TGI_3819P14113A01_c0v0.pdf
PDF 2 MB Posted
- Solicitation number
- N6264925RA024
About this file
This Task Group Instruction (TGI) details repair and preservation work for deck plating on the USS Blue Ridge (LCC-19), specifically focusing on two areas: the Fifth Deck in 6-76-2-A (Frames between 81 and 82, Port) and the First Platform in 6-76-2-A. The work involves weld repair of mechanical damage, including drilling 1/2-inch holes, countersinking, conducting air hose tests, and performing preservation tasks on new and disturbed surfaces.
The project is scheduled for contractor work from January 12, 2026, to May 15, 2027, with the Naval Ship Repair Facility-Japan Regional Maintenance Center (SRF-JRMC) providing support services including crane rigging, utility services, safety inspections, and on-site engineering support for weld repair. The work requires special attention to fire zone boundaries, necessitating the fabrication and staging of a non-flammable closure. The total work area comprises approximately one lot of deck plating on the Fifth Deck and 414 square feet on the First Platform, with potential lead hazards noted in the initial conditions.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
24-AUG-2024 0828
20.14.15.0.8993 (August 2024) ICN: 3819P14113 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: DK PLTG IN 6-76-2-A AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: F/O - ACCOMPLISH REPAIR & PRESERVATION OF DECK PLATING IN 6-76-2-A
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 4
ES01NPJC * ES01NPJD
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
ASHINA, TAKAAKI 231B 3152434370 16-APR-2024
APPROVED BY: CODE: PHONE: DATE:
TAKAGI, RYOUTA 231B 3152434502 16-APR-2024
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
ES01-NPJC * ES01-NPJD
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
141A0013
1. SCOPE/PURPOSE:
1.1 Title: Repair and Preservation of Deck Plating in 6-76-2-A; accomplish
1.2 Location of Work:
1.2.1 B Division Storeroom (6-76-2-A)
1.2.2 ER09 Office (5-79-2-Q)
1.3 Identification:
1.3.1 Quantity (One Lot), Deck Plating, Fifth Deck in 6-76-2-A, Frames between 81 and 82, Port
Base Material: OS, MIL-S-22698 GR-A, 12.75 LBs Plate Remarks: See Sketch Enclosure-01 for location detail
JCN: ES01-NPJD
TGI Short Form
24-AUG-2024 0828
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14113 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: DK PLTG IN 6-76-2-A AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: F/O - ACCOMPLISH REPAIR & PRESERVATION OF DECK PLATING IN 6-76-2-A
FOUO Pg 2 of 4
CU PHASE DESCRIPTION (Cont.)
1.3.2 Quantity (414 SF), Entire Deck Plating, First Platform in 6-76-2-A, including vertical surface up to height of 6 inches from deck and manhole cover plates and air vent hose connection (AVHC) cover plate, Port
Remarks: The area excepts where compartment insulation is installed.
JCN: ES01-NPJC
1.4 Security Classification: None.
1.5 Initial Condition:
1.5.1 Potential Lead Hazard
1.6 Contractor Work start date: 1/12/2026
1.7 Contractor Work completion date: 5/15/2027
2. PROCEDURE:
2.1 Accomplish weld repair of mechanical damage on each existing deck plating listed in 1.3.1, using Ref. No. 3 for guidance.
See 2.6.7.
2.1.1 Drill 1/2 inch diameter hole on each deck plating.
2.1.1.1 Shape remaining hole to minimum 20 degrees countersink.
2.1.2 Accomplish the requirements of 009-12 of Ref. No. One, including Table 2, Column(s) A, Lines One through 7.
2.1.3 Accomplish the requirements of 009-25 of Ref. No. One for a local air hose test of each new weld of the deck plating.
Allowable leakage: None.
2.2 Accomplish the requirements of 009-32 of Ref. No. One, including Table 3, Line(s) 6, for each area listed in 1.3.2.
2.3 Accomplish the requirements of 009-32 of Ref. No. One for each new and disturbed surface.
2.4 Notes:
2.4.1 Planner: Code 231B T. Ashina, 243-4370
Engineer: Code 250 J. Igarashi, 243-4230
2.4.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
2.4.3 This TGI clears DFS LCC-19-1017-2024 in its entirety.
2.4.4 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper
24-AUG-2024 0828
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14113 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: DK PLTG IN 6-76-2-A AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: F/O - ACCOMPLISH REPAIR & PRESERVATION OF DECK PLATING IN 6-76-2-A
FOUO Pg 3 of 4
CU PHASE DESCRIPTION (Cont.)
air flow onboard the ship.
2.4.5 JCNs ES01-NPJC and ES01-NPJD are related to this TGI.
2.5 Government Furnished Material (GFM): None.
2.6 SRF-JRMC will provide the following service work: (TGI No. 3819P14113S02)
2.6.1 [C740] Crane and crane rigging service.
2.6.2 [X99E] Utility service, electrical.
2.6.3 [X99M] Utility service, including low pressure air supply, water supply, and steam supply.
2.6.4 [C106.1] Safety inspection for SRF-JRMC employees.
2.6.5 [C106.2] Gas free inspection for SRF-JRMC employees.
2.6.6 [C133] QA inspection for (G) symbol(s).
2.6.7 [C250] On-site engineering support for weld repair.
24-AUG-2024 0828
20.14.15.0.8993 (August 2024) (Continued) ICN: 3819P14113 KeyOp: A01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: DK PLTG IN 6-76-2-A AY A 0 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P
CU PHASE TITLE: F/O - ACCOMPLISH REPAIR & PRESERVATION OF DECK PLATING IN 6-76-2-A
FOUO Pg 4 of 4
OTHER SPECIAL REQUIREMENTS:
This work affects a fire zone boundary. Fabrication and/or staging of a non-flammable closure is required.
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N 3 DWG 104-2491048 5th Deck PLTG FR51-1/2 -
FR102-1/4
M Y ALL
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
2.1 SFTR HRs, WELD HRs, PNTR HRs, RGRS HRs, CARP HRs, QA HRs
22/KE PC N
2.2 PNTR HRs, SMTL HRs, SFTR HRs, QA HRs 22/KE PC N
2.3 PNTR HRs, QA HRs 22/KE PC N
Structure Work CFM: $ for firewatch cost, air compressor rental cost and fuel oil cost for air hose test, and misc such as electrode, covering materials, gases, and other consumable.
22/MQ CS N
Preservation Work CFM: $ for all paints, thinner, lead analysis cost, slip-resistant self adhesive tread, and misc such as covering material, temporary closure, and other consumable.
22/MQ CS N
Process Funding Document 10/CT OM N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
ATTACHMENT LIST
TITLE FILE NAME SAVED DATE
ENCLOSURE-01 3819P14113A01-Sketch.pdf 15-APR-2024 0000
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P14113 KEY OP: A01
Takaaki.Ashina.ja Text Box
LOCATION DETAIL FOR WELD REPAIR
Takaaki.Ashina.ja_1 Text Box
Takaaki.Ashina.ja_2 Text Box
PLAN VIEW
FIRST PLATFORM FR 76 - 86
PORT
Takaaki.Ashina.ja_3 Line
Takaaki.Ashina.ja_4 Text Box 3819P14113A01
Takaaki.Ashina.ja_5 Line
Takaaki.Ashina.ja_6 Text Box
SKETCH
ENCLOSURE-01
Takaaki.Ashina.ja_7 Text Box Sheet 1 of 1
Takaaki.Ashina.ja_8 Line
Takaaki.Ashina.ja_9 Line
Takaaki.Ashina.ja_10 Text Box
FR 83
Takaaki.Ashina.ja_11 Text Box
FR 79
Takaaki.Ashina.ja_12 Text Box
FR 76
Takaaki.Ashina.ja_13 Text Box
FR 86
Takaaki.Ashina.ja_14 Line
Takaaki.Ashina.ja_15 Text Box
FWD
Takaaki.Ashina.ja_16 Text Box
LONG BHD
Takaaki.Ashina.ja_17 Text Box
SHELL
Takaaki.Ashina.ja_18 Line
Takaaki.Ashina.ja_19 Rectangle
Takaaki.Ashina.ja_20 Text Box 6'-3"
Takaaki.Ashina.ja_21 Line
Takaaki.Ashina.ja_22 Text Box 28"
Takaaki.Ashina.ja_23 Text Box
DETAIL 1-B
Takaaki.Ashina.ja_24 Line
Takaaki.Ashina.ja_25 Rectangle
Takaaki.Ashina.ja_26 Text Box
B DIVISION STOREROOM (6-76-2-A)
Takaaki.Ashina.ja_27 Text Box
TRANSV BHD
Takaaki.Ashina.ja_28 Text Box
TRANSV BHD
Takaaki.Ashina.ja_29 Text Box
:MECHANICAL DAMAGE
Takaaki.Ashina.ja_30 Rectangle
Takaaki.Ashina.ja_31 Line
Takaaki.Ashina.ja_32 Line
Takaaki.Ashina.ja_33 Text Box
FIRE ROOM (8-76-0-E)
Takaaki.Ashina.ja_34 Line
Takaaki.Ashina.ja_35 Text Box
DETAIL 1-B
INVERTED VIEW
FIFTH DECK PLATING IN 6-76-2-A
Takaaki.Ashina.ja_36 Line
Takaaki.Ashina.ja_37 Oval
Takaaki.Ashina.ja_38 Text Box
MECHANICAL DAMAGE
Takaaki.Ashina.ja_39 Line
Takaaki.Ashina.ja_40 Text Box
FWD
Takaaki.Ashina.ja_41 Line
Takaaki.Ashina.ja_42 Text Box
:MECHANICAL DAMAGE
Takaaki.Ashina.ja_43 Oval
Takaaki.Ashina.ja_44 Rectangle
Takaaki.Ashina.ja_45 Line