURPOSES ONLY- it is not, nor is it intended to be, contractually binding. Accordingly, the information contained within the CPOA Review Guide is expressly not, nor shall it be construed to be, incorporated either directly or by reference into the terms of the CPOA requirement itself nor into the terms and conditions of any underlying contract which contains the CPOA requirement.

A007

Critical Safety Item, Characteristic, and Critical Defect Report

App Code: A

Subtitle:

CICL, Notification, Investigation, and Restart Request

Dist Statement Required: B

Data Item Number: DI-SAFT-80970 Frequency: ASREQ

Contract Reference: Section E As of Date: N/A

PQM 0 1 0

AQE 0 1 0

REMARKS

If applicable, the CICL shall be submitted no later than 60 days prior to First Article Test (FAT) or initiation of production if FAT is not required. Government shall provide a response within 45 calendar days of initial submission. If further revisions are necessary, the contractor shall have 15 calendar days to provide revisions and the Government shall provide response within 15 calendar days. If applicable, the CICL shall be approved prior to FAT, if FAT is required, or prior to initiation of production. Disposition will be provided by the PCO.

Critical Defect - Notification of critical defect shall be made to the PCO, Contract Specialist, PQM and QAR within 24 hours of the event. Root cause investigation and corrective action and segregated suspect material use, shall be submitted to the Government for approval. Government will respond within 15 calendar days of receipt of original and any required revisions. Disposition will be provided by the PCO.

Restart Request - Contractor shall submit request to restart to the Government for approval. Government will respond within 3 business days of receipt. Disposition will be provided by the PCO.

Submit via email or AMRDEC SAFE: https://safe.amrdec.army.mil/safe/Welcome.aspx Specific email addresses for the distribution list will be provided by the PCO.

A CCCP/CPOA Review Guide is available to assist Contractors on the ARDEC Public Website (http://www.ardec.army.mil/organizations/QESA/) in the application of the CICL requirement. The CCCP/CPOA Review Guide's content, in its entirety, is provided solely for REFERENCE and GUIDANCE PURPOSES ONLY- it is not, nor is it intended to be, contractually binding. Accordingly, the information contained within the CCCP/CPOA Review Guide is expressly not, nor shall it be construed to be, incorporated either directly or by reference into the terms of the CICL requirement itself nor into the terms and conditions of any underlying contract which contains the CICL requirement.

A008

First Article Qualification Test Plan and Procedures

App Code: A

Subtitle: N/A Dist Statement Required: B

Data Item Number: DI-NDTI-81307 Frequency: ASREQ

Contract Reference: Section E As of Date: N/A

PQM 0 1 0

AQE 0 1 0

First Article Test (FAT) Plans shall be submitted 60 days prior to FAT. The Government shall provide response within 30 calendar days of initial submission. If further revisions are necessary, the Contractor shall have 15 calendar days to provide revisions and the Government shall provide response within 15 calendar days. Disposition will be provided by the PCO. Approval of the FAT Plan shall be obtained prior to FAT.

A009

Title: Test/Inspection Report App Code: A

Subtitle:

First Article Test (FAT) Report

Dist Statement Required: B

Data Item Number: DI-NDTI-80809 Frequency: ASREQ

Contract Reference: Section E As of Date: N/A

PQM 0 1 0

AQE 0 1 0

The First Article Test (FAT) Report shall be submitted with Quality Assurance Representative (QAR) findings on DD Form 1222. The FAT Report shall be submitted no later than 30 calendar days after completion of the FAT. The Government requires 30 calendar days for review. Disposition of the FAT report will be provided through the PCO. If further revisions are necessary, the Contractor shall have 15 calendar days to provide revisions and the Government shall provide response within 15 calendar days. PCO approval of the FAT Report shall be obtained prior to start of production.

Submit electronically via email or AMRDEC SAFE https://safe.amrdec.army.mil/safe/Welcome.aspx.

A010

Title: Test/Inspection Report App Code: N/A

Subtitle:

Lot Acceptance Test Report

Dist Statement Required: B

Data Item Number: DI-NDTI-80809 Frequency: ASREQ

Contract Reference: Section E As of Date: N/A

Requiring Office: AMSJM-QAO/P Date of 1st Submission:

30 days after test completion

DD 250: NO Date of Subsequent Submission: ASREQ

Lot Acceptance Test Reports (LATRs) shall be submitted for each lot.

LATRs shall be submitted 30 calendar days after completion of LAT.

LATRs shall be submitted by accessing the Worldwide Ammunition Repository Program (WARP) which is located on the Munitions History Program (MHP) website at https://mhp.redstone.army.mil/.

A011

Failure Summary and Analysis Report

App Code: A

Subtitle: N/A Dist Statement Required: B

Data Item Number: DI-SESS-80255 Frequency: ASREQ

Contract Reference: Section E As of Date: N/A

PQM 0 1 0

AQE 0 1 0

Contractor shall notify the the addressee list in block 14 via email within 24 hours after the occurrence of a failure during acceptance testing, including but not limited to, any failures during First Article Test (FAT)/Lot Acceptance Test (LAT) and any destructive/nondestructive test failures. Formal submittal shall be no later than 10 calendar days after reported failure.

Final report shall be submitted no later than 30 calendar days after determining/conducting root cause/failure analysis.

The Government will provide a response within 15 calendar days of initial submission. If further revisions are necessary, the Contractor shall have 15 calendar days to provide revisions. Disposition will be provided by the Procuring Contracting Officer (PCO).

A012

Acceptance Description Sheets

App Code: A

Subtitle:

Loading Authorizations and Description Sheets

Dist Statement Required: B

Data Item Number: DI-MGMT-81978 Frequency: ASREQ

Contract Reference: Section E As of Date: N/A

DD 250: NO Date of Subsequent Submission: ASREQ

Loading authorizations, Propellant Description Sheets and/or Description Sheets for chemicals and explosives shall be submitted for each lot or batch processed and shall be loaded into Worldwide Ammunition Repository Program (WARP) at the time of acceptance.

Electronic submissions are made by accessing the WARP housing the Description Sheets and Loading Authorizations modules which are located on the Munitions History Program (MHP) website at https://mhp.redstone.army.mil.

This requirement is in addition to the distribution requirements called out in the specification and contract. Note: The first energetic Description Sheet submitted in the WARP system will undergo a Government review.

A013

Title: Test Procedure App Code: A

Subtitle:

Preproduction Procedure - Phosphate Coating (Light)

Dist Statement Required: N/A

Data Item Number: DI-NDTI-80603 Frequency: ONE/R

Contract Reference:

TT-C-490, Type 1, Para 3.2.1, 3.2.2

As of Date: N/A

Requiring Office: RDAR-MEE-W Date of 1st Submission: ASREQ

DD 250: XX Date of Subsequent Submission: N/A

ARDEC Corrosion Team 0 1 0

REMARKS

Submit procedure for approval 60 days prior to First Article Test or production if First Article is not applicable. Allow 14 days for USG approval/disapproval. Contractor shall resubmit with Government revisions within 10 days.

Submit electronically to the PCO and ARDEC Corrosion Team mailbox at usarmy.ria.ardec.mbx.ri-corrosion-team@mail.mil.

Coated panels per paragraph 3.2.2 shall include three with phosphate only, three with phosphate and primer, and three with phosphate, primer and top coat. A DD Form 250 is not required for phosphate coating procedural approval. Contractor format acceptable. Written procedures shall be submitted using a PC compatible format (i.e. PDF, Rich Text Format, or Word File).

A014

Title: Test Procedure App Code: A

Subtitle:

Preproduction Procedure - Phosphate Coating (Heavy)

Dist Statement Required: N/A

Data Item Number: DI-NDTI-80603A Frequency: ONE/R

Contract Reference: MIL-DTL-16232G, Para 3.1 As of Date: N/A

Requiring Office: RDAR-MEE-W Date of 1st Submission: ASREQ

DD 250: XX Date of Subsequent Submission: N/A

ARDEC Corrosion Team 0 1 0

Submit procedure for approval 60 days prior to First Article Test or production if First Article is not applicable. Allow 14 days for USG approval/disapproval. Contractor shall resubmit with Government revisions within 10 days.

Submit electronically to the PCO and ARDEC Corrosion Team mailbox at usarmy.ria.ardec.mbx.ri-corrosion-team@mail.mil.

A DD Form 250 is not required for phosphate coating procedural approval. Contractor format acceptable. Written procedures shall be submitted using a PC compatible format (i.e. PDF, Rich Text Format, or Word File).

A015

Contractual Baseline Report

App Code: N/A

Subtitle: TDP Baseline Report Dist Statement Required: D

Data Item Number: DI-SESS-81856A Frequency: SEMIA

Contract Reference: Section E As of Date: ASREQ

PQM 0 1 0

AQE 0 1 0

Contractor format acceptable. Each report shall be annotated with calendar date for revision control. Submit electronically in PDF prior to First Article Test (FAT) or initiation of production and every six (6) months (Semi-Annually) thereafter.

A016

Title: Request for Variance App Code: N/A

Subtitle: N/A Dist Statement Required: *

Data Item Number: DI-SESS-80640D Frequency: ASREQ

Contract Reference: Section C As of Date: N/A

Requiring Office: RDAR-EIS-PD Date of 1st Submission: ASREQ

ARDEC 0 1 0

Data must be in Government compatible software (i.e., Microsoft Office or PDF).

*Distribution Statement will be assigned and implemented by the DoD configuration control authority. The preferred method for submittal is DD Form 1694 located at http://www.dtic.mil/whs/directives/infomgt/forms/.

Submit electronically to the PCO and ARDEC at usarmy.pica.rdecom-ardec.mbx.ecp-document@mail.mil.

A017

Engineering Change Proposal

App Code: N/A

Subtitle: N/A Dist Statement Required: *

Data Item Number: DI-SESS-80639D Frequency: ASREQ

Contract Reference: Section C As of Date: N/A

*Distribution Statement will be assigned and implemented by the DoD configuration control authority. The preferred method for submittal is DD Form 1692 located at http://www.dtic.mil/whs/directives/infomgt/forms/.

A018

Title: Notice of Revision App Code: N/A

Subtitle: N/A Dist Statement Required: *

Data Item Number: DI-SESS-80642D Frequency: ASREQ

Contract Reference: Section C As of Date: N/A

*Distribution Statement will be assigned and implemented by the DoD configuration control authority. The preferred method for submittal is DD Form 1695 located at http://www.dtic.mil/whs/directives/infomgt/forms/.

A019

Title: OPSEC Plan App Code: A

Subtitle: N/A Dist Statement Required: D

Data Item Number: DI-SESS-80934C Frequency: ONE/R

Contract Reference: Section C As of Date: ASREQ

Requiring Office: AMSJM-FP/G2 Date of 1st Submission: ASREQ

JMC OPSEC 0 1 0

Delete reference “Applying OPSEC to U.S. Government contracts.” Replace with reference “Sample Acquisitions OPSEC Plan.”

OPSEC Plan shall be submitted 30 calendar days after the PCO provides the list of known Critical Information (CI)/Threat Information. Allow 10 calendar days for USG review and approval. Resubmit within 10 calendar days after USG review.

Submit electronically to the PCO and JMC OPSEC at usarmy.ria.jmc.mbx.opsec-fd@mail.mil

File details come from the government source that posted it. Updated .