Upper Green River SOI.pdf
PDF 28 KB Posted
- Attached to
- UNITED STATES FOREST SERVICE, INTERMOUNTAIN REGION 4, ROAD AND BRIDGE CONSTRUCTION SERVICES MATOC
- Solicitation number
- 1240LU24R0012
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items (SOI) for the Upper Green River Corridor Road Improvement Phase One project in the Bridger-Teton National Forest, Pinedale Ranger District in Sublette County, Wyoming. The document is divided into three base sections covering different road areas: Base 1 (Union Pass Road), Base 2 (Green River Lakes Road), and Base 3 (Additional Green River Lakes Road).
The work includes mobilization, construction staking, culvert removal and installation, aggregate surface course placement, road reconditioning, roadway embankment construction, and temporary traffic control. Specific quantities include 6,700 CY of aggregate surface course and installation of various sized culverts (18-inch, 24-inch, and 30-inch) for Base 1; 2,990 CY of aggregate surface course and 3,920 CY of roadway embankment construction for Base 2; and 3,710 CY of aggregate surface course and 4,880 CY of roadway embankment construction for Base 3. The document provides blank columns for unit prices and total costs to be filled in by bidders.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS (SOI)
Date:
Item Number Description Method of
Measurement Unit Quantity Unit Price Total
151.01 Mobilization LSQ LS 1
152.01 Construction Staking LSQ LS 1
203.01 Removal of Existing Culvert AQ EA 11
301.12
Aggregate Surface Course
(Government Furnished, Compacted In-Place, includes hauling)
CQ CY 6700
303.01 Road Reconditioning CQ MI 2.81
602.01 18 Inch Culvert (Furnish & Install) AQ LF 360
602.02 24 Inch Culvert (Furnish & Install) AQ LF 150
603.03 30 Inch Culvert (Furnish & Install) AQ LF 60
635.01 Temporary Traffic Control LSQ LS 1
Item Number Description Method of
Measurement Unit Quantity Unit Price Total
151.02 Mobilization LSQ LS 1
152.02 Construction Staking LSQ LS 1
203.02 Removal of Existing Culverts AQ EA 15
204.01
Roadway Embankment
Construction, Placement method
2 (Commercial Source, Compacted In-Place, includes hauling)
CQ CY 3920
301.13
Aggregate Surface Course
(Government Furnished, Compacted In-Place, includes hauling)
CQ CY 2990
602.04 18 Inch Culvert (Furnish & Install) AQ LF 715
602.05 24 Inch Culvert (Furnish & Install) AQ LF 60
602.06 36 Inch Culvert (Furnish & Install) AQ LF 125
635.02 Temporary Traffic Control LSQ LS 1
Item Number Description Method of
Measurement Unit Quantity Unit Price Total
151.03 Mobilization LSQ LS 1
152.03 Construction Staking LSQ LS 1
204.02
Roadway Embankment
Construction, Placement method
2 (Commercial Source, Compacted In-Place, includes hauling)
CQ CY 4880
301.14
Aggregate Surface Course
(Government Furnished, Compacted In-Place, includes hauling)
CQ CY 3710
635.03 Temporary Traffic Control LSQ LS 1
Base 1, 2, 3 Items Total
Base 2 Items (Green River Lakes Road)
Base 2 Items Sub-Total
Base 3 Items (Additional Green River Lakes Road)
Base 3 Items Sub-Total
Upper Green River Corridor Road Improvement Phase One
Bridger-Teton National Forest
Pinedale Ranger District
Sublette County, Wyoming
Base 1 Items (Union Pass Road)
Base 1 Items Sub-Total
File details come from the government source that posted it. Updated .