M31_Fin_Amendment_03_Questions_&_Answers_W15QKN-19-R-0015_QUESTIONS_SUBMISSION_2.docx
DOCX document 20 KB Posted
- Attached to
- M31 FIN RFP W15QKN-19-R-0015
- Solicitation number
- W15QKN-19-R-0015
About this file
This document contains questions and answers regarding solicitation number W15QKN-19-R-0015 from the Department of the Army Materiel Command Contracting Command Picatinny Arsenal for the production of 120mm M31 tail fins. The solicitation requires an original proposal and seven paper copies along with two electronic CD copies, with the price factor included in all copies. The Process Control and Continuous Improvement clause and associated Process Control Plan are included as Attachment 0011 in the original solicitation, which provides guidance on characteristics requiring PFMEA, capability studies, MSA, and SPC.
This is an additional Question and Answer Attachment for "Submission 2" under RFP W15QKN-19-R-0015. There are only two (2) questions and responses in this attachment (Q6 & Q7). All other terms and conditions of this solicitation remain unchanged. Please read carefully.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Consolidated 120MM M31 Tail Fin RFP Questions W15QKN-19-R-0015
SUBMISSION 02
Firecon RFP/Program Questions
6. Question: It is unclear if the Price Factor should be included in the paper copies and the CD’s, per L.2.3.1.b. I do understand that 1 CD with the Price Factor only is required, but should the Price Factor, Volume III, be included in the “Original and 7 paper copies and 2 electronic CD copies of the proposal volumes, as reflected in L.3.”?
Response: Per the Solicitation in Section L.2.3.1.b., all Volumes are required to include an original, seven (7) paper copies, and two (2) electronic CD copies.
7. Question: We have an additional question regarding the PCCI clause and associated PCP (CDRL A010). The solicitation references both Table's g(1) and g(2) which are supposed to provide a list of characteristics that require PFMEA, Capability Studies, MSA and SPC respectively. We are not seeing these tables in the solicitation or in any of the attachments. Request guidance on how to determine which characteristics require these process control initiatives. Please reference C.5.8.2 and C.5.8.3 of the solicitation.
Response: The PCCI Clause is in "Attachment 0011" from Section J in Original 120mm M31 Tail Fin Solicitation (RFP) W15QKN-19-R-0015 in pages 10-13 along with Tables g(1) ( g(2) to complete CDRL A010. The processes and guidance are all within this PCCI Clause in Attachment 0011.