This document contains industry questions and government responses regarding a solicitation for tactical troposcatter transmission systems production and sustainment. The government agreed to revise language in the performance work statement to ensure consistency regarding priority levels for software trouble reports. While industry requested a one-week extension to the proposal response date of April 2nd due to required reviews, the government denied this request and maintained the original deadline. The government also declined alternate payment terms other than payment upon completion/delivery for non-hardware contract line items under the fixed-price contract.

Attachment 0015

View the file

Other files

File Type Posted
Question_and_Answer_from_SVD_051418.pdf PDF
Amend_0009.pdf PDF
A07_-_W15P7T18R0008-0008.pdf PDF
Attch_0016_Industry_Question_and_Govt_Response_No._74.xlsx XLSX spreadsheet
W15P7T18R0008-0007.pdf PDF
W15P7T18R0008-0005.pdf PDF
W15P7T18R0008-0006.pdf PDF
Attch_0001_FINAL_TROPO_PWS_23Mar2018.pdf PDF
W15P7T18R0008-0004.pdf PDF
Attch_0001_FINAL_TROPO_PWS_09Mar2018_Amend_0003.pdf PDF
Attch_0006_SVD_Addendum_13March2018_Amend_0003.docx DOCX document
Attch_0013_questions_and_answers_16Mar2018.xlsx XLSX spreadsheet
Attch_0009_TROPO_Pricing_25FEB2018_amend_0003.xlsx XLSX spreadsheet
Attch_0014_Security_Control_(004)_Amend_0003.pdf PDF
W15P7T18R0008_Amend_0003_16Mar2018.pdf PDF
Attch_0012_March_2_2018_combined_references_and_questions_and_answers_amend_0002.xlsx XLSX spreadsheet
W15P7T18R0008-0002.pdf PDF
Attch_0001_TROPO_PWS_7March2018.docx DOCX document
Attch_0002_TROPO_PWS_Appendix_A_-_SPS_27FEB2018.docx DOCX document
Attch_0009_TROPO_Pricing_25FEB2018_amend_0002.xlsx XLSX spreadsheet
Master_PWS_CDRL_List_update_02272018.xlsx XLSX spreadsheet
Attch_0006_SVD_Addendum_28FEB2018_amend_0002.docx DOCX document
Attch_0001_TROPO_PWS_27FEB2018_(002)_amend_0002.docx DOCX document
Attch_0006_SVD_Addendum_28FEB2018_amend_0002.docx DOCX document
Attch_0009_TROPO_Pricing_25FEB2018_amend_0002.xlsx XLSX spreadsheet
Attch_0012_March_2_2018_combined_references_and_questions_and_answers_amend_0002.xlsx XLSX spreadsheet
W15P7T18R0008-0001_16FEB2018.pdf PDF
Attch_0003_TROPO_PWS_Appendix_B_v2_Provisioning_Requirements.pdf PDF
Attch_0004_TROPO_PWS_Appendix_C_v2_CDA_Input_Data.pdf PDF
Attch_0001_FINAL_TROPO_PWS_9FEB2018.pdf PDF
Attch_0009_TROPO_Pricing_ak_09FEB2018_1332.xlsx XLSX spreadsheet
Attch_0010_TROPO_SBPCD_1545_240118v3.docx DOCX document
Attch_0011_DD254_Continuation.docx DOCX document
W15P7T-18-R-0008_14FEB2018.pdf PDF
Attch_0006_SVD_Addendum_30JAN2018.pdf PDF
Attch_0007_Marine_Corps_ID_Plate_Gold_Standard.pdf PDF
Exhibit_A_-_Master_PWS_CDRL_List_update_01292018.xlsx XLSX spreadsheet
Attch_0002_TROPO_PWS_Appendix_A_-_SPS.pdf PDF
Attch_0011_DD254__-_TROPO_13_NOV_17.pdf PDF
Attch_0005_TROPO_PWS_Appendix_D_v2_MAC_Prep.pdf PDF
Attch_0008_Visit_Request_Steps.ppt PPT presentation
DRAFT_TROPO_Pricing_Spreadsheet_and_Instructions_-_Draft_-_1-17-18.xlsx XLSX spreadsheet
PWS_draft_RFP_v30NOV2017.pdf PDF
PWS_Attach-A_SPS_draft_RFP_v30NOV2017.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Question NumberReferenceQuestionAnswer
71PWS Paragraph 3.8.2.2 and 3.4.7.2The Government appears to have conflicting language regarding the fix of STRs in Attachment 1 PWS Amendment 3. In PWS Paragraph 3.8.2.2 the Government indicates that all priority 1 and 2 STRs as agreed by the Government and the contractor shall be closed prior to delivery of the product with Priority 1 STRs corrected while priority 2 STRs corrected or mitigated down to a lower priority STR. However in PWS Paragraph 3.4.7.2 the language reads “The Contractor shall fix through a maintenance plan / warranty all software Category 1, 2, and 3 Type failures immediately upon becoming aware of the failure IAW Contractor’s best practices and the Government Configuration Control Process. Recommend the Government update PWS Paragraph 3.7.4.2 to be consistent with PWS Paragraph 3.8.2.2 and update to read: The Contractor shall correct or mitigate through a maintenance plan / warranty all software priority 1 and 2 Software Trouble Reports (STRs), as agreed to by the Government and contractor, IAW Contractor’s Best Practices and the Government Configuration Control Process. Priority 1 STRs shall be corrected while priority 2 STRs shall be corrected or mitigated down to the lesser priority STR.The Government accepts the proposed language as submitted. The PWS is revised to reflect the changed language.
72SolicitationAs a result of the questions responses and RFP updates, industry will need to complete a self-assessment and management review and approval prior to providing our bids to the Government. In order to accommodate these reviews and changes, it is respectfully requested that a one (1) week extension until April 9, 2018 be provided to respond to the Troposcatter solicitation.The Government does not concur with the request to extend the proposal response time by one week. The original proposal submission date of 2 April 2018 is sufficient.
73SolicitationWill the Government consider alternate payment terms (e.g. Progress Payments, milestones, Performance Based Payments, etc.) other than payment on completeion/delivery for non-hardware, fixed price CLINs?The Government will not consider alternate payment terms.