This is a Schedule of Items form for the North Fritz Creek Culvert Replacement project, which appears to be part of a larger USFS road and bridge construction MATOC solicitation. The form outlines 10 line items covering the full scope of the culvert replacement work, including mobilization, construction survey and staking, soil erosion control, clearing and grubbing, culvert removal and disposal, structure excavation, riprap placement, culvert installation, and stream channel rehabilitation.
The specific quantities required include 20 cubic yards of Class 3 riprap from a commercial source and 40 cubic yards of aggregate surface course with Grading (H) and Compaction (B) specifications under Option 1. Most line items are designated as lump sum with a quantity of 1. The form includes columns for unit costs and total costs but is blank, appearing to be a template for contractors to complete with their proposed pricing.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
North Fritz Creek Culvert Replacement
Item No.
Unit of
Measure Qty Unit Cost Total
15100 Lump Sum 1
15200 Lump Sum 1
15700 Lump Sum 1
20100 Lump Sum 1
20300 Lump Sum 1
20800 Lump Sum 1
25100 Cubic Yard 20
60300 Lump Sum 1
64800 Lump Sum 1
32200 Cubic Yard 40 Aggregate surface course, Grading (H), Compaction (B), (Commercial Source)
Project Total:
Structure Excavation and Backfill
Placed Riprap, Class 3 (Commercial Source)
Culvert Structure, Design, Fabricate, Deliver, and Install
Stream Channel rehabilitation
Option 1
Description
Mobilization
Construction Survey and Staking
Soil erosion and pollution control
Clearing and Grubbing, Slash Treatment Methods for Tops and Limbs (k), Logs (i), and Stumps (a)
Removal of Culvert, Disposal Method (a)