This is a Task Order Proposal Request (TOPR) for road and bridge construction services under the USFS Region 4 MATOC, specifically for the Upper Green River Corridor Improvements project in the Bridger-Teton National Forest, Wyoming. The scope includes two reroutes and road reconditioning on Cove Mountain Road (NFSR 30343), road reconditioning and surfacing on Holt Canyon Road (NFSR 30010), and New Castle – Pine Valley Road (NFSR 30011).

The project value ranges between $500,000 and $3,000,000, with a 20% bid bond required for offers exceeding $150,000. Performance and payment bonds of 100% are required for contracts over $150,000. Work must commence within 10 days of Notice to Proceed and be completed within 120 calendar days, no later than October 14, 2025. The project location is approximately 31 miles northwest of Pinedale, Wyoming. A site visit is expected before submitting an offer. The contract includes minority (5.1%) and female (6.9%) participation goals for Utah, Washington County. Responses must be emailed to paul.larsen@usda.gov, with wage determination WY20240038 applicable to the project.

View the file

Other files

File Type Posted
1240LU24R0012 Amendment 0003.pdf PDF
RFIs as of 27Jan2025.pdf PDF
RFIs as of 21Jan2025.pdf PDF
FSR4_RoadandBridgeMATOC_SiteVisit_Attendance_241028.pdf PDF
Upper Green River Drawings 1.7.2025 Amd 0002.pdf PDF
Causey Reservoir Drawings 01.10.2025_Part2.pdf PDF
Causey Reservoir Drawings 01.10.2025_Part1.pdf PDF
Causey Reservoir SOI 1.10.2025 Amd 0002.pdf PDF
Cove Mountain SOI Amd 0002.pdf PDF
Upper Green River SOI 1.7.2025 Amd 0002.pdf PDF
1240LU24R0012 Amendment 0002.pdf PDF
Charleston Jarbidge Site Pictures.pdf PDF
RFIs as of 16Jan2025.pdf PDF
RFIs as of 8Jan2025.pdf PDF
North Fritz Creek Images.pdf PDF
1240LU24R0012 Amendment 0001.pdf PDF
Cove Mountain Drawings.pdf PDF
Charleston Jarbidge TOPR.pdf PDF
Charleston Jarbidge Bridge FSSS.pdf PDF
Upper Green River Drawings.pdf PDF
North Fritz Culvert TOPR.pdf PDF
Cove Mountain FSSS final.pdf PDF
Past Performance Questionnaire.docx DOCX document
North Fritz Culvert Drawings.pdf PDF
North Fritz Culvert SOI.pdf PDF
Cove Mountain TOPR.pdf PDF
Upper Green River FSSS.pdf PDF
Causey TOPR.pdf PDF
Charleston Jarbidge SOI.pdf PDF
Causey Cover Sheet Signed.pdf PDF
North Fritz Culvert FSSS.pdf PDF
Cove Mountain SOI.pdf PDF
Causey Reservoir FSSS.pdf PDF
Causey Reservoir Drawings.pdf PDF
Causey Reservoir SOI.pdf PDF
1240LU24R0012 USFS Region 4 MATOC.pdf PDF
Upper Green River SOI.pdf PDF
Charleston Jarbidge Bridge Drawings.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TASK ORDER PROPOSAL REQUEST (TOPR)

USFS, Region 4, Road and Bridge Construction MATOC

Project Name:

Upper Green River Corridor Improvements

Contracting Officer/Email: paul.larsen@usda.gov

Technical Contact/Email: Phil Wong, philip.wong@usda.gov

Project Location: The Bridger-Teton National Forest (BTNF), Upper Green River Corridor Improvement project is in Sublette County, Wyoming within the Pinedale Ranger District.

Map location is approx. 31 miles northwest of Pinedale, Wyoming via U.S Hwy 191 (6.0 miles, MP 105.5) and WY-352 (25.0 miles).

National Forest System Road (NFSR) 370600, Union Pass Road, starts at the end of pavement where WY-352 ends. Approximate Latitude and Longitude of the start of Union Pass Road and Green River Lakes Road are 43.221276°, - 110.008124° and 43.260033°, -110.016450°, respectively.

Reply Due (Date/Time): See SF 1442 for 1240LU24R0012

This is a competitive request under the USFS, Region 4 IDIQ Road and Bridge Construction Services MATOC. Responses shall be emailed to paul.larsen@usda.gov. All questions regarding this request shall be submitted in writing to the Contracting Officer at the email listed.

Scope of Work: Work consists of two reroutes as well as road reconditioning on the Cove Mountain Road (NFSR 30343), road reconditioning and surfacing on the Holt Canyon Road (NFSR 30010), and road reconditioning and surfacing on the New Castle – Pine Valley Road (NFSR 30011).

Special Conditions:

Price range per FAR 36.204(d): Between $500,000 and $3,000,000.

Bid Bond/Offer Guarantee (FAR 52.228-1): 20% required if quote/offer in excess of $150,000.

Performance and Payment Bonds: Both required at 100% of original contract price if value in excess of $150,000, due 10 days after award. Only payment protections required for contracts exceeding $35,000 but not exceeding $150,000, irrevocable letter or credit or payment bond allowed per FAR 52.228-13, due within 10 days of contract award.

Period of Performance (52.211-10): Commence work within 10 days following NTP, complete work within 120 calendar days, complete the entire work ready for use not later than 14 October 2025.

Site Visit: Per FAR 52.236-3 offerors are encouraged and expected to visit the site of construction prior to submitting an offer.

Wage Determination, General Decision Number: WY20240038

FAR 52.222-23 Goals: Minority 5.1%, Female 6.9%, Covered Area- Utah, Washington County.