Exhibit_A_-_CDRLs_-_01.17.2017.pdf

PDF 406 KB Posted

Attached to
Joint Air-to-Ground Missile (JAGM) Shipping and Storage Containers (SSC)
Solicitation number
W31P4Q-17-R-0063
Issued by

About this file

Exhibit A - CDRLs

View the file

Other files

File Type Posted
Attachment_04_-_Deliverable_Hardware_Matrix_-_03.16.2017.pdf PDF
JAGM_SSC_Amendment_0005.pdf PDF
JAGM_SSC_Amendment_0004.pdf PDF
JAGM_SSC_Amendment_0003.pdf PDF
JAGM_SSC_Amendment_0002.pdf PDF
JAFM_SSC_Amendment_0001.pdf PDF
Attachment_02_-_DOCUMENT_SUMMARY_LIST_(DSL)_-_01.17.2017.pdf PDF
Attachment_03_-TECHNICAL_DATA_PACKAGE_(TDP)_13556595_-_01.17.2017.pdf PDF
Attachment_10_-_SECTION_L_-_INSTRUCTION_FOR_PROPOSAL_PREPARATION_-_01.17.2017.pdf PDF
Attachment_08_-_UNIT_PRICE_TABLE_-_01.17.2017.pdf PDF
Exhibit_A_-_CONTRACT_DATA_REQUIREMENTS_LIST_(CDRL)_-_01.17.2017.pdf PDF
Attachment_06_-_PRODUCTION_READINESS_PROCESS_MANUAL_-_01.17.2017.pdf PDF
Attachment_04_-_DELIVERABLE_HARDWARE_MATRIX_-_01.17.2017.pdf PDF
Attachment_13_-_SPECIAL_CLAUSES.pdf PDF
JAGM_SSC_RFP_17-R-0063_OFFICIAL.pdf PDF
Attachment_09_-GOVERNMENT_FURNISH_PROPERTY_(GFP)_-_01.17.2017.pdf PDF
Attachment_01_-STATEMENT_OF_WORK_(SOW)_-_01.17.17.pdf PDF
Attachment_11_-_SECTION_M_-_BASIS_FOR_AWARD_-_01.17.2017.pdf PDF
Attachment_05_-CONTRACT_SECURITY_CLASSIFICATION_DATA_(DD254)_WITH_SECURITY_CLASS_GUIDE_(SCG)_-_01.24.2017.pdf PDF
Attachment_07_-_PALLET_UNIT_CONFIGURATION_-_01.17.2017.pdf PDF
Attachment_12_-_PAST_PERFORMANCE_EVALUATION_QUESTIONNAIRE_FORM_-_01.17.2017.pdf PDF
Attachment_03_-_Technical_Data_Package_13556595_-_01.17.2017.pdf PDF
Exhibit_A_-_CDRLs_-_01.17.2017.pdf PDF
JAGM_SSC_Draft_RFP.pdf PDF
Attachment_05_-_DD254_SCG_and_SCG_attached_-_01.24.2017.pdf PDF
Attachment_12_-_Past_Performance_Evaluation_Questionnaire_Form_-_01.17.2017.pdf PDF
Attachment_09_-_Government_Furnished_Property_-_01.17.2017.pdf PDF
Attachment_07_-_Pallet_Unit_Configuration_-_01.17.2017.pdf PDF
Attachment_10_-_Section_L_v4.0_-_01.17.2017.pdf PDF
Attachment_01_-_SSC_SOW_Rev_1.5_-_01.17.17.pdf PDF
Attachment_04_-_Deliverable_Hardware_Matrix_-_01.17.2017.pdf PDF
Attachment_11_-_Section_M_v4.0_-_01.17.2017.pdf PDF
Attachment_06_-_Production_Readiness_Process_Manual_-_01.17.2017.pdf PDF
Attachment_02_-_Document_Summary_List_-_01.17.2017.pdf PDF
Attachment_08_-_Pricing_Table_-_01.17.2017.pdf PDF
Attachment_12_-_Past_Performance_Evaluation_Questionnaire_Form_-_01.17.2017.pdf PDF
JAGM_SSC_Draft_RFP.pdf PDF
Attachment_04_-_Deliverable_Hardware_Matrix_-_01.17.2017.pdf PDF
Attachment_01_-_SSC_SOW_Rev_1.5_-_01.17.17.pdf PDF
Attachment_09_-_Government_Furnished_Property_-_01.17.2017.pdf PDF
Attachment_06_-_Production_Readiness_Process_Manual_-_01.17.2017.pdf PDF
Attachment_07_-_Pallet_Unit_Configuration_-_01.17.2017.pdf PDF
Attachment_11_-_Section_M_v4.0_-_01.17.2017.pdf PDF
Attachment_10_-_Section_L_v4.0_-_01.17.2017.pdf PDF
Attachment_08_-_Pricing_Table_-_01.17.2017.pdf PDF
Attachment_02_-_Document_Summary_List_-_01.17.2017.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Shipping and Storage Container, Guided Missile P/N 13556595

Contract Data Requirements List (CDRL)

EXHIBIT A

W31P4Q-17-R-0063

DATE – 01 Jan 2017

Joint Air-to-Ground Missile

EXPORT CONTROL ACT WARNING: "WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App. 2401 et seq), as amended. Violations of these export laws are subject to severe criminal penalties.

Disseminate in accordance with provisions of DoD Directive 5230.25."

DISTRIBUTION STATEMENT D: Distribution authorized to the Department of Defense (DoD) and U.S. DoD contractors only; Critical Technology; 30 April 2014. Other requests shall be referred to: Project Manager, JAMS, SFAE-MSL-JA, Redstone Arsenal, AL 35898- 5710.

RRCONTRACT DATA REQUIREMENTS LIST (CDRL)

(1 Data Item)

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q‐17‐R‐0063

F. CONTRACTOR:

1. DATA ITEM NO.

A001

2. TITLE OF DATA ITEM

Production Status Report

3. SUBTITLE 17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐MGMT‐81255

5. CONTRACT REFERENCE

[SOW 27]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

Monthly

12. DATE OF FIRST SUBMISSION

30 DAC

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

N/A Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 14 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Dave Brown

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

1/17/2017 DD FORM 1423‐1, Feb 2001 PREVIOUS EDITION MAY BE USED Page 1 of 1 page(s)

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A002

2. TITLE OF DATA ITEM

Scientific and Technical Reports

3. SUBTITLE

Diminishing Manufacturing Sources and Material Shortages (DMSMS) Management

Plan

17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐MISC‐80711A

5. CONTRACT REFERENCE

[SOW 42]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

30 DAC

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

N/A Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 14 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Dave Brown

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A003

2. TITLE OF DATA ITEM

Scientific and Technical Reports

3. SUBTITLE

Production Line Changes

17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐MISC‐80711A

5. CONTRACT REFERENCE

[SOW 46]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

As Required

12. DATE OF FIRST SUBMISSION

N/A

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

As Required

13. DATE IF SUBSEQUENT SUBM.

N/A Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 14 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Dave Brown

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A004

2. TITLE OF DATA ITEM

Test Plan

3. SUBTITLE

First Article Test (FAT) Plan

17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐NDTI‐80566A

5. CONTRACT REFERENCE

[SOW 56], [SOW 64]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

See 16 Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 14 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blks 12 & 13: Submit NLT 28 days prior to testing.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Mark Tillman

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A005

2. TITLE OF DATA ITEM

Test Plan

3. SUBTITLE

Product Acceptance Performance Oriented Packaging (POP) Plan

17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐NDTI‐80566A

5. CONTRACT REFERENCE

[SOW 59]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

See 16 Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 14 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blks 12 & 13: Submit NLT 28 days prior to testing.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Mark Tillman

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A006

2. TITLE OF DATA ITEM

Test/Inspection Report

3. SUBTITLE

First Article Test (FAT) Report

17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐NDTI‐80809B

5. CONTRACT REFERENCE

[SOW 58], [SOW 67]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

See 16 Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 28 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blks 12 & 13: Submit NLT 28 days after testing.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Mark Tillman

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A007

2. TITLE OF DATA ITEM

Test/Inspection Report

3. SUBTITLE

Product Acceptance Performance Oriented Packaging (POP) Report

17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐NDTI‐80809B

5. CONTRACT REFERENCE

[SOW 61]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

See 16 Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 28 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blks 12 & 13: Submit NLT 28 days after testing.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Mark Tillman

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A008

2. TITLE OF DATA ITEM

Bill of Materials (BOM) for Diminishing Manufacturing Sources and Material Shortages Management

3. SUBTITLE 17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐PSSS‐81656A

5. CONTRACT REFERENCE

[SOW 40]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

30 DAC

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

30 DPT EOC Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 14 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Dave Brown

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A009

2. TITLE OF DATA ITEM

Engineering Change Proposal (ECP)

3. SUBTITLE 17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐SESS‐80639D

5. CONTRACT REFERENCE

[SOW 32]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

See 16

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

See 16 Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval of ECPs within 60 days after submittal.

Blk 9: DS shall be that of the most restrictive document being changed. For ECW see end of 1423 CDRL Package.

Blks 12 & 13: The Contractor shall submit formal ECPs to propose updates for Government controlled documents.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Sam Johnson

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A010

2. TITLE OF DATA ITEM

Request for Variance (RFV)

3. SUBTITLE 17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐SESS‐80640D

5. CONTRACT REFERENCE

[SOW 34]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

See 16

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

See 16 Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval of ECPs within 14 days after submittal.

Blk 9: DS shall be that of the most restrictive document being changed. For ECW see end of 1423 CDRL Package.

Blks 12 & 13: The Contractor shall submit formal RFVs to deviate from Government controlled documents.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Sam Johnson

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A011

2. TITLE OF DATA ITEM

Notice of Revision (NOR)

3. SUBTITLE 17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐SESS‐80642D

5. CONTRACT REFERENCE

[SOW 32]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

See 16

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

See 16 Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval of NORs within 60 days after submittal.

Blk 9: DS shall be that of the most restrictive document being changed. For ECW see end of 1423 CDRL Package.

Blks 12 & 13: The Contractor shall submit NORs concurrently with the formal ECP, DI‐

SESS‐80369.

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Sam Johnson

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Form Approved

OMB NO. 0704‐0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704‐0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization.

Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT

A

C. CATEGORY:

TDP _____ TM _____ Other __X__

D. SYSTEM/ITEM

JAGM SSC

E. CONTRACT/PR NO.

W31P4Q-17-R-0063

F. CONTRACTOR:

1. DATA ITEM NO.

A012

2. TITLE OF DATA ITEM

Configuration Audit Plan

3. SUBTITLE

Physical Configuration Audit (PCA) Plan

17. PRICE

GROUP

4. AUTHORITY (Data Acquisition Document No.)

DI‐SESS‐81646B

5. CONTRACT REFERENCE

[SOW 95]

6. REQUIRING OFFICE

SFAE‐MSL‐JAP

18. ESTIMATED

TOTAL PRICE

7. DD 250 REQ

LT

9. DIST STATEMENT

REQUIRED

D

10. FREQUENCY

N/A

12. DATE OF FIRST SUBMISSION

See 16

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

8. APP CODE

A

11. AS OF DATE

N/A

13. DATE IF SUBSEQUENT SUBM.

N/A Draft Final

Reg Repro

16. REMARKS

Blk 8: Government Approval or Disapproval within 21 days of receipt. Contractor shall submit revisions and comment responses within 14 days after receipt of Government comments.

Blk 9: For DS and ECW see end of 1423 CDRL Package.

Blk 12: Submit NLT 28 days prior to First Article Test (FAT).

Blk 14: Submission shall be via EDMS.

SFAE‐MSL‐JAP 1

See 16

15. Total 1

G. PREPARED BY

Sam Johnson

H. DATE

1/17/2017

I. APPROVED BY

Sam Johnson

J. DATE

Exhibit A

CDRL BLOCK 9 DISTRIBUTION STATEMENTS AND EXPORT CONTROL

DISTRIBUTION TYPE AND DESCRIPTION

A. Approved for public release; distribution is unlimited.

B. Distribution Authorized to U.S. Government Agencies Only; Administrative and Operational Use; 18 Aug 2014. Other requests for this document shall be referred to Joint Attack Munition Systems (JAMS) Project Office, ATTN: SFAE-MSL- JA, Redstone Arsenal, AL 35898-5710.

C. Distribution authorized to U.S. Government Agencies and their Contractors Only;

Administrative and Operational Use; 18 Aug 2014. Other requests for this document shall be referred to Joint Attack Munition Systems (JAMS) Project Office, ATTN: SFAE-MSL-JA, Redstone Arsenal, AL 35898-5710.

D. Distribution Authorized to DOD and U.S. DOD Contractors Only; Administrative and Operational Use; 18 Aug 2014. Other requests for this document shall be referred to Joint Attack Munition Systems (JAMS) Project Office, ATTN: SFAE-MSL- JA, Redstone Arsenal, AL 35898-5710.

E. Distribution Authorized to DOD Only; Administrative and Operational Use; 18 Aug 2014. Other requests for this document shall be referred to Joint Attack Munition Systems (JAMS) Project Office, ATTN: SFAE-MSL-JA, Redstone Arsenal, AL 35898-5710.

F. Further distribution only as directed by: Project Manager, Joint Attack Munition Systems (JAMS) Project Office, ATTN: SFAE-MSL-JA, Redstone Arsenal, AL 35898-5710 or higher DOD Authority. Critical Technology, 18 Aug 2014.

EXPORT CONTROL ACT STATEMENT

UNLESS OTHERWISE APPROVED BY THE JAMS PROJECT OFFICE, ALL

ENGINEERING TECHNICAL DATA, SOFTWARE AND COST DATA SHALL BE

SUBJECT TO EXPORT RESTRICTIONS AS FOLLOWS:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et. Seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App. 2401 et. Seq.

Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DOD Directive 5230.25.

File details come from the government source that posted it. Updated .