This document is a Demolition Specification (Section 02 41 00) for the Rio Puerto Nuevo Project Main Channel Design Supplemental Contract 3 in San Juan, Puerto Rico. The specification provides comprehensive instructions for demolition activities, including the removal of existing structures, utilities, equipment, and materials with specific requirements for handling, recycling, and disposal.
Key demolition requirements include completely removing existing bridge components and channel lining, demolishing concrete piles to 2 feet below the final channel invert, and systematically dismantling structures from top to bottom. The contractor must coordinate closely with LUMA (the local utility) for equipment inventory, recycling, and asset recovery. Special attention is given to environmental compliance, such as proper handling of ozone-depleting substances, transformer recycling, and waste management. The specification also identifies specific items for reuse, including a kiosk, garbage facility, and gondola cables, with detailed instructions for their careful removal and preservation.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rio Puerto Nuevo Project Main Channel Design Supplemental Contract 3 San Juan, Puerto Rico
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 REFERENCES
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
1.2.1.2 Demolition Plan
1.2.2 Demolition Plan
1.2.3 General Requirements
1.3 ITEMS TO REMAIN IN PLACE
1.3.1 Gondola Cables
1.3.2 Existing Construction Limits and Protection
1.3.3 Trees
1.3.4 Utility Service
1.3.5 Facilities
1.4 BURNING
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.6.1 Dust and Debris Control
1.7 PROTECTION
1.7.1 Traffic Control Signs
1.7.2 Protection of Personnel
1.8 RELOCATIONS
1.9 EXISTING CONDITIONS
1.9.1 LUMA EQUIPMENT INVENTORY
PART 2 PRODUCTS
2.1 FILL MATERIAL
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
3.1.2.2 Disconnecting Existing Utilities
3.1.3 Chain Link Fencing
3.1.4 Paving and Slabs
3.1.5 Concrete
3.1.6 Structural Steel
3.1.7 Miscellaneous Metal
3.1.8 Carpentry
3.1.9 Acoustic Ceiling Tile
3.1.10 Patching
3.1.11 Air Conditioning Equipment
SECTION 02 41 00 Page 1 W51DQV25RA002 Amendment 0003
3.1.12 Cylinders and Canisters
3.1.13 Locksets on Swinging Doors
3.1.14 Mechanical Equipment and Fixtures
3.1.14.1 Preparation for Storage
3.1.14.2 Piping
3.1.14.3 Ducts
3.1.14.4 Fixtures, Motors and Machines
3.1.15 Electrical Equipment and Fixtures
3.1.15.1 Fixtures
3.1.15.2 Electrical Devices
3.1.15.3 Wiring Ducts or Troughs
3.1.15.4 Conduit and Miscellaneous Items
3.2 CONCURRENT EARTH-MOVING OPERATIONS
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
3.3.1.1 MATERIALS OWNED BY LUMA
3.3.1.2 EQUIPMENT DISASSEMBLY
3.3.1.3 EQUIPMENT SEGREGATION
3.3.1.4 INVENTORY MAINTENANCE
3.3.1.5 RECYCLABLE MATERIALS
3.3.1.6 TRANSFORMER RECYCLING
3.3.1.7 CONCRETE OR METAL POLES
3.3.1.8 COORDINATION
3.3.2 Reuse of Materials and Equipment
3.3.3 Disposal of Ozone Depleting Substance (ODS)
3.3.3.1 Special Instructions
3.3.3.2 Fire Suppression Containers
3.3.4 Transportation Guidance
3.3.5 Non-Recyclable Material
3.4 CLEANUP
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
3.5.2 Removal from Government Property
ATTACHMENTS:
Kiosk
Garbage Facility
Gondola Cables
-- End of Section Table of Contents --
SECTION 02 41 00 Page 2
SECTION 02 41 00
DEMOLITION
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AIR-CONDITIONING, HEATING AND REFRIGERATION INSTITUTE (AHRI)
AHRI Guideline K (2009) Guideline for Containers for Recovered Non-Flammable Fluorocarbon Refrigerants
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.6 (2006) Safety & Health Program Requirements for Demolition Operations - American National Standard for Construction and Demolition Operations
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety and Occupational Health (SOH) Requirements
U.S. DEFENSE LOGISTICS AGENCY (DLA)
DLA 4145.25 (Jun 2000; Reaffirmed Oct 2010) Storage and Handling of Liquefied and Gaseous Compressed Gases and Their Full and Empty Cylinders http://www.aviation.dla.mil/UserWeb/aviationengineering/HazInfo/
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures
MIL-STD-129 (2014; Rev R) Military Marking for Shipment and Storage
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
40 CFR 61 National Emission Standards for Hazardous Air Pollutants
40 CFR 82 Protection of Stratospheric Ozone
49 CFR 173.301 Shipment of Compressed Gases in Cylinders and Spherical Pressure Vessels
SECTION 02 41 00 Page 3
1.2 PROJECT DESCRIPTION
1.2.1 Definitions
1.2.1.1 Demolition
Demolition is the process of wrecking or taking out any load-supporting structural member of a facility together with any related handling and disposal operations.
1.2.1.2 Demolition Plan
Demolition Plan is the planned steps and processes for managing demolition activities and identifying the required sequencing activities and disposal mechanisms.
1.2.2 Demolition Plan
Prepare a Demolition Plan and submit proposed demolition, and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials, coordination with other work in progress, a disconnection schedule of utility services, a detailed description of methods and equipment to be used for each operation and of the sequence of operations. Provide details for the pickup of concrete or steel poles, transformers, and underground and overhead components according to LUMA's Assets Recovery SOP. Coordinate with Waste Management Plan in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Provide procedures for safe conduct of the work in accordance with EM 385-1-1 . Plan shall be approved by Contracting Officer prior to work beginning.
1.2.3 General Requirements
Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. The work includes demolition and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1 , Section 23, Demolition, and other applicable Sections.
1.3 ITEMS TO REMAIN IN PLACE
Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items at no cost to the Government. Coordinate the work of this section with all other work indicated. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Increase structural supports or add new supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract. Do not overload structural elements. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the Contracting Officer prior to performing such work.
SECTION 02 41 00 Page 4
1.3.1 Gondola Cables
Provide a plan for temporarily displacing or removing, storing, and reinstalling the existing gondola cables. Include documentation of coordination with the Municipality of San Juan. Damaged cables or equipment shall be replaced at no cost to the Government.
1.3.2 Existing Construction Limits and Protection
Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction and for staging areas as indicated on the Drawings. Provide temporary shoring and bracing for support of building components to prevent settlement or other movement.
Provide protective measures to control accumulation and migration of dust and dirt in all work areas. Remove dust, dirt, and debris from work areas daily.
1.3.3 Trees
Protect trees within the project site which might be damaged during demolition or deconstruction, and which are indicated to be left in place, by a 6 foot high construction safety fence. Erect and secure fence a minimum of 5 feet from the trunk of individual trees or follow the outer perimeter of branches or clumps of trees. Replace any tree designated to remain that is damaged during the work under this contract with like-kind or as approved by the Contracting Officer.
1.3.4 Utility Service
Maintain existing utilities indicated to stay in service and protect against damage during demolition and deconstruction operations. Prior to start of work, utilities serving each area of alteration or removal will be shut off by the Government and disconnected and sealed by the Contractor .
1.3.5 Facilities
Protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities. Floors, roofs, walls, columns, pilasters, and other structural components that are designed and constructed to stand without lateral support or shoring, and are determined to be in stable condition, must remain standing without additional bracing, shoring, or lateral support until demolished or deconstructed, unless approved otherwise by the Contracting Officer.
Ensure that no elements determined to be unstable are left unsupported and place and secure bracing, shoring, or lateral supports as may be required as a result of any cutting, removal, deconstruction, or demolition work performed under this contract.
1.4 BURNING
The use of burning at the project site for the disposal of refuse and debris will not be permitted.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
SECTION 02 41 00 Page 5 submittals not having a "G" designation are for information only.
Designation RO stands for Resident Office and designation DO stands for District Office. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Demolition Plan ; G, RO
Existing Conditions
Gondola Cables ; G, RO
Luma Equipment Inventory ; G, RO
SD-07 Certificates
Notification ; G, RO
SD-11 Closeout Submittals
Receipts
1.6 QUALITY ASSURANCE
Submit timely notification of demolition projects to Federal, Commonwealth, regional, and local authorities in accordance with 40 CFR 61 , Subpart M. Notify the local air pollution control district/agency and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61 , Subpart M. Comply with federal, commonwealth, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSP A10.6 . Comply with the Environmental Protection Agency requirements specified. Use of explosives will not be permitted.
1.6.1 Dust and Debris Control
Prevent the spread of dust and debris and avoid the creation of a nuisance in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, or pollution.
1.7 PROTECTION
1.7.1 Traffic Control Signs
a. Where pedestrian and driver safety is endangered in the area of removal work, use traffic barricades with flashing lights. Notify the Contracting Officer prior to beginning such work.
1.7.2 Protection of Personnel
Before, during and after the demolition work continuously evaluate the condition of the structure being demolished and take immediate action to protect all personnel working in and around the project site. No area, section, or component of floors, roofs, walls, columns, pilasters, or other structural element will be allowed to be left standing without sufficient bracing, shoring, or lateral support to prevent collapse or
SECTION 02 41 00 Page 6 failure while workmen remove debris or perform other work in the immediate area.
1.8 RELOCATIONS
Perform the removal and reinstallation of relocated items as indicated with workmen skilled in the trades involved. Repair or replace items to be relocated which are damaged by the Contractor at no cost to the Government with new undamaged items as approved by the Contracting Officer.
1.9 EXISTING CONDITIONS
Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work. Record existing conditions in the presence of the Contracting Officer showing the condition of structures and other facilities adjacent to areas of alteration or removal. Digital photographs reproduced at a size of 4 inches x 6 inches and a minimum of 300 dpi resolution will be acceptable as a record of existing conditions. Include in the record the elevation of the top of foundation walls, finish floor elevations, possible conflicting electrical conduits, plumbing lines, alarms systems, the location and extent of existing cracks and other damage and description of surface conditions that exist prior to before starting work. It is the Contractor's responsibility to verify and document all required outages which will be required during the course of work, and to note these outages on the record document. Submit site condition survey results.
1.9.1 LUMA EQUIPMENT INVENTORY
Submit an inventory of material or equipment owned by LUMA within the project limits which is to be demolished or salvaged. Provide equipment type, material information, quantity, and location of all equipment within the inventory. Notify LUMA and the Contracting Officer a minimum of 15 calendar days prior to the demolition or deconstruction of materials or equipment owned by LUMA.
PART 2 PRODUCTS
2.1 FILL MATERIAL
a. Comply with excavating, backfilling, and compacting procedures for soils used as backfill material to fill basements, voids, depressions or excavations resulting from demolition or deconstruction of structures.
b. Fill material shall conform to Section 31 00 00 EARTHWORK.
PART 3 EXECUTION
3.1 EXISTING FACILITIES TO BE REMOVED
3.1.1 Structures
a. Existing bridge components including but not limited to, entire structure and channel lining shall be completely removed. Existing concrete piles shall be demolished to a minimum of 2 feet below the final channel invert.
SECTION 02 41 00 Page 7
b. Remove existing structures indicated to be removed to the ground surface, including supporting slabs. Interior walls, other than retaining walls and partitions, shall be removed to 2 feet below grade. Break up basement slabs to permit drainage. Remove sidewalks, curbs, gutters and street light bases as indicated on the Drawings.
c. Demolish structures in a systematic manner from the top of the structure to the ground. Complete demolition work above each tier or floor before the supporting members on the lower level are disturbed.
Demolish concrete and masonry walls in small sections. Remove structural framing members and lower to ground by means of derricks, platforms hoists, or other suitable methods as approved by the Contracting Officer.
d. Locate demolition and deconstruction equipment throughout the structure and remove materials so as to not impose excessive loads to supporting walls, floors, or framing.
e. Building, or the remaining portions thereof, not exceeding 80 feet in height may be demolished by the mechanical method of demolition.
3.1.2 Utilities and Related Equipment
3.1.2.1 General Requirements
Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by the Contracting Officer. Do not interrupt existing utilities serving facilities occupied and used by the Government except when approved in writing and then only after temporary utility services have been approved and provided. Do not begin demolition or deconstruction work until all utility disconnections have been made.
Shut off and cap utilities for future use, as indicated.
3.1.2.2 Disconnecting Existing Utilities
Remove existing utilities , as indicated and terminate in a manner conforming to the nationally recognized code covering the specific utility and approved by the Contracting Officer. When utility lines are encountered but are not indicated on the drawings, notify the Contracting Officer prior to further work in that area. Remove meters and related equipment and deliver to a location in accordance with instructions of the Contracting Officer.
3.1.3 Chain Link Fencing
Remove chain link fencing, gates and other related items scheduled for removal and transport to designated areas. Remove gates as whole units.
Cut chain link fabric to 25 foot lengths and store in rolls off the ground.
3.1.4 Paving and Slabs
Remove concrete and asphaltic concrete paving and slabs including aggregate base as indicated to a depth of 12 inches below existing adjacent new finish grade. Provide neat sawcuts at limits of pavement removal as indicated. Pavement and slabs designated to be recycled and utilized in this project shall be moved, ground and stored as approved by the Contracting Officer. Pavement and slabs not to be used in this project shall be removed from the Installation at Contractor's expense.
SECTION 02 41 00 Page 8
3.1.5 Concrete
Saw concrete along straight lines to a depth of a minimum 2 inch . Make each cut in walls perpendicular to the face and in alignment with the cut in the opposite face. Break out the remainder of the concrete provided that the broken area is concealed in the finished work, and the remaining concrete is sound. At locations where the broken face cannot be concealed, grind smooth or saw cut entirely through the concrete. Removed concrete debris, which meets project material requirements, designated to be recycled and utilized in this project shall be moved, ground and stored as approved by the Contracting Officer.
3.1.6 Structural Steel
Dismantle structural steel at field connections and in a manner that will prevent bending or damage. Flame-cutting torches are permitted when other methods of dismantling are not practical. Transport steel joists and girders as whole units and not dismantled. Transport structural steel shapes to a designated area as directed by the Contracting Officer, stacked according to size, type of member and length, and stored off the ground, protected from the weather.
3.1.7 Miscellaneous Metal
Recycle scrap metal as part of demolition and deconstruction operations.
Provide separate containers to collect scrap metal and transport to a scrap metal collection or recycling facility, in accordance with the Waste Management Plan.
3.1.8 Carpentry
Remove windows, doors, frames, and cabinets, and similar items as whole units, complete with trim and accessories. Do not remove hardware attached to units, except for door closers. Brace the open end of door frames to prevent damage.
3.1.9 Acoustic Ceiling Tile
Remove, neatly stack, and recycle acoustic ceiling tiles. Recycling may be available with manufacturer. Otherwise, priority shall be given to a local recycling organization. Recycling is not required if the tiles contain or may have been exposed to asbestos material.
3.1.10 Patching
Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish. Patching shall be as specified and indicated, and shall include:
a. Concrete and Masonry: Completely fill holes and depressions, left as a result of removals in existing masonry walls to remain, with an approved masonry patching material, applied in accordance with the
SECTION 02 41 00 Page 9 manufacturer's printed instructions.
b. Where existing partitions have been removed leaving damaged or missing resilient tile flooring, patch to match the existing floor tile.
c. Patch acoustic lay-in ceiling where partitions have been removed. The transition between the different ceiling heights shall be effected by continuing the higher ceiling level over to the first runner on the lower ceiling and closing the vertical opening with a painted sheet metal strip.
3.1.11 Air Conditioning Equipment
Remove air conditioning, refrigeration, and other equipment containing refrigerants without releasing chlorofluorocarbon refrigerants to the atmosphere in accordance with the Clean Air Act Amendment of 1990.
3.1.12 Cylinders and Canisters
Remove all fire suppression system cylinders and canisters and dispose of in accordance with the paragraph entitled "Disposal of Ozone Depleting Substance (ODS)."
3.1.13 Locksets on Swinging Doors
Remove all locksets from all swinging doors indicated to be removed and disposed of. Deliver the locksets and related items to a designated location for receipt by the Contracting Officer after removal.
3.1.14 Mechanical Equipment and Fixtures
Disconnect mechanical hardware at the nearest connection to existing services to remain, unless otherwise noted. Disconnect mechanical equipment and fixtures at fittings. Remove service valves attached to the unit. Do not remove equipment until approved. Do not offer low-efficiency equipment for reuse.
3.1.14.1 Preparation for Storage
Remove water, dirt, dust, and foreign matter from units; tanks, piping and fixtures shall be drained; interiors, if previously used to store flammable, explosive, or other dangerous liquids, shall be steam cleaned.
Seal openings with caps, plates, or plugs. Secure motors attached by flexible connections to the unit. Change lubricating systems with the proper oil or grease.
3.1.14.2 Piping
Disconnect piping at unions, flanges and valves, and fittings as required to reduce the pipe into straight lengths for practical storage. If the piping that remains can become pressurized due to upstream valve failure, end caps, blind flanges, or other types of plugs or fittings with a pressure gage and bleed valve shall be attached to the open end of the pipe to ensure positive leak control. Carefully dismantle piping that previously contained gas, gasoline, oil, or other dangerous fluids, with precautions taken to prevent injury to persons and property. Store piping outdoors until all fumes and residues are removed. Box prefabricated supports, hangers, plates, valves, and specialty items according to size and type. Wrap sprinkler heads individually in plastic bags before
SECTION 02 41 00 Page 10 boxing. Classify piping as scrap metal where applicable.
3.1.14.3 Ducts
Classify removed duct work as scrap metal.
3.1.14.4 Fixtures, Motors and Machines
Remove fixtures, motors and machines associated with plumbing, heating, air conditioning, refrigeration, and other mechanical system installations. Box and store auxiliary units and accessories with the main motor and machines. Classify broken, damaged, or otherwise unserviceable units and not caused to be broken, damaged, or otherwise unserviceable as debris to be disposed of by the Contractor.
3.1.15 Electrical Equipment and Fixtures
Remove motors, motor controllers, and operating and control equipment that are attached to the driven equipment. Remove wiring systems and components. Box loose items and tag for identification. Disconnect primary, secondary, control, communication, and signal circuits at the point of attachment to their distribution system.
3.1.15.1 Fixtures
Remove electrical fixtures. Remove unprotected glassware from the fixture separately. Remove incandescent, mercury-vapor, and fluorescent lamps and fluorescent ballasts manufactured prior to 1978, boxed and tagged for identification, and protected from breakage.
3.1.15.2 Electrical Devices
Remove witches, switchgear, transformers, conductors including wire and nonmetallic sheathed and flexible armored cable, regulators, meters, instruments, plates, circuit breakers, panelboards, outlet boxes, and similar items. Box and tag these items for identification according to type and size.
3.1.15.3 Wiring Ducts or Troughs
Remove wiring ducts or troughs. Dismantle plug-in ducts and wiring troughs into unit lengths. Remove plug-in or disconnecting devices from the busway and store separately.
3.1.15.4 Conduit and Miscellaneous Items
Remove conduit except where embedded in concrete or masonry. Consider corroded, bent, or damaged conduit as scrap metal. Sort straight and undamaged lengths of conduit according to size and type. Classify supports, knobs, tubes, cleats, and straps as debris to be removed and disposed.
3.2 CONCURRENT EARTH-MOVING OPERATIONS
Do not begin excavation, filling, and other earth-moving operations that are sequential to demolition or deconstruction work in areas occupied by structures to be demolished or deconstructed until all demolition and deconstruction in the area has been completed and debris removed. Fill holes, open basements and other hazardous openings.
SECTION 02 41 00 Page 11
3.3 DISPOSITION OF MATERIAL
3.3.1 Title to Materials
All materials and equipment removed, except as noted in the paragraph MATERIALS OWNED BY LUMA, shall become the property of the Contractor and shall be removed from Government property. Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin demolition and deconstruction. The Government will not be responsible for the condition or loss of, or damage to, such property after contract award. Showing for sale or selling materials and equipment on site is prohibited.
3.3.1.1 MATERIALS OWNED BY LUMA
All demolished or salvaged materials and equipment owned by LUMA shall be stockpiled onsite for material disposition to be done by LUMA. LUMA may elect to salvage material for reuse or recycling and will remain the property of LUMA. Removal of this specific material and equipment from the site will be completed by LUMA. Any remaining material and equipment shall become the property of the Contractor and shall be removed from Government property. For bidding purposes, assume all material will be disposed of by the Contractor. Refer to Section 02 42 00 DECONSTRUCTION OF ELECTRIC TRANSMISSION AND DISTRIBUTION UTILITY for additional information related to demolished or salvaged materials and equipment owned by LUMA.
3.3.1.2 EQUIPMENT DISASSEMBLY
Completely disassemble all poles including, but not limited to, cross arms, bolts, fuse cutouts, insulators, transformers, overhead lines, and underground components.
3.3.1.3 EQUIPMENT SEGREGATION
Segregate equipment for disposal, recycling, or reuse categorizing them by material type, such as aluminum, metal, concrete, wood, and differentiate between overhead and underground components. As the wood materials are neither recyclablable nor reusable, dispose of them.
3.3.1.4 INVENTORY MAINTENANCE
Maintain an inventory of all removed equipment including, but not limited to, poles, transformers, conductors, and underground components.
3.3.1.5 RECYCLABLE MATERIALS
Designate a sorting area for recyclable materials such as aluminum, copper, and metals.
Process recyclable materials through LUMA's recycling program.
LUMA will provide a dumpster for recyclable materials and equipment collection once all materials are segregated by material type and ready for collection. Coordinate with LUMA's assets recovery office for the dumpster.
SECTION 02 41 00 Page 12
3.3.1.6 TRANSFORMER RECYCLING
Place transformers inside a special transformer containment bag and a small containment area for recycling. Transformer bags should safely contain both non-leaking and leaking transformers for transport. The contractor is responsible of acquiring the special transformer containment bags. LUMA will not provide special transformer containment bags.
3.3.1.7 CONCRETE OR METAL POLES
Coordinate with LUMA for the pickup of concrete or metal poles.
3.3.1.8 COORDINATION
a. Coordinate with LUMA for the pickup of recyclable materials and equipment.
LUMA Asset Recovery
Contact: Giovanni Taffanelli, Supervisor Email: AR@lumapr.com Phone: (787)-349-6931
b. Ensure that all materials are disassembled and ready for pickup before LUMA's scheduled collection.
c. Comply with LUMA's Assets Recovery SOP for recycling transformers and coordinating pickup.
3.3.2 Reuse of Materials and Equipment
Remove and store materials and equipment listed in the Demolition Plan to be reused or relocated to prevent damage, and reinstall as the work progresses. Coordinate the re-use of materials and equipment with the re-use requirements in accordance with Section 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. Capture re-use of materials in the diversion calculations for the project. Items designated for reuse include:
1. Kiosk - Sta. 110+90, Right Channel Bank (Photo Attached)
2. Garbage Facility - Sta. 113+75, Left Channel Bank (Photo Attached)
3. Gondola Cables - Sta. 114+00, Crossing Channel (Photo Attached)
3.3.3 Disposal of Ozone Depleting Substance (ODS)
Class I and Class II ODS are defined in Section, 602(a) and (b), of The Clean Air Act. Prevent discharge of Class I and Class II ODS to the atmosphere. Place recovered ODS in cylinders meeting AHRI Guideline K suitable for the type ODS (filled to no more than 80 percent capacity) and provide appropriate labeling. Recovered ODS shall be removed from Government property and disposed of in accordance with 40 CFR 82 .
Products, equipment and appliances containing ODS in a sealed, self-contained system (e.g. residential refrigerators and window air conditioners) shall be disposed of in accordance with 40 CFR 82 . Submit Receipts or bills of lading, as specified. Submit a shipping receipt or bill of lading for all containers of ozone depleting substance (ODS) shipped to the Defense Depot, Richmond, Virginia.
SECTION 02 41 00 Page 13
3.3.3.1 Special Instructions
No more than one type of ODS is permitted in each container. A warning/hazardous label shall be applied to the containers in accordance with Department of Transportation regulations. All cylinders including but not limited to fire extinguishers, spheres, or canisters containing an ODS shall have a tag with the following information:
a. Activity name and unit identification code
b. Activity point of contact and phone number
c. Type of ODS and pounds of ODS contained
d. Date of shipment
e. National stock number (for information, call (804) 279-4525).
3.3.3.2 Fire Suppression Containers
Deactivate fire suppression system cylinders and canisters with electrical charges or initiators prior to shipment. Also, safety caps must be used to cover exposed actuation mechanisms and discharge ports on these special cylinders.
3.3.4 Transportation Guidance
Ship all ODS containers in accordance with MIL-STD-129 , DLA 4145.25 (also referenced one of the following: Army Regulation 700-68, Naval Supply Instruction 4440.128C, Marine Corps Order 10330.2C, and Air Force Regulation 67-12), 49 CFR 173.301 , and DOD 4000.25-1-M .
3.3.5 Non-Recyclable Material
Dispose of non-recyclable combustible material off the site.
3.4 CLEANUP
Remove debris and rubbish from basement and similar excavations. Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.
3.5 DISPOSAL OF REMOVED MATERIALS
3.5.1 Regulation of Removed Materials
Dispose of debris, rubbish, scrap, and other materials resulting from removal operations with all applicable federal, commonwealth and local regulations as contractually specified in the Waste Management Plan in Section 01 74 19 .
3.5.2 Removal from Government Property
Transport waste materials removed from demolished structures, except waste soil, from Government property for legal disposal. Dispose of waste soil and excess excavated material at approved disposal sites or approved landfill.
-- End of Section --
SECTION 02 41 00 Page 14
SECTION 02 41 00 Page 15
| 02 41 00 - DEMOLITION |
| 02 41 00 - DEMOLITION |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 PROJECT DESCRIPTION |
| 1.2.1 Definitions |
| 1.2.1.1 Demolition |
| 1.2.1.2 Demolition Plan |
| 1.2.2 Demolition Plan |
| 1.2.3 General Requirements |
| 1.3 ITEMS TO REMAIN IN PLACE |
| 1.3.1 Gondola Cables |
| 1.3.2 Existing Construction Limits and Protection |
| 1.3.3 Trees |
| 1.3.4 Utility Service |
| 1.3.5 Facilities |
| 1.4 BURNING |
| 1.5 SUBMITTALS |
| 1.6 QUALITY ASSURANCE |
| 1.6.1 Dust and Debris Control |
| 1.7 PROTECTION |
| 1.7.1 Traffic Control Signs |
| 1.7.2 Protection of Personnel |
| 1.8 RELOCATIONS |
| 1.9 EXISTING CONDITIONS |
| 1.9.1 LUMA EQUIPMENT INVENTORY |
| PART 2 PRODUCTS |
| 2.1 FILL MATERIAL |
| PART 3 EXECUTION |
| 3.1 EXISTING FACILITIES TO BE REMOVED |
| 3.1.1 Structures |
| 3.1.2 Utilities and Related Equipment |
| 3.1.2.1 General Requirements |
| 3.1.2.2 Disconnecting Existing Utilities |
| 3.1.3 Chain Link Fencing |
| 3.1.4 Paving and Slabs |
| 3.1.5 Concrete |
| 3.1.6 Structural Steel |
| 3.1.7 Miscellaneous Metal |
| 3.1.8 Carpentry |
| 3.1.9 Acoustic Ceiling Tile |
| 3.1.10 Patching |
| 3.1.11 Air Conditioning Equipment |
| 3.1.12 Cylinders and Canisters |
| 3.1.13 Locksets on Swinging Doors |
| 3.1.14 Mechanical Equipment and Fixtures |
| 3.1.14.1 Preparation for Storage |
| 3.1.14.2 Piping |
| 3.1.14.3 Ducts |
| 3.1.14.4 Fixtures, Motors and Machines |
| 3.1.15 Electrical Equipment and Fixtures |
| 3.1.15.1 Fixtures |
| 3.1.15.2 Electrical Devices |
| 3.1.15.3 Wiring Ducts or Troughs |
| 3.1.15.4 Conduit and Miscellaneous Items |
| 3.2 CONCURRENT EARTH-MOVING OPERATIONS |
| 3.3 DISPOSITION OF MATERIAL |
| 3.3.1 Title to Materials |
| 3.3.1.1 MATERIALS OWNED BY LUMA |
| 3.3.1.2 EQUIPMENT DISASSEMBLY |
| 3.3.1.3 EQUIPMENT SEGREGATION |
| 3.3.1.4 INVENTORY MAINTENANCE |
| 3.3.1.5 RECYCLABLE MATERIALS |
| 3.3.1.6 TRANSFORMER RECYCLING |
| 3.3.1.7 CONCRETE OR METAL POLES |
| 3.3.1.8 COORDINATION |
| 3.3.2 Reuse of Materials and Equipment |
| 3.3.3 Disposal of Ozone Depleting Substance ODS |
| 3.3.3.1 Special Instructions |
| 3.3.3.2 Fire Suppression Containers |
| 3.3.4 Transportation Guidance |
| 3.3.5 Non-Recyclable Material |
| 3.4 CLEANUP |
| 3.5 DISPOSAL OF REMOVED MATERIALS |
| 3.5.1 Regulation of Removed Materials |
| 3.5.2 Removal from Government Property |