UFGS 09 06 90 Color Schedule (need colors).docx

DOCX document 30 KB Posted

Attached to
Hill Air Force Base Epoxy Flooring and Maintenance IDIQ Federal contract opportunity
Solicitation number
FA8201-23-R-0010
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

View the file

Other files for this federal contract opportunity

Other files attached to Hill Air Force Base Epoxy Flooring and Maintenance IDIQ, newest first.
File Type Posted
Epoxy IDIQ Solicitation QA.pdf PDF
Schedule B 5.5 yrs.xlsx XLSX spreadsheet
Screenshot Seed Task Area.jpg JPG image
Epoxy IDIQ Section L 1 May 23 Updated.docx DOCX document
Seed Task Order Striping Plan.pdf PDF
Revised Basic IDIQ SOW 1_May_23.pdf PDF
Screenshot Meeting Location.jpg JPG image
Epoxy IDIQ Section M 1 May 2023.docx DOCX document
Seed TO Bldg-265 WT 12390692 Epoxy West Section.pdf PDF
UFGS 09 67 23.15 Fuel Resistive Resinous Flooring, 3-Coat System.pdf PDF
UFGS 32 01 19.61 Rigid Pavement Joint Seal.pdf PDF
UFGS 09 96 59 High-Build Glaze Coatings.pdf PDF
WD - Davis.pdf PDF
WD - Box Elder.pdf PDF
Schedule B 5.5 yrs.xlsx XLSX spreadsheet
Seed Task Order Pricing Sheet - Bldg 265 West Bay.xlsx XLSX spreadsheet
afi31-118.pdf PDF
BASE FACILITY DESIGN STANDARD.Jan 23 2023.docx DOCX document
UFGS 01 57 19 Temporary Environmental Controls.pdf PDF
UFGS 09 67 23.16 Fuel Resistive Resinous Flooring, 5-Coat System.pdf PDF
UFGS 01 11 00 Summary of Work.pdf PDF
UFGS 02 42 51 Carpet Removal and Reclamation.pdf PDF
UFGS 32-13-13.06 PCC.docx DOCX document
Solicitation - FA820123R0010.pdf PDF
Epoxy IDIQ Section L 1 May 23.docx DOCX document
Seed TO Bldg 265 West Bay SOW 22 March 2023.pdf PDF
UFGS 01 45 00.00 20 Quality Control.pdf PDF
UFGS 01 20 00 Price and Payment Procedures.pdf PDF
01 57 20 Environmental Protection.docx DOCX document
UFGS 09 67 23.14 Chemical Resistant Resinous Flooring.pdf PDF
UFGS 02 41 00 Demolition and Deconstruction.pdf PDF
UFGS 32 01 19.61 Resealing of Joints in Rigid Pavement.docx DOCX document
Epoxy IDIQ SOW 1_May_23.pdf PDF
RFP for Epoxy Seed Task Order Bldg 265 West Bay.pdf PDF
UFGS 09 90 00 Paints and Coatings.pdf PDF
ufc_1_300_02.pdf PDF
UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls.pdf PDF
UFGS 01 35 26 Government Safety Requirements.pdf PDF
UFGS 32 13 13.06 Concrete for Site Facilities.pdf PDF
UFGS 01 32 01.00 10 Project Schedule.pdf PDF
UFGS 09 06 00 Schedules for Finishes.pdf PDF
01 35 26 Government Safety Requirements.docx DOCX document
UFGS 09 67 23.13 Standard Resinous Flooring.pdf PDF
01 32 00 Project Schedule.docx DOCX document
UFGS 01 62 35 Recycled - Recovered Materials.docx DOCX document
01 00 00 General Requirements.docx DOCX document
WD - Weber.pdf PDF
UFGS 09 96 00 High-Performance Coatings.docx DOCX document
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION TABLE OF CONTENTS

DIVISION 09 – FINISHES

SECTION 09 06 90

COLOR SCHEDULE

05/09

PART 1 GENERAL

1.1 SUMMARY

PART 2 PRODUCTS

2.1 COLOR SCHEDULE

2.2 EXTERIOR FINISHES (NOT USED)

2.3 INTERIOR FINISHES

2.3.1 Interior Floor Finishes

2.3.1.1 Concrete (Paint)

2.3.1.2 Industrial Floor Coating

2.3.2 Interior Base Finishes

2.3.2.1 Resilient Base and Moldings

2.3.2.2 Integral Cove Base

2.3.2.3 Paint

2.3.3 Interior Wall Finishes (Not Used)

2.3.4 Interior Ceiling Finishes (Not Used)

2.3.5 Interior Trim

2.3.5.1 Metal Stairs

2.3.5.2 Bollards

2.4 PLACEMENT SCHEDULE

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 09 06 90 Page 2

SECTION 09 06 90 COLOR SCHEDULE

05/09

PART 1 GENERAL

1.1 SUMMARY

This section covers only the color of interior materials and products that are exposed to view in the finished construction. The word "color", as used herein, includes surface color and pattern. Requirements for quality, product specifications, and method of installation are covered in other appropriate sections of the specifications. Specific locations where the various materials are required are shown on the drawings if not identified in this specification. Items not designated for color in this section may be specified in other sections. When color is not designated for items, propose a color for approval.

PART 2 PRODUCTS

2.1 COLOR SCHEDULE

The color schedule information provided in the following paragraphs lists the colors, patterns and textures required for exterior and interior finishes, including both factory applied and field applied colors. Where color is shown as being specific to one manufacturer, an equivalent color by another manufacturer may be submitted for approval. Manufacturers and materials specified are not intended to limit the selection of equal colors from other manufacturers. In the case of difference between the drawings and specifications, colors identified in this specification govern.

2.2 EXTERIOR FINISHES

Not used.

2.3 INTERIOR FINISHES

2.3.1 Interior Floor Finishes

Provide flooring materials to match the colors listed below.

2.3.1.1 Concrete (Paint)

2.3.1.2 Industrial Floor Coating

2.3.2 Interior Base Finishes

Provide base materials to match the colors listed below.

2.3.2.1 Resilient Base and Moldings

2.3.2.2 Integral Cove Base

2.3.2.3 Paint

2.3.3 Interior Wall Finishes

Not used.

2.3.4 Interior Ceiling Finishes

Not used.

2.3.5 Interior Trim

Provide interior trim to match the colors listed below.

2.3.5.1 Metal Stairs

2.3.5.2 Bollards

2.4 PLACEMENT SCHEDULE

Placement of color to be in accordance with the following schedule:

ROOM # AND NAME
FLOOR
BASE
REMARKS

PART 3 EXECUTION

Not Used

-- End of Section --