About this file
This is a Task Order Proposal Request (TOPR) from the USFS Region 4 for the Charleston Jarbidge Bridge Replacement project in Elko County, Nevada. The work involves removing an existing bridge and installing a 128" x 83" corrugated metal pipe-arch culvert while maintaining public vehicle access through a temporary rock ford upstream.
The project, valued between $250,000-$500,000, requires completion by October 30, 2025, with work to commence within 10 days of Notice to Proceed. Key requirements include: construction during low creek flow periods (typically August-October), pressure washing of all equipment before entering National Forest land, obtaining necessary permits (Construction Stormwater, Working In Waterways, Temporary Discharge), and maintaining temporary facilities. A 20% bid bond is required for offers exceeding $150,000, with 100% performance and payment bonds due within 10 days of award. The project includes minority (9.2%) and female (6.9%) employment goals for Elko County, Nevada. Site visits are expected prior to offer submission, and responses should be emailed to paul.larsen@usda.gov.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TASK ORDER PROPOSAL REQUEST (TOPR)
USFS, Region 4, Road and Bridge Construction MATOC
Project Name:
Charleston Jarbidge Bridge Replacement
Contracting Officer/Email: paul.larsen@usda.gov
Technical Contact/Email: Coby Cubic, coby.cubic@usda.gov
Project Location: From Elko, NV drive northwest on NV-225 N (Mountain City Highway) for 54 miles. Turn right (east) on N Fork Charleston Road / County Road 746 and continue east for approximately 20 miles. Road will curve left, continue north for another 2.5 miles. The culvert is along Charleston Jarbidge road /County Road 746. The project is located at 41° 42.2' N, 115° 29.0' W
Reply Due (Date/Time): See SF 1442 for 1240LU24R0012
This is a competitive request under the USFS, Region 4 IDIQ Road and Bridge Construction Services MATOC. Responses shall be emailed to paul.larsen@usda.gov. All questions regarding this request shall be submitted in writing to the Contracting Officer at the email listed.
Scope of Work: Work will consist of removing the existing Charleston-Jarbidge Road Bridge and installing a 128” x 83” corrugated metal pipe-arch culvert in the same location. Public vehicle access must be maintained during the entire project, so a rock ford and road approaches shall be constructed and maintained just upstream of the existing bridge prior to the bridge removal.
Special Conditions:
- Construction will occur in and over 76 Creek. Construction must take place when creek flows are low and ground is not frozen. In a typical year, work can be completed from August to October.
- All construction equipment shall be pressure washed before entering National Forest System lands.
The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brush-guard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
- In general, utilities are not available at the site for construction purposes. Water from the creek shall not be used for construction purposes.
- The Contractor shall provide temporary toilet facilities at the site during all construction work.
- Contractor to obtain all necessary construction permits, including but not limited to Construction
Stormwater Permit, Working In Waterways Permit and Temporary Discharge Permit.
- The contractor will be responsible to obtain a Utah pollution Discharge Elimination Systems permit for the project and is responsible to adhering to best management practices throughout construction.
No work anticipated to be performed in riparian areas or wetlands.
- Staging and camping will be allowed and approved by the CO.
Price range per FAR 36.204(d): Between $250,000 and $500,000.
Bid Bond/Offer Guarantee (FAR 52.228-1): 20% required if quote/offer in excess of $150,000.
Performance and Payment Bonds: Both required at 100% of original contract price if value in excess of $150,000, due 10 days after award. Only payment protections required for contracts exceeding $35,000 but not exceeding $150,000, irrevocable letter or credit or payment bond allowed per FAR 52.228-13, due within 10 days of contract award.
Period of Performance (52.211-10): Commence work within 10 days following NTP, complete work within
120 calendar days, complete the entire work ready for use not later than 30 October 2025.
Site Visit: Per FAR 52.236-3 offerors are encouraged and expected to visit the site of construction prior to submitting an offer.
Wage Determination, General Decision Number: NV20240055
FAR 52.222-23 Goals: Minority 9.2%, Female 6.9%, Covered Area- Nevada, Elko County.