Site-Visit Documentation_Attendance List_W51DQV25RA002.pdf
PDF 13 MB Posted
- Solicitation number
- W51DQV25RA002
- Issued by
-
Department of the Army
About this file
This document is a pre-bid conference presentation for the Rio Puerto Nuevo Flood and Risk Management (RPN FRM) Project, Supplemental Contract 3 for Channel Bottom and Wall Improvements in San Juan, Puerto Rico. The U.S. Army Corps of Engineers is seeking a contractor for a complex flood management infrastructure project with an estimated construction magnitude over $500 million. The contract is a firm-fixed-price design-bid-build construction contract with a 2,190-calendar-day performance period, and liquidated damages of $37,500 per day of delay.
Key project specifics include approximately 1,700 six-foot diameter concrete drill shaft piles (100 feet deep), channel wall improvements spanning two miles, sewer siphon installation, utility bridge construction with a 48-inch watermain, power line relocation, and stormwater penetration work. The solicitation (W51DQV25RA002) will be available on SAM.gov on May 19, 2025, with bids due by July 3, 2025, at 10:00 am AST. Bidders must submit electronically via the Procurement Integrated Enterprise Environment (PIEE), provide a bid guarantee of 20% of bid price or $3,000,000, and be prepared to submit payment and performance bonds within 10 days of contract award.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RIO PUERTO NUEVO FLOOD AND RISK MANAGEMENT
(RPN FRM) PROJECT
SUPPLEMENTAL CONTRACT 3
CHANNEL BOTTOM & WALL IMPROVEMENTS
PRE-BID CONFERENCE
CARIBBEAN DISTRICT
12 JUNE 2025
AGENDA
CONTRACTING
OVERVIEW
PROJECT OVERVIEW SITE VISIT
PROJECT OVERVIEW
Jose D Bilbao, P.E., PMP Chief, Program Manager Rio Puerto Nuevo Branch
Stephen M. Dupries, P.E.
Program Engineering Technical Lead
44 RIO PUERTO NUEVO FLOOD RISK MANAGEMENT PROJECT
OVERVIEW
5A
5B
6B 7B
BC
LC
6A
7C
7A
SCOPE OF WORK
• Channel Walls ~2 Miles of Tangent Piles
• Demonstration Piles per Crew
• Working Platforms
• Sewer Siphon
• Utility Bridge with 48” Watermain
• Main Channel Transition
• River Diversion
• Josefina Channel Transition
• Power Line Relocation
• Dredging and Excavation
• Stormwater Penetrations
Temporary Sheet Piles
Drilled Shaft Piles
Guardrail
Concrete Cap
Drilled Shaft
Project Specifics
160’
~2 5’
Channel Bottom
• Approx. 1,700 six-foot diameter concrete drill shaft piles (~100 feet deep)
• Approx. 200,000 cy of concrete
• Approx. 46,000 tons of reinforcing steel
• Approx. 600,000 cy of excavated material to be disposed
• Approx. 25,000 cy of suitable fill
• Approx. 8,000 tons of steel sheet pile
Pay attention to POP: 2,190 days
• Perform confirmation borings
• Working platform with temporary sheet piles
• Install temporary casing to Approx. –50 feet
• Auger material with slurry
• Polymer or mineral slurry
• Inspect hole using sonicaliper testing and bottom excavation inspection device
• Install rebar cage and sonic logging testing tubes
• Concrete mix is critical with several additives
• Tremie concrete into hole
• Remove temporary casing
• Testing of pile
• Install concrete cap
Equipment to install and remove the temporary casing shall have sufficient vibratory, impact, and rotational torque capacity
Project Specifics
Excavation
Fill
Temporary Sheet Pile
Rio Piedras
Drilled Shaft
Pile
Working Platforms
Demonstration Wall per Crew
Single and Double Rows of Tangent Piles
Jet Grout (in some critical areas)
Drilled Shaft Piles, Heavily Reinforced
Rebar Cage
Sewer Siphon
Project Specifics
Four 20-inch diameter sanitary sewer pipes in 30-inch diameter steel permanent casing pipes
Drilled Shaft Piles
Pile Caps
Drilled Shaft Piles
Rip Rap
New Effluent BoxNew Influent Box
160’
Jack and Bore Pit Temporary Sheet Pile
Drilled Shaft Pile
Perimeter Walers and Bracing
Jacking Equipment
30-inch Diameter Steel Casing
Rio Piedras
Concrete Slab
~3
Fe et
Utility Bridge with 48-inch Diameter Watermain
Project Specifics
Rip Rap
Drilled Shaft Piles
48-inch Diameter Watermain
Pipe Saddles
Bridge Girder
Important Notes:
The contractor cannot increase the flooding risk of the surrounding community by obstructing flow
Florida Department of Transportation (FDOT) beams will be used for the utility bridge. This will require special coordination with the prestress beam suppliers in P.R
Valve Box Valve Box
Channel Transitions
Main Channel
Transition
Josefina Channel
Transition
Project Specifics Main Channel Transition
Articulated Concrete
BlockDrilled Shaft Piles
Concrete Armor Units
Rip Rap
Articulated Concrete Block
Rip Rap
Concrete Armor Units
Sheet Piles
River Flow
250’
Articulated Concrete Block
Drilled Shaft Piles
Permanent Sheet Piles
Temporary Sheet Piles
Concrete Armor Units
Drilled Shaft Piles
Main Channel Transition Water Diversion
Diverted River
Josefina Channel Transition
Articulated Concrete
Block
Drilled Shaft Piles
Concrete Armor Units
Rip Rap
Articulated Concrete
Block
Sheet Piles
Rip Rap Concrete
Armor Units
Sheet Piles
Concrete Armor Units
River Flow
163’
Power Line Relocation
Transmission and distribution lines to be demolished
Transmission and distribution lines to be constructed
Drilled Shaft Piles
Stormwater Box Opening
Existing Ground
Concrete Shelf
Stormwater Penetrations Through the Wall
Cap Beam
Manhole
Soil Improvement
Existing Storm Water Pipe
Stormwater Box Opening
Guardrail
Cap Beam
Concrete Shelf
Stormwater Penetrations Through the Wall
3’ 8’
La Chuleta
Material Management Areas, two (2):
1. La Chuleta for bank excavation
2. Offshore for material under the mean high high water line
Project Specifics
San Juan Harbor
La Chuleta
Mean High High Water Line
Offshore
La Chuleta
CONTRACTING OVERVIEW
Jaclyn Yocum Contract Specialist
Renee Booth Contracting Officer
Project Limits
ACQUISITION APPROACH
• Solicitation No. W51DQV25RA002
• Type of contract: Firm-fixed-price Design-Bid-Build Construction
• Acquisition Method: FAR Part 15 Negotiations – Request for Proposal (RFP), Full and Open Competition (Unrestricted)
• Transmission Method: Electronically via Procurement Integrated Enterprise Environment (PIEE). Bids must be received by the Government no later than July 3, 2025, at 10:00 am (AST).
• Estimated Magnitude of Construction: Over $500,000,000
• North American Industry Classification System (NAICS): 237990, Other Heavy and Civil Engineering Construction
• Estimated Period of Performance: 2190 calendar days after receipt of the Notice to Proceed (NTP)
• Liquidated Damages: $37,500.00 for each calendar day of delay until the work is completed or accepted
• Performance of Work by the Contractor: 30%
PROJECT GENERAL INFO
• Technical Inquiries and Questions: shall be submitted via Bidder Inquiry in ProjNet at (https://www.projnet.org). ProjNet closes ten (10) calendar days prior to bid closing. Bidders inquiries must be entered into ProjNet for an official answer.
• Bid Guarantee: an electronic copy of the bid guarantee shall be submitted with the bid. The bid guarantee shall be 20% of bid price or $3,000,000, whichever is less.
• Payment and Performance Bonds: awardee must submit payment and performance bonds equal to the total bid price within 10 days of contract award.
• Note: Subcontracting Plan is required from Other than Small Business Firms (FAR Part 19)
PROJECT GENERAL INFORMATION
https://www.projnet.org
• All amendments must be acknowledged in block 19 of the Standard Form (SF 1442) Solicitation
1. Make sure to monitor SAM.gov and PIEE for any amendments to be published.
AMENDMENTS
RESOURCES
• Systems for Award Management (SAM): www.sam.gov
• ProjNet: www.projnet.org
• Procurement Integrated Enterprise Environment (PIEE): https://piee.eb.mil
1. The only authorized transmission method of proposals in response to the subject solicitation is electronically via the Procurement Integrated Enterprise Environment (PIEE) website. No other transmission methods, such as email, facsimile, hand-carried, proprietary or DOD SAFE submissions, proposals submitted by mail, etc. will be accepted. Offers submitted via any other transmission method other than the PIEE website will not be evaluated.
2. The Offeror’s proposal/bid must be received by the Government no later than the date/time specified in the solicitation and cited above.
http://www.sam.gov/ http://www.projnet.org/ https://piee.eb.mil/
SITE VISIT DETAILS
Jorge L. Ayala-Burgos, P.E.
Chief, Technical Support Branch
Site Visit Start
Site Visit Stops/Drive-by Coordinates:
Stop 1:
• 18.421589, -66.082488
Stop 2:
• 18.420566, -66.082524
Drive-by 3: 25 Street
• 18.418203, -66.080975
Stop 4:
• 18.411928, -66.072259
Stop 5:
• 18.414003, -66.075766
| Rio Puerto nuevo flood and risk management (RPN FRM) PROJECT�supplemental Contract 3�channel bottom & wall improvements��PRE-bid CONFERENCE |
| agenda |
| project OVERVIEW |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Slide Number 17 |
| Slide Number 18 |
| Slide Number 19 |
| CONTRACTING OVERVIEW |
| Acquisition approach |
| PROJECT GENERAL INFO |
| Project General Information |
| AMENDMENTS |
| resources |
| Site visit details |
| Slide Number 27 |
File details come from the government source that posted it. Updated .