This performance work statement outlines facility planning requirements at the Lake City Army Ammunition Plant. The contractor shall develop and update facility plans and strategies including capacity planning, strategic planning, and investment planning. The contractor must also provide production base data and respond to industrial capacity inquiries. For government-funded projects, the contractor shall submit new project requirements and cost estimates. Additional requirements include pre-contract support, project reviews, schedule and expenditure reporting, and real property data maintenance. This document specifies planning and analysis services required to support ongoing operations and modernization efforts at the Lake City Army Ammunition Plant facility.

Attachment 0018 - PWS 18 - Facility Plans, Strategies, and Analyses

View the file

Other files

File Type Posted
LCAAP_Draft_RFP_Q&As__1_Rev_1.pdf PDF
LCAAP_Draft_RFP_Q&As__2.pdf PDF
LCAAP_Draft_RFP_Q&As.pdf PDF
W52P1J-17-R-0141_-_DRAFT_Rev_1_-_19JUL18.pdf PDF
Attachment_0037_-_Price_Matrix_-_Summary_Evaluation_Matrix.xlsx XLSX spreadsheet
Attachment_0046_-_Component_Suppliers_Template.xlsx XLSX spreadsheet
Attachment_0011_-_PWS_11_-_Occupational_Health_and_Industrial_Hygiene.pdf PDF
Attachment_0016_-_PWS_16-_On-Site_Government_Personnel_Support.pdf PDF
Attachment_0029_-_Price_Matrix__7.62mm_Family.xlsx XLSX spreadsheet
Exhibit_B_-_Contract_Data_Requirements_List_-_7.62mm.pdf PDF
Exhibit_E_-_Contract_Data_Requirements_List_-_Caliber_.22.pdf PDF
Attachment_0040__-_Price_Matrix_(INDEMNIFIED)_-_5.56mm_Family.xlsx XLSX spreadsheet
Attachment_0017_-_PWS_17_-_Armament_Retooling_and_Manufacturing_Support.pdf PDF
Attachment_0007_-_PWS_7_-_Government_Property_in_Possession_of_the_Contractor.pdf PDF
Attachment_0027_-_Award_Term_Plan.pdf PDF
Attachment_0002_-_PWS_2_-_Safety.pdf PDF
Attachment_0050_-_Example_Order_-_7.62mm.pdf PDF
Attachment_0024_-_DD254_-_Contract_Security_Classification_Specification_(FOR_POSTING).pdf PDF
Attachment_0034_-_FAAT_Price_Matrix_-_.50_Caliber.xlsx XLSX spreadsheet
Attachment_0009_-_PWS_9_-_Contract_Production_and_Delivery_Reporting.pdf PDF
Exhibit_A_-_Contract_Data_Requirements_List_-_5.56mm.pdf PDF
Attachment_0003_-_PWS_3_-_Security_and_Antiterrorism_(FOR_POSTING).pdf PDF
Attachment_0025_-_Hazardous_Material_Classification.pdf PDF
Attachment_0001_-_PWS_1_-_Maintenance.pdf PDF
Exhibit_F_-_Contract_Data_Requirements_List_-_PWS.pdf PDF
Attachment_0012_-_PWS_12_-_Support_of_Onsite_Government_BSO_and_NATO_North_American_Regional_Test_Center.pdf PDF
Attachment_0039_-_Currency_Fluctuation_Worksheet.xlsx XLSX spreadsheet
Attachment_0047_-_Small_Business_Participation_Plan.pdf PDF
Attachment_0030_-_Price_Matrix__.50_Caliber_Family.xlsx XLSX spreadsheet
Attachment_0033_-_FAAT_Price_Matrix_-_7.62mm.XLSX XLSX spreadsheet
Attachment_0010_-_PWS_10_-_Contract_Start-Up_and_Transition.pdf PDF
Attachment_0013_-_PWS_13_-_Mowing_(FOR_POSTING).pdf PDF
Attachment_0020_-_EPR_NDA_-_Corporate.pdf PDF
Attachment_0008_-_PWS_8_-_Ammunition_Materiel_Management.pdf PDF
Attachment_0049_-_Example_Order_-_5.56mm.pdf PDF
Exhibit_C_-_Contract_Data_Requirements_List_-_.50_Caliber.pdf PDF
Attachment_0044_-_Virtual_Techncial_Library_-_On-Site_Library_Contents_(FOR_POSTING).pdf PDF
Attachment_0043_-_Price_Matrix_(INDEMNIFIED)_-_.22_Caliber.xlsx XLSX spreadsheet
Attachment_0028_-_Price_Matrix_-_5.56mm_Family.xlsx XLSX spreadsheet
Attachment_0045_-_SAIC_Non-Disclosure_Agreement.pdf PDF
Attachment_0023_-_Government_Owned_Equipment_(FOR_POSTING).pdf PDF
Attachment_0041_-_Price_Matrix_(INDEMNIFIED)_-_7.62mm_Family.xlsx XLSX spreadsheet
Attachment_0022_-_Sample_OPSEC_Plan.pdf PDF
Attachment_0048_-_Past_Performance_Questionnaire.pdf PDF
W52P1J-17-R-0141_-_DRAFT_29JUN18.pdf PDF
Attachment_0031_-_Price_Matrix_-_.22_Caliber_Family.xlsx XLSX spreadsheet
Attachment_0006_-_PWS_6_-_Fire_and_Emergency_Services.pdf PDF
Attachment_0035_-_FAAT_Price_Matrix_-_.22_Caliber.xlsx XLSX spreadsheet
Attachment_0038_-_EPA_Material_Content_Factors.pdf PDF
Exhibit_D_-_Contract_Data_Requirements_List_-_.30_Caliber.pdf PDF
Show 40 more

Latest 50 of 64 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 0018 June 20, 2018

PWS 18 – FACILITY PLANS, STRATEGIES, AND ANALYSES (DIRECT)

1. OBJECTIVE: To develop and update plans and strategies for overall facility management to include capacity planning, strategic planning, and investment planning.

The results of this planning will provide a tool/roadmap for decision makers regarding facility and investment strategies at LCAAP.

2. BACKGROUND:

2.1. The JM&L LCMC is responsible for performing Industrial Preparedness Planning (IPP) and the planning and execution for Government funded projects.

2.1.1. IPP is performed to document production capabilities and capacities, perform production base analyses, assist in developing acquisition strategies, as well as make proper production base decisions. This PWS is for the Contractor to provide and update LCAAP production base data required for the Government to perform the IPP mission.

2.1.2. The Government funded programs provide investment and modernization for industrial base capabilities. These efforts under this PWS are for the planning and analyses for Government funded projects at LCAAP. Execution of individual projects are direct funded via separate SOWs, or in some instances, support SOWs performed by others.

3. REQUIREMENTS:

3.1. IPP:

3.1.1. The Contractor shall respond to industrial base capacity inquiries on an informal as needed basis. Typically comprehensive requests will be 2-3 times per year. Recurring information requested will include, but is not limited to:

Building/equipment utilization

Building/equipment capacities

Single point failure areas

Identification of bottle necks and time and cost to resolve

Critical skills, critical equipment, critical spare parts

Identify availability and capability of workforce

Critical materials/ingredients

Process support to include software and hardware

Infrastructure support

Data shall be provided in a format which can be imported into software that would allow for geographical presentations compatible with Government software; formats include MS Word, PowerPoint, Excel, Project, and Access DB.

The estimated useful life of critical buildings or equipment including process software or hardware shall be identified and prioritized in need of replacement.

3.2. Government Funded Projects:

3.2.1. The Contractor shall respond within 30 days, or as specified, to the annual Production Base Support (PBS) call letter which requests submission of new project requirements in addition to updating the current project data including, but not limited to, project purpose, benefits, justification, cost estimates, and economic analyses for modernization, layaway, and maintenance of inactive facility projects. In the project purpose and justification, issues such as operational continuity to assure production, environmental impact or issues, cost avoidances or savings, safety, strategic importance and security shall be addressed. The project information shall be provided in a P25 format (Appendix A) and when applicable, DOD Format 1391, and updated quarterly. Projects shall address the need to maintain capacity, utilization, or infrastructure requirements of the industrial base projecting requirements outward by a minimum of five years.

3.2.2. The Contractor shall perform pre-contract actions for projects scheduled for execution. These tasks include, but are not limited to, supporting Determination and Findings, supporting SOW preparation and review, and preparing responses to RFPs; this includes any pre-design activities required by the Contractor to respond to RFPs. Final or full design of the proposed efforts shall be addressed as a proposed project on a case-by-case basis.

3.2.3. The Contractor shall support/host periodic on-site reviews at the request of PEO AMMO, LCAAP Government Staff and/or JMC; stated reviews may range from a program wide review or project specific reviews (approximately 6 – 8 times per year).

3.2.4. The Contractor shall provide a project schedule in an integrated master schedule (IMS) IAW CDRL A123. Consistent with the Contractor’s accounting system, the Contractor shall electronically provide monthly reports detailing expenditures incurred on cost reimbursable funded actions IAW CDRL A124.

3.2.5. The Contractor shall submit ROMs for all proposed project submissions.

ROMs will include supporting data/rationale for the basis of estimate (BOE) and include a cost break-out to show the material and labor costs. The BOE shall include the assumed overhead, management reserve and fee percent used in the ROM. ROMs will be submitted in an electronic format compatible with MS Office.

3.2.6. The Contractor shall submit data to support a Project Planning Document.

(A125) The Project Planning Document will include, but are not limited to following:

Introduction:

- Description of facilities including current condition and remaining useful life;

- Production capabilities; and

- Single point failure areas.

Production Capacity by Operation:

- Include process/equipment processing rate;

- Operational availability;

- Number of machines; and

- Shift rate assumptions, via 3-8-5 or equivalent.

Project Requirements:

- Current available technology and advances;

- Planning process methodology;

- Prioritization and tentative timelines;

- Funding requirements; and

- Project listing and summary information.

Detailed Project Data:

- Project executive summaries;

- Purpose;

- Justifications/benefits;

- Impact if not implemented;

- Cost data: project cost estimates, return on investment, savings; and

- Supporting data: impacts to operational continuity, safety, environmental, and energy consumption, etc.

3.3. Base Operations:

3.3.1. The Contractor shall comply with all base operations reporting requirements. These requirements include, but are not limited to:

3.3.1.1. Operating Contractor shall input and maintain Installations Status Report (ISR) data in a format compatible with the Army’s automated database (currently known as ISR- Infrastructure (ISR-I) and ISR – Mission Capacity (ISR – MC)). Contractor shall comply with Assistant Chief of Staff for Installation Management (ACSIM) annual FY Implementing Instructions as posted on ISR Web pages, https://isr.hqda.pentagon.mil) guidance and reporting requirements as supplemented by HQ AMC Program Manager and the Government staff.

The ISR-I data shall be maintained in a manner to support electronic data extractions from ISR-I on annual, semi-annual, quarterly and special need basis, by JMC, AMC, DA and DoD IAW statutory and regulatory requirements.

The Contractor shall be responsible for performing the ISR-I/ISR-MC assessments and ratings of all facilities and rating criteria IAW AR 210-14 and FY Implementing Instructions. Rating for ISR-I shall include physically assessing asset as described yearly in the ISR-I Implementation Standards. At a minimum 25% of the yearly requirements for assessments shall be completed per quarter. Rating for ISR-MC shall include completing all questions and questionnaires, yearly, for ISR-MC as described yearly in the ISR-I Implementation Standards. Ratings shall be completed on the compressed AMC schedule, which will be provided by the PCO/ACO and allow for Government review.

Contractor shall provide all efforts up to the point of validation roles and validation with ISR.

3.3.1.2. Validate and update the General Fund Enterprise Business Systems (GFEBS)

3.3.1.3. The Real Property Planning and Analysis System (RPLANS) should be analyzed quarterly to ascertain if the system reflects adequate allowances and requirements for the installation. A report shall be generated for the real property accountability officer (RPAO) which describes each allowance and requirements as well as proposed allowances. At the direction of the RPAO, edits to requirements shall be IAW WEBRPLANS format and prepared and submitted through the system.

APPENDIX A

PRODUCTION SUPPORT AND FACILITIES PROJECTS

Exhibit P-25 Feeder

Production Base Support (PBS) Project Submission

Provision of Industrial Facilities (PIF) & Layaway of Industrial Facilities

(LIF)

DATE: DD MMM YYYY

1. Project Number/Type: 5XXXXXX (PINT/ENV/SAF/FIN)

2. Fund Code: PAA, 4210 Category (PIF or LIF): XXX

3. Project Title:

4. Facility:

a. Name & Location: XXXXX AAP City, State

b. Contractor: XXXXXXXXXXXX

5. Project Narrative:

a. Objective.

b. Need.

c. Requirement.

d. Background.

6. Project Priorities (double-click on below chart to populate)

Weights: 20% 15% 30% 15% 20%

Evaluation Score 1, 3 , 9 Probability Score 1, 3, 9 Score = Weight x Eval x Probability Raw Score

C o s t

E n v i r o n m e n t a l

O p e r a t i o n a l

C o n t i n u i y

R e t u r

I n v e s t m e

S f e i t i c a

T

F v i o r n m e n t e r a t i o n a l

C o n t i n u i t u

I n v e s t m e f e v i r o n m e n t e r a t i o n a l

C o n t i n u i t u

I n v e s t m e f e c o

0.00 0.00 0.00 0.00 0.00 0.00

7. Project Investment Costs:

INVESTMENT COSTS FYXX CONSTANT $M

Acquisition

Transportation *

Installation *

Testing *

Construction

Training

Other

G&A

Fee

Total Project Cost (constant $M):

*Included in acquisition cost.

8. Project Schedule:

ACTIVITY DURATION (# months)

Design

Construction

Equipment Procurement

Installation

Prove-out

9. Economic Analysis: