This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS BLUE RIDGE naval vessel, dated 11-MAR-2025, specifically focused on conducting a tightness and operational test for the Heating System (S/A 80964K - KTR). The TGI involves three primary work tasks: contractor work, quality assurance (QA) work, and support/field (S/F) work, all of which are to accomplish and document the tightness and operational test in accordance with reference document TP 51111-3-300KTR. The document includes administrative details such as preparation by Ishii, Yuuhei and approval by Ohta, Jason Y., with a component number of 51111-3-300KTR and a key operational code of T02.
The TGI is part of a larger naval ship repair and modernization effort for the USS BLUE RIDGE, which involves multiple task group instructions and test phases for ship repair, overhaul, preservation, and replacement work. The work is being conducted in support of the US Naval Ship Repair Facility and Japan Regional Maintenance Center (SRF-JRMC), with an anticipated contractual performance period from 12-Jan-2026 through 12-Jun-2027. The specific heating system test described in this TGI represents one small component of the comprehensive ship maintenance and modernization project.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
11-MAR-2025 1554
20.14.15.2.9020 (September 2024) ICN: 3819P51206 KeyOp: T02
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51111-3-300KTR TT T 7 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 51111
CU PHASE TITLE: HEATING SYS (T & OP), S/A 80964K - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EXSAZC04
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
ISHII, YUUHEI 246.2 3152434302 24-FEB-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 10-MAR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSA-ZC04
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
512G0006
Tightness & Operational Test for Heating System S/A 80964K - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
11-MAR-2025 1554
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P51206 KeyOp: T02
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51111-3-300KTR TT T 7 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 51111
CU PHASE TITLE: HEATING SYS (T & OP), S/A 80964K - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 51111-3-300KTR HEATING SYSTEM (T & OP) -
KTR
LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 51111-3-300KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 51111-3-300KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 51111-3-300KTR.
/ EXSA N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P51206 KEY OP: T02