Question Set 5 for RFP W15QKN-22-R-0008 - final.pdf

PDF 144 KB Posted

Attached to
155mm XM1128 Artillery Metal Parts Assembly
Solicitation number
W15QKN-22-R-0008
Issued by

View the file

Other files

File Type Posted
W15QKN-22-R-0008 Amendment 0008 - Released for Posting 23 June 2022.pdf PDF
Attachment 0020 - ECP R22A2018 - XM1128 Metal Parts TDP Update.pdf PDF
Exhibit A - CDRL Index - XM1128 Artillery Metal Parts Assembly.docx DOCX document
W15QKN-22-R-0008 Amendment 0007 - Released for Posting 6 June 2022.pdf PDF
Responses to Question Set 10 for RFP W15QKN-22-R-0008 - final.pdf PDF
Amendment 0006 under RFP W15QKN-22-R-0008 - Released 24 May 2022.pdf PDF
Amendment 0005 under RFP W15QKN-22-R-0008 - 17 May 2022.pdf PDF
Question Set 9 for RFP W15QKN-22-R-0008 - final.pdf PDF
Attachment 0019 - ECP R21A2045 - 155MM Projectiles Add Additional Anti-Seize Vendors.pdf PDF
W15QKN-22-R-0008 - Amendment 0005 - Released for Posting 13 May 2022.pdf PDF
Question Set 8 for RFP W15QKN-22-R-0008 - final.pdf PDF
Question Set 7 for RFP W15QKN-22-R-0008 - final.pdf PDF
W15QKN-22-R-0008 Amendment 0004 - Released 13 April 2022.pdf PDF
Revised Exhibit A - CDRL Index - XM1128 Artillery Metal Parts Assembly.docx DOCX document
Question Set 6 for RFP W15QKN-22-R-0008 - final.pdf PDF
Exhibit A - CDRLs A001-A038 Index-XM1128 Artillery Metal Parts Assembly - Updated.docx DOCX document
Amendment 0003 under RFP W15QKN-22-R-0008 - Released 30 Mar 2022.pdf PDF
Attachment 0004 - Low Level Process Map - updated.pdf PDF
Attachment 0003 - Quality Assurance Addendum - updated.docx DOCX document
Attachment 0018 - XM1128 Metal Parts DD1423 Block14.pdf PDF
Question Set 4 for RFP W15QKN-22-R-0008 - final.pdf PDF
Question Set 2 for RFP W15QKN-22-R-0008 - final 24 Mar 2022.pdf PDF
Question Set 3 for RFP W15QKN-22-R-0008 - final.pdf PDF
Updated Attachment 0002 - Data Item Description Index - Contains 27 DIDS.docx DOCX document
Updated Exhibit A - CDRLs A001-A038 Index-XM1128 Artillery Metal Parts Assembly.docx DOCX document
Amendment 0002 under RFP W15QKN-22-R-0008.pdf PDF
Updated Attachment 0003 - Quality Assurance Addendum.docx DOCX document
Question Set 1 for RFP W15QKN-22-R-0008 - Final 10 March 2022.pdf PDF
Amendment 0001 to W15QKN-22-R-0008.pdf PDF
Attachment 0012 - ECP R21A2023 - 155mm Pallet Specification - Clarifying Nails.pdf PDF
Attachment 0003 - Quality Assurance Addendum.docx DOCX document
Attachment 0002 - Data Item Description Index - Contains 28 DIDS.pdf PDF
Attachment 0005 - FORM 3002 - Clearance Tech Information for Public Release.pdf PDF
Attachment 0006 - Non-Disclosure Agreement.docx DOCX document
Attachment 0010 - Past Performance Letter and Questionnaire.docx DOCX document
Attachment 0001 XM1128 Metal Parts Price Matrix.xlsx XLSX spreadsheet
Attachment 0016 - TDP 13071733 - XM1128 Metal Parts Assembly.pdf PDF
RFP W15QKN-22-R-0008 - XM1128 Metal Parts Assembly Released 26 Jan 2022.pdf PDF
Attachment 0008 - AMSTA-AR Form 1350 - Technical Data Request Questionnaire.pdf PDF
Attachment 0017 - TDP 13082834 - XM1128 Base Closure.pdf PDF
Attachment 0004 - Low Level Process Map.pptx PPTX presentation
Attachment 0011 - Proposal Adequacy Checklist.doc DOC document
Attachment 0015 - ECP R21A2038 - XM1128 Metal Parts Specification Release.pdf PDF
Attachment 0009 - Certificate of Destruction.doc DOC document
Attachment 0007 - DD2345MilitarilyCriticalTechnicalDataAgreement.pdf PDF
Attachment 0013 - RFV R20K8002 - Addtion of Mold Inibitors to Wood Pallets.pdf PDF
Exhibit A - CDRLs A001-A038 Index-XM1128 Artillery Metal Parts Assembly.docx DOCX document
Attachment 0014 - ECP R21K2015 - Clarification for Pallet Nails.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10MAR2022 Questions

W15QKN-22-R-0008

1. RFP page 32, SOW C.3.3.1.1 Process Control Documents: This SOW section requires the Contractor's Process Control Documents to be submitted for review. However, it does not indicate whether submittal is for Approval or for Information. If the Process Control Documents are required for approval, please provide the associated CDRLs and approval, revision, and final approval timeframes.

Government Response: Amendment 002 updated paragraph C.3.3.1.1.1 Phosphate and Painting Coating, under paragraph C.3.3.1.1, to include specific language stating “…the Contractor shall submit to the Government for review and approval all…”. Paragraph C.3.3.1.1.2 updated as follows : “…The Contractor shall submit the aforementioned documents, including revisions thereto, to the Government for review and approval in accordance with DD Form 1423 (DI- MGMT-81580). The submission shall include all data collected on qualification, testing and inspection as required in MIL-DTL-32692 paragraphs 4.4.4 and 3.7, and their respective subparagraphs, using the Process Control Documents submitted.” CDRL A007 already references C.3.3.1.1.1 and contains all associated timelines. CDRL A008 already references paragraph C.3.3.1.1.2 and contains all associated timelines.

2. MIL-DTL-326692 revNA, 3.4 Mechanical Properties: Can the USG provide evidence that the Mechanical Properties are achievable for the XM1128 Metal Parts?

Government Response: The Government will not provide evidence.

3. MIL-DTL-326692 revNA, 3.5 Projectile plane-strain fracture toughness: Can the USG provide evidence that Projectile Plane-Strain Fracture Toughness is achievable for the XM1128 Metal Parts?

Government Response: The Government will not provide evidence.

4. MIL-DTL-326692 revNA, 3.9.2 Ultrasonic wall thickness testing: The most recent ultrasonic calibration standards drawings were not provided with the solicitation and associated TDP.

Please provide the most recent ultrasonic calibration standards drawings.

Government Response: TDPL 13071733 (PRON: P22C12) Technical Data Package List for Projectile, 155MM: HE, XM1128 Metal Parts Assembly dated 09 DEC 2021 includes drawing 13071729 Rev -, Ultrasonic Inspection Standard, Wall Thickness. There are no further revisions.

5. MIL-DTL-326692 revNA, 4.3.1.1 Heat treatment inspection lot: Can the USG please provide more definition to the term "any length of time" in MIL-DTL-32692 para 4.3.1.1 Heat treatment inspection lot?

10MAR2022 Questions

W15QKN-22-R-0008

Government Response: The stated “any length of time” requirement in MIL-DTL-32692 paragraph 4.3.1.1 means amount of time greater than zero.

6. MIL-DTL-326692 revNA, 6.11 Heat treatment based on mechanical properties failure: Will the USG provide a rework procedure for the contractor to follow?

Government Response: The Government will not provide a rework procedure as a rework procedure is the responsibility of the Contractor per Attachment 003 Quality Assurance Addendum Item 3 Rework and Repair of Nonconforming Material, paragraph b.