Summary of Work.pdf

PDF 306 KB Posted

Attached to
Circuit 680 UG Cable Replacement Construction Services
Solicitation number
1412223678
Issued by
Duval County, Florida

About this file

This is a Summary of Work document for the City of Jacksonville's Circuit 680 UG Cable Replacement Construction Services project, managed by JEA (Jacksonville Electric Authority). The project involves the replacement of approximately 1,200 feet of 69 kV underground transmission cable originating from the Dillion Substation, with work occurring both within the substation and generation facility and within the City of Jacksonville right-of-way along Talleyrand Avenue and Wigmore Street. The scope of work includes installation of an open-cut, concrete-encased duct bank; installation of a horizontal directional drilling (HDD) duct bank; pulling and installation of 69 kV EPR cable; modifications to an overhead transmission riser pole and substation termination structures; removal of existing direct-buried 69 kV cable; site restoration; and maintenance of traffic. A mandatory pre-response meeting is scheduled for October 5, 2026, with a solicitation due date of October 27, 2026. The contractor must submit pre-construction submittals for engineer approval and coordinate with the JEA Project Manager regarding sequence of work, means of access, material storage space, and corridor use.

The contractor is responsible for all material and equipment procurement, with JEA providing no furnishings. The contractor must remove as much of the existing 2000kcmil 69kV cable as feasible and coordinate its pickup with the JEA project manager, with any remaining cable cut into 5-foot sections and returned. Existing lightning arrestors, terminators, and miscellaneous equipment must be removed and disposed of off JEA/City property. The contractor must obtain digging permits prior to excavation, contact local utility locating services at least 48 hours before excavating, and notify the JEA Project Manager 48 hours prior to starting excavation work. A qualified Environmental Health and Safety Coordinator with current OSHA HAZWOPER training listed on the JEA RBL must be provided to ensure compliance with site health and safety requirements, monitor work conditions, and maintain authority to stop work if necessary.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 11 00

SUMMARY OF WORK

08/26

1. GENERAL

1.1. Submittals: Engineer approval is required for submittals. Submit the following in accordance with Section 01

33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

1.2. Work Covered by Contract Documents:

1.2.1. Project Description: The work includes underground transmission installation and incidental related work.

1.3. Occupancy of Premises: Before work is started, arrange with the JEA Project Manager a sequence of procedure, means of access, space for storage of materials and equipment, and use of corridors.

1.4. Existing Work: The Contractor shall take all steps necessary to prevent damage to or interference with existing power lines, communication facilities, roadways, waterways, buried cables, pipelines, drainage structures, or other facilities adjacent to the project construction.

1.4.1. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

1.4.2. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the JEA Project Manager. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.4.3. Environmental Requirements

1.4.3.1. Contractor shall provide a competent professional defined as a practicing environmental scientist or engineer with current Title 29 of the Code of Federal Regulations (29 CFR) Part 1910.120 (OSHA HAZWOPER) training, as the Environmental Health and Safety Coordinator (EH&S Coordinator) for the purpose of assuring and documenting compliance with this SGMP. The qualified professional must also be on the JEA RBL WE-11. The EH&S Coordinator shall brief employees on the hazards associated with the potential exposure and components of the SGMP. The EH&S Coordination shall also be on-Site during work activities to monitor work conditions and workspace for potential exposures to Site contaminants and assisting with the field screening, sampling, and proper disposition of excavated soil and recovered groundwater, if any.

Workers must be provided Site-specific health and safety training compliant with Federal and State requirements relative to work in areas where incidental contact with potentially contaminated soil, groundwater, and/or air may occur. The EH&S Coordinator shall have the authority to stop any and all work and require contractors to implement modifications to their work and/or perform additional measures to ensure compliance with this SGMP.

1.5. Location of Underground Utilities: Obtain digging permits prior to start of excavation and comply with Installation requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.

Verify existing utility locations indicated on contract drawings, within area of work.

1.5.1. Notification Prior to Excavation: Notify the JEA Project Manager at least 48 hours prior to starting excavation work.

1.6. Owner Material and Equipment: JEA will not furnish any materials and equipment for installation by the Contractor.

1.7. Salvage Material and Equipment: The Contractor shall remove as much of the existing 2000kcmil 69kV cable as feasible. Coordinate pick up with the JEA project manager. Any additional cable left on the cable reels after pulling, shall be cut into 5' sections to be returned to the JEA Project Manager. The contractor shall remove the existing lightning arrestors, terminators, and miscellaneous equipment and dispose of off of JEA/City property.

1.8.

2. PRODUCTS

Not Used

3. EXECUTION

Not Used