Causey Reservoir SOI 1.10.2025 Amd 0002.pdf
PDF 66 KB Posted
- Attached to
- UNITED STATES FOREST SERVICE, INTERMOUNTAIN REGION 4, ROAD AND BRIDGE CONSTRUCTION SERVICES MATOC
- Solicitation number
- 1240LU24R0012
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a Schedule of Items document for a construction project at Causey Reservoir, issued by the USDA Forest Service. The schedule outlines three main components: a base bid for an overflow parking lot, Option 1 for an overflow parking lot trail, and Option 2 for a concrete sidewalk.
The base bid includes 11 line items for parking lot construction, featuring mobilization, survey/staking, clearing/grubbing (1 acre), excavation (2,200 CY), crushed aggregate base course (1,000 CY), 80 barrier rocks, riprap installation, 16 reflective signs, traffic control plan, 2 bollards, and geotextiles. Option 1 encompasses trail construction with 5 line items including mobilization, survey work, clearing/grubbing (1 acre), excavation (675 CY), and crushed aggregate surface course (75 CY). Option 2 consists of a single line item for concrete sidewalk installation requiring approximately 7 cubic yards each of concrete and crushed aggregate. The document includes columns for unit pricing and total pricing, though no prices are filled in.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LINE
ITEM
ITEM
NUMBER DESCRIPTION METHOD OF
MEASUREMENT UNIT QUANTITY UNIT PRICE TOTAL PRICE
BASE BID- OVERFLOW PARKING LOT
1 15101 Mobilization LSQ LS 1 $ -
2 15201 Construction Survey and Staking, Method I, Tolerance A LSQ LS 1 $ -
3 20102 Clearing And Grubbing, Disposal By Scattering in project site - In Area Designated by COR CQ ACRE 1 $ -
4 20401 Excavation and Embankment (Parking Lot, Includes ditchwork, includes moving wheel stops approx. up to 300ft ) - Common and Loose Rock. (F) Placement Method 6. CQ CY 2,200 $ -
5 30103 Crushed Aggregate Base course purchased Gradation Designation D , Haul and Place- 6" compacted. (F) Placement Method 6. (For Parking Lot) CQ CY 1,000 $ -
6 322205-2 Barrier Rocks: 36"+/- 6" ( Must be imbedded 1/3 of the way) Commercial Source. AQ EA 80 $ -
7 25101 Rock Disipator -Riprap (Class II) -Furnish and Place as shown on sheet 8. See Table 705-1 CQ CY 30 $ -
8 63306 Signs (See Sheet 15) Type 4 Retro Reflective with metal tube / breakable base AQ EA 16 $ -
9 63501 Traffic Control Plan and Implementation (Includes 4 Construction/Information Signs) LSQ LS 1 $ -
10 710.04 Bollard Installation- 7' Of 6" Steel Pipe filled with Concrete. AQ EA 2 $ -
11 71401 Earthwork Geotextiles - Class 1 Non-Woven Type A, Furnish and Install. (Rock Dissipater See sheet 8. ) CQ SY 200 $ -
OPTION 1 - OVERFLOW PARKING LOT TRAIL
1 15101 Mobilization LSQ LS 1 $ -
2 15201 Construction Survey and Staking, Method I, Tolerance A LSQ LS 1 $ -
3 20102 Clearing And Grubbing, Disposal By Scattering in project site - In Area Designated by COR CQ ACRE 1 $ -
4 20401 Excavation and Embankment (Trail Access) - Common and Loose Rock (F) Placement Method 6 CQ CY 675 $ -
5 30103 Crushed Aggregate Surface course purchased Gradation Designation H, Haul and Place- 6" compacted. (F) Placement Method 6 (For Trail Leading to Reservoir) CQ CY 75 $ -
OPTION 2 - CONCRETE SIDEWALK
1 60102 Concrete, Pads 4" Thick (Infront of new restrooms) ( Includes prepwork, Roadbase, Forming) -
Approx. 7 cubic yards of concrete, Approx. 7 cubic yards of 4" layer of Crushed Aggregate Gradation Designation C
LSQ LS 1 $ -
Total
Total
TOTAL BASE PLUS ALL OPTIONS
USDA Forest Service
Total
SCHEDULE OF ITEMS
Causey Reservoir Project