This document contains questions and answers related to a solicitation for the production and sustainment of tactical troposcatter transmission systems. The solicitation seeks proposals for a potential ten-year contract to provide troposcatter systems to the Army's Program Executive Office for Command Control Communications-Tactical, Project Manager Tactical Network, and Product Manager Network Modernization. Key details include questions on pricing approaches, contract ceilings, deliverables, testing requirements, cybersecurity controls, and mapping of performance work statement requirements to contract line items. Clarification is provided on references, evaluation criteria, and compliance with military standards.

Attachment 0013 Industry Questions and Government Responses

View the file

Other files

File Type Posted
Question_and_Answer_from_SVD_051418.pdf PDF
Amend_0009.pdf PDF
A07_-_W15P7T18R0008-0008.pdf PDF
Attch_0016_Industry_Question_and_Govt_Response_No._74.xlsx XLSX spreadsheet
W15P7T18R0008-0007.pdf PDF
W15P7T18R0008-0005.pdf PDF
W15P7T18R0008-0006.pdf PDF
Attch_0001_FINAL_TROPO_PWS_23Mar2018.pdf PDF
Attch_0015_Industry_Questions_and_Government_Responses_Amend_0004_23Mar2018.xlsx XLSX spreadsheet
W15P7T18R0008-0004.pdf PDF
Attch_0001_FINAL_TROPO_PWS_09Mar2018_Amend_0003.pdf PDF
Attch_0006_SVD_Addendum_13March2018_Amend_0003.docx DOCX document
Attch_0009_TROPO_Pricing_25FEB2018_amend_0003.xlsx XLSX spreadsheet
Attch_0014_Security_Control_(004)_Amend_0003.pdf PDF
W15P7T18R0008_Amend_0003_16Mar2018.pdf PDF
Attch_0012_March_2_2018_combined_references_and_questions_and_answers_amend_0002.xlsx XLSX spreadsheet
W15P7T18R0008-0002.pdf PDF
Attch_0001_TROPO_PWS_7March2018.docx DOCX document
Attch_0002_TROPO_PWS_Appendix_A_-_SPS_27FEB2018.docx DOCX document
Attch_0009_TROPO_Pricing_25FEB2018_amend_0002.xlsx XLSX spreadsheet
Master_PWS_CDRL_List_update_02272018.xlsx XLSX spreadsheet
Attch_0006_SVD_Addendum_28FEB2018_amend_0002.docx DOCX document
Attch_0001_TROPO_PWS_27FEB2018_(002)_amend_0002.docx DOCX document
Attch_0006_SVD_Addendum_28FEB2018_amend_0002.docx DOCX document
Attch_0009_TROPO_Pricing_25FEB2018_amend_0002.xlsx XLSX spreadsheet
Attch_0012_March_2_2018_combined_references_and_questions_and_answers_amend_0002.xlsx XLSX spreadsheet
W15P7T18R0008-0001_16FEB2018.pdf PDF
Attch_0003_TROPO_PWS_Appendix_B_v2_Provisioning_Requirements.pdf PDF
Attch_0004_TROPO_PWS_Appendix_C_v2_CDA_Input_Data.pdf PDF
Attch_0001_FINAL_TROPO_PWS_9FEB2018.pdf PDF
Attch_0009_TROPO_Pricing_ak_09FEB2018_1332.xlsx XLSX spreadsheet
Attch_0010_TROPO_SBPCD_1545_240118v3.docx DOCX document
Attch_0011_DD254_Continuation.docx DOCX document
W15P7T-18-R-0008_14FEB2018.pdf PDF
Attch_0006_SVD_Addendum_30JAN2018.pdf PDF
Attch_0007_Marine_Corps_ID_Plate_Gold_Standard.pdf PDF
Exhibit_A_-_Master_PWS_CDRL_List_update_01292018.xlsx XLSX spreadsheet
Attch_0002_TROPO_PWS_Appendix_A_-_SPS.pdf PDF
Attch_0011_DD254__-_TROPO_13_NOV_17.pdf PDF
Attch_0005_TROPO_PWS_Appendix_D_v2_MAC_Prep.pdf PDF
Attch_0008_Visit_Request_Steps.ppt PPT presentation
DRAFT_TROPO_Pricing_Spreadsheet_and_Instructions_-_Draft_-_1-17-18.xlsx XLSX spreadsheet
PWS_draft_RFP_v30NOV2017.pdf PDF
PWS_Attach-A_SPS_draft_RFP_v30NOV2017.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Question NumberReferenceQuestionAnswer
57Appendix A - System Performance Specification, paragraph 6, Table 6-1Rows I, 2. 3, 15, 16, 17 all contain "Error! Reference source not found" in the Section Reference column. Please provide the correct references or guidance that we can disregard that language.The references have been updated and the issue is resolved
58Attachment Tropo SBPCD, paragraph I, Table 1aTable 1a, Row A states: "This value shall equal the TOTAL CONTRACT VALUE defined as the IDIQ contract ceiling. $$$." Please provide the contract ceiling.The total contract value is the total value of your proposal.
59CDRLs, A063 Hardware Sustainment Transition PlanThe 1423 for this CDRL will not open. Request that the Government please provide the 1423 for CORL A063The updated list of CDRLs has corrected this issue.
60CDRLs, A077 Technical Data PackageThe 1423 for this CDRL is blank (i.e., the file contains a blank 1423 form)The updated list of CDRLs has corrected this issue.
61SPS, paragraph 3.1 1.4MIL-STD-1472 section 5.7.2.5, Signal Word, defines when to use Danger, Warning, Caution or Notice based on severity of bodily harm or equipment damage. This in combination with results from Radiation Hazard testing and standoff distance analysis based on maximum permissible radiation exposure limits will determine what level of "signal word" is used for RF radiation hazard. Is it the Government's intent that the SPS supersedes the MIL-STD-1472No, it is not Government’s intent to make SPS supersede the MIL-STD-1472. As stated in MIL-STD 1472, the combination of test results and safety risk assessment will determine the appropriate level of signal word.
62Where should contractor price the scope to execute PWS 3.1.50 NON-PDSS Transitioning CSC ls. Should this be provided in the Interim Contractor Support CLIN?This item is not typically separately priced. Offerors can add a row in the Attachment 0009 Pricing Spreadsheet under "Other FFP" tab if they chose to include the price in their proposal. Additional blank lines have been provided in this tab for these items.
63W15P7T-18-R-0008, paragraph 4, Government Testing Requirements: Production Verification Testing (PVT)Why only 2 systems when other programs ( T2C2) had 10?The Government intends to conduct simultaneous PVT tests. It is the intent to begin PVT after the first 2 systems are ready, and when additional systems are ready, they would be utilized for the respective PVT event(s) as well.
64PWS, paragraph 3.1.16.1Is it the Government's intent to make Army training optional?Yes, the Army may or may not elect to purchase training from the Offeror who receives the contract.
65PWS Appendix A, paragraphs 3.5.5.2 and 3.5.5.3The referenced MIL-STD-188-124B section 5.1.2.1.1.4 and 5.1.1.3.8.5
shielding of system cables and waveguides are for Fixed permanent facilities installation and not for transportable or tactical systems such as the ANT/TRC-XXX. PWS section 3.1.27.6 sets forth a requirement for the offeror's equipment grounding to be compliant with the requirements of NFPA 70-14, article 250, and the requirements of UL 60950-1, par 1.6.4 and section 2.6. Recommend PWS Appendix A 3.5.5.2 and 3.5.5.3 be replaced with PWS section 3.1.27.6 in order to ensure complete consistency.MIL-STD-188-124B is for grounding, bonding, and shielding for Long Haul/Tactical Communication Systems Including Ground Based Communications- Electronics Facilities and Equipments. As such, the MIL-STD applies to both tactical and fixed facilities. Any deviations that apply exclusively to tactical systems or fixed facilities are noted in the standard. What was section 3.1.27.6 (now 3.4.1.6) addresses grounding on the system level, while 3.5.5.2 and 3.5.5.3 of Appendix A references shielding of cables and grounding of waveguides, respectively.
66Pricing Sheet Warranty TabRecommend Government update tab to be consistentAttachment 0009, Pricing Spreadsheet and Instructions has been updated to be consistent with the ranges in other tabs.
67PWS, paragraph 4.6.1As typical there are identified vulnerabilities that are not remediated due to various limitations or design needs. This falls into a residual risk category that is acceptable. Recommend that adjusting the language to: “The Contractor shall perform selfassessment prior to any Government witnessed tests, and prioritize the remediation of all Very Low, Low, Moderate, High, and Very High findings with coordination with contractor/government CCB.”This recommended change to the Government will align this section with the language set forth in 4.7.1.The government concurs with the change and will make updates to the document accordingly.
68PWS, paragraphs 1.6.1 and 1.6.2Recommend updating to state that acceptance and inspection shall be at origin or destination on a CLIN by CLIN basis as this varies in the CLIN structure.The government concurs with the change and will make updates to the document accordingly.
69PWS and Section BThe PWS requirements do not clearly map to the CLIN structure as provided in the solicitation document. Instructions to industry as to what PWS line items to bid to what CLINs remains unclear and creates confusion for industry in being able to respond with clear and fair proposals to the Government. We recommend that the correct CLIN to PWS mapping be issued to industry.The CLINS have been revised to show the correct references to the PWS. In the event that industry continues to have uncertainty regarding the mapping of CLINs to the PWS, for any costs or prices that are not included elsewhere in the Pricing Spreadsheet and Instructions (Attachment 009), industry can use the additional rows in the "Other FFP" tab in the Pricing Spreadsheet and Instructions (Attachment 009) for such costs or prices.
70PWS, paragraph 4.5.3Industry requests that the Government provide the fully defined flow down/tailored RMF CNSSI 1253 controls specifically for this system.The Government has provided attachment 0014 (DoD Cybersecurity Control) containing Control Correlation Identifier (CCI) references. Detailed information of the individual CCI is available in NIST SP 800-53 Rev 4.

File details come from the government source that posted it. Updated .