VA69D-18-B-1687-00003004.pdf
PDF 1 MB Posted
- Attached to
- Complete Construction 1st & 2nd floors B405 Project# 676-18-107 Tomah VA Medical Center, Tomah, WI
- Solicitation number
- VA69D18B1687
About this file
VA69D-18-B-1687 00003 S06 - Amendment 00003 - Floor Flatness Test Results Letter.pdf
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
13605 1st Avenue N., Suite 100 Plymouth, MN 55441 Tel: 763.412.4000 Fax: 763.412.4090 www.ae-mn.com
A Service-Disabled Veteran-Owned Small Business
Civil Engineering Architecture Land Surveying Environmental Services Landscape Architecture
Anderson Engineering of Minnesota, LLC
Tomah VA Medical Center September 18, 2015 500 E. Veterans Street, B408/Rm 3800 Tomah, WI 54660
Attn: James Plimpton, Project Manager VIA Email: Jim Plimpton
Re: Floor Flatness Test Results Construct Building 405 for 75 MH RRTP Beds, VA Project #676-322 AE Project # 13316
Dear Jim, We have reviewed the Floor Flatness Test Results for the ground level slab as documented in the report prepared by Chosen Valley Testing, Inc. dated August 28, 2015 (attached). Three (3) test sections were done on the main floor area (West Wing, East Wing, and North Wing), with a fourth test area for the tramway link between Building 405 and 404.
A. The project specifications require the following:
1) The minimum acceptable overall values for finished slab flatness (FF) is 36 and the minimum levelness (FL) is 20. Minimum local values are FF-24 and FL-15. Test results at or above these numbers represent acceptable floor flatness and floor levelness of the slab.
2) The specifications also require level tolerance such that 80 percent of all points fall within a 20 mm (3/4 inch) envelope +10 mm, -10 mm (+3/8 inch, -3/8 inch) from the design elevation.
3) If individual slab section measures less than either of specified minimum local FF/FL numbers, that section shall be rejected and remedial measures shall be required. Sectional boundaries may be set at construction and contraction (control) joints, and not smaller than one half bay.
4) If composite value of entire slab installation, combination of all local results, measures less than either of specified overall FF/FL numbers, then whole slab shall be rejected and remedial measures shall be required.
B. The test results indicate the following:
1) The combined FF of the slab on grade for the main building pour areas is 27.11, and the combined FL is 19.75. Both of these are lower than the specified overall values of 36 and 20, respectively, and require remedial measures to bring the slab within specified tolerances.
Remedial measures to correct the slab areas are detailed in the project specifications and include grinding, planing, surface repair with underlayment compound or repair topping, re-topping, or removal and replacement of entire rejected slab areas. We recommend that a corrective plan of action be submitted by SEEDJV for approval by the VA.
2) Test results were also included for the tramway. As a significant area of the tramway is sloped the test results in this area were not incorporated into the combined FF/FL calculations. This area has an overall FF value of 11.64, which does not meet the minimum local FF value of FF-24. A corrective plan for this area should also be submitted. Note: Because of the sloping floor in this area FL requirements are not applicable.
ACCOMPANYING AMENDMENT VA69D-18-B-1687 00003
http://www.ae-mn.com/
Floor Flatness Test Results: Anderson Engineering of MN, LLC Construct Bldg 405 for 75 MH RRTP Beds AE Project #13316:
Date: 9/18/15
3) 80% of all points fall within a ¾’ envelope of the design floor elevation. This meets the specified requirement.
Please contact me if you have any questions about our review of the test results.
Sincerely, Bill Beaupre, RA, LEED AP Senior Project Architect Direct: 763-412-4051 Email: bbeaupre@ae-mn.com mailto:bbeaupre@ae-mn.com
Chosen Valley Testing, Inc.
La Crosse, WI Rochester, MN Mankato, MN St. Cloud, MN
135 Buchner Place, La Crosse, WI 54603 Phone (608) 782-5505 Fax (608) 785-2818
Mr. Tim Bentley August 28, 2015
Master Design Build
4706 N. Ravenswood Avenue
Chicago, IL 60640 tim@masterdesignbuild.com
Re: Floor Flatness Test Results
Tomah VA – Building 405
Tomah, Wisconsin
CVT Project# 6383.14.WIL
Dear Mr. Bentley, As requested, we have been performing floor flatness testing on the ground level slab of the Tomah
VA – Building 405, in Tomah, Wisconsin. The slab was poured on various days in August, 2015.
The specified FF is 36 and the specified FL is 20, with minimum local values of FF 24 and FL 15 for topping slabs which are exposed or receive thin-set tile or resilient flooring. Test results at or above these numbers represent acceptable floor flatness and floor levelness of the slab. In addition to the flatness and levelness numbers, the level tolerance must be such that 80% of all points fall within a
¾” envelope (± ⅜”) from the design elevation. The start point of each of our testing runs was assigned the assumed final floor elevation (100’).
The test was performed in general accordance with ASTM E 1155, Determining FF Floor Flatness and FL Floor Levelness Numbers. A Face Construction Technologies Dipstick 2272 Floor Profiler was used to obtain the test data.
Pour 8/6/15
The data was obtained in 4 runs using a zig-zag layout. The results of each run, as well as the overall results, are tabulated below. The approximate locations are shown on the attached sketch.
Run Number FF FL
1 26.59 19.12
2 25.81 12.59
3 26.71 28.51
4 33.21 22.97
Overall – 8/6/15 27.68 18.08
Specification 36 20
Pour 8/12/15
The data was obtained in 6 runs using a parallel and perpendicular layout. The results of each run, as well as the overall results, are tabulated below. The approximate locations are shown on the attached sketch.
1 28.69 52.15
2 26.16 18.03
3 27.04 33.57
ACCOMPANYING AMENDMENT VA69D-18-B-1687 00003
mailto:tim@masterdesignbuild.com
MDB_LLC
Typewritten Text
- West Wing
MDB_LLC
Typewritten Text
- East Wing
Building 405 – Tomah VA August 28, 2015
Project # 6383.14.WIL Page 2
La Crosse, Wisconsin Chosen Valley Testing Rochester, Minnesota
4 28.79 28.18
5 22.76 14.07
6 20.84 19.07
Overall – 8/12/15 25.16 21.13
Pour 8/26/15
The data was obtained in 6 runs using a parallel and perpendicular layout. The results of each run, as well as the overall results, are tabulated below. The approximate locations are shown on the attached sketch.
1 32.47 14.56
2 38.22 22.28
3 24.09 25.19
4 38.91 24.90
5 30.37 27.68
6 50.13 30.82
Overall – 8/26/15 31.31 21.10
Tramway
The data was obtained in 19 runs using a zig zag layout. The results of each run, as well as the overall results, are tabulated below. The approximate locations are shown on the attached sketch.
1 12.09 10.42
2 17.07 9.90
3 8.83 2.92
4 14.62 2.67
5 14.72 12.15
6 9.7 6.46
7 8.36 2.16
8 19.45 2.35
9 15.40 2.49
10 9.35 2.20
11 13.07 7.99
12 12.31 7.01
13 9.45 2.86
14 11.00 2.88
15 11.62 3.57
16 15.51 4.42
17 11.10 5.12
18 13.39 4.26
19 10.69 2.70
Overall – 8/26/15 11.64 3.38
Specification 36 N/A
Summary
The combined FF of the slab on grade is 27.11, with a combined FL of 19.75. The FF and the FL are lower than the specified overall value, though each pour meets the minimum local value.
The attached graphs show that 80% of all points fall within a ¾” envelope of the design floor
MDB_LLC
Typewritten Text
- North Wing
Building 405 – Tomah VA August 28, 2015
Project # 6383.14.WIL Page 3
La Crosse, Wisconsin Chosen Valley Testing Rochester, Minnesota elevation.
The ground level tramway was also tested. Because of the sloping floor, the test results were not incorporated into the overall results.
Remarks
We appreciate the opportunity to provide our services to you. If you have any questions, or need additional services, please call us at (608) 782-5505.
Sincerely, Kraig McCoy
Laboratory Manager
Elevations
1 2 3 in c h e s feet
0.1
0.2
0.3
0.4
0.5
-0.1
-0.2
-0.3
-0.4
-0.5
0 10 20 30 40 50
ACCOMPANYING AMENDMENT VA69D-18-B-1687 00003
User Line
User Line kmccoy Typewriter -.375 kmccoy Typewriter .375 kmccoy Typewriter Pour 8/6/15
4 5 6 in c h e s feet
0.1
0.2
0.3
0.4
0.5
-0.1
-0.2
-0.3
-0.4
-0.5
0 5 10 15 20 25
ACCOMPANYING AMENDMENT VA69D-18-B-1687 00003
kmccoy Typewriter Pour 8/26/15 kmccoy Typewriter .375 kmccoy Typewriter kmccoy Typewriter -.375
User Line
User Line
4 5 6 in c h e s feet
0.1
0.2
0.3
0.4
0.5
0.6
-0.1
-0.2
-0.3
-0.4
-0.5
-0.6
0 10 20 30
ACCOMPANYING AMENDMENT VA69D-18-B-1687 00003
kmccoy Typewriter kmccoy Typewriter Pour 8/12/15
User Line
User Line kmccoy Typewriter kmccoy Typewriter -.375 kmccoy
.375
��0�1����2���� ��0��3�� ���������4����������������+���������������� �������3��� �0������������������� ����3�������������������� ���������4��������4)�)���� �0����� ����'���0��3� ���5�4��
��6� ��6�
��6���6�
��6� ��6�
�6
�6 � �1
6�����
�7�� �����*+��'���-�1
�0��- .�*��8����� ���4 ���������������1��
�1
ACCOMPANYING AMENDMENT VA69D-18-B-1687 00003
User Arrow
User Arrow
User Arrow
User Arrow kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter Pour 8/6/15 kmccoy Typewriter Pour 8/12/15 kmccoy Typewriter
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter Pour 8/26/15 kmccoy Typewriter
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy
| ����� | �� | |
| ���� | ���� |
| � | �� | ������� |
| ������������ | ��� |
| ��������� | � |
| ����� | ������������������ |
| ���������� | �������� |
| ���������� | ���������� |
| ���� | ��������� |
ACCOMPANYING AMENDMENT VA69D-18-B-1687 00003
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow
User Arrow kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy Typewriter kmccoy
File details come from the government source that posted it.