TE-04 Project Schedule Example.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- Solicitation for Protective Coatings Federal contract opportunity
- Solicitation number
- W911S825BA015
- Issued by
- Department of the Army
About this file
The provided file is a Project Schedule Example spreadsheet for a Department of the Army solicitation for Protective Coatings IDIQ contract at Joint Base Lewis-McChord (JBLM), Washington. The contract will support Public Works activities through individual Task Orders (TOs) for maintenance, repair, and minor protective coatings construction work. The IDIQ contract requires the contractor to provide all materials, equipment, and personnel to complete construction tasks, with a company representative located near JBLM to manage proposal preparation, negotiation, and contract correspondence.
The spreadsheet contains two example project schedules demonstrating potential contract execution timelines, with CLINs (Contract Line Item Numbers) broken down into preconstruction activities, major work locations, and closeout phases. Each example schedule spans approximately 14-39 days, with percentage allocations for different work stages ranging from 5% to 40% of total project completion. The solicitation (W911S825BA015) indicates that Task Orders will vary in size and may include incidental disciplines necessary for protective coatings actions, with the contractor expected to be fully equipped to handle diverse construction requirements at JBLM and supported organizations.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Example #1
| Example Project Schedule | ||
| Contract #: W911S8-20-D-XXX | Project Title: ______ | |
| Task Order #: _______________ |
| Days/Weeks | ||||||||||||||||||
| SOVs | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | |||
| CLIN XXXXAA: Preconstruction Activities | 12.00% | |||||||||||||||||
| Action 1 | 7.00% | |||||||||||||||||
| Action 2 | 5.00% | |||||||||||||||||
| CLIN XXXXAA: Major Location/Item of Work | 40.00% | |||||||||||||||||
| Action 1 | 15.00% | |||||||||||||||||
| Action 2 | 25.00% | |||||||||||||||||
| CLIN XXXXAB: Major Location/Item of Work | 35.00% | |||||||||||||||||
| Action 1 | 17.00% | |||||||||||||||||
| Action 2 | 15.00% | |||||||||||||||||
| Action 3 | 3.00% | |||||||||||||||||
| CLIN XXXXAB: Major Location/Item of Work | 8.00% | |||||||||||||||||
| Action 1 | 8.00% | |||||||||||||||||
| CLIN XXXXAB: Closeout | 5.00% | |||||||||||||||||
| Total: | 100.00% |
Example #2
| Project Schedule | Contract: W911S8-XX-D-00XX | ||||
| Project Number: XXXXX | |||||
| Project Title: Example | |||||
| CLIN | Work Activities | Start Date | Completion Date | Total Days | SOVs |
| CLIN AA | Preconstruction Activities | 9/1/19 | 9/15/19 | 14 | 12% |
| CLIN AA | Major Location/Item of Work | 9/16/19 | 10/25/19 | 39 | 30% |
| CLIN AB | Major Location/Item of Work | 10/26/19 | 11/5/19 | 10 | 35% |
| CLIN AB | Major Location/Item of Work | 11/6/19 | 12/1/19 | 25 | 18% |
| CLIN AB | Closeout | 12/2/19 | 12/16/19 | 14 | 5% |
| Total: | 100% |