33 71 02.00 Underground Electrical Transmission.pdf
PDF 413 KB Posted
- Solicitation number
- 1412223678
- Issued by
- Duval County, Florida
About this file
This is a technical specification document for Underground Electrical Transmission work issued by JEA (Jacksonville Electric Authority) in Florida, detailing standards and requirements for the Circuit 680 UG Cable Replacement Construction Services project. The specification establishes comprehensive technical requirements for installation of approximately 1,200 feet of 69 kV underground cable originating from the Dillon Substation, with work occurring within the substation, generation facility, and the City of Jacksonville right-of-way along Talleyrand Avenue and Wigmore Street. The scope includes open-cut concrete-encased duct bank installation, horizontal directional drilling (HDD) duct bank installation, pulling and installation of 69 kV EPR cable, modifications to overhead transmission riser poles and substation termination structures, removal of existing direct-buried 69 kV cable, site restoration, and traffic maintenance. A mandatory pre-response meeting is scheduled for October 5, 2026, with solicitation responses due October 27, 2026.
The specification incorporates extensive industry standards and codes including NFPA 70, IEEE C2, ASTM standards, NEMA specifications, and ACI requirements to govern all materials, equipment, and installation methods. All materials including copper conductors, PVC and HDPE conduit, precast concrete structures, and cable support systems must meet stringent quality assurance requirements with two years of satisfactory commercial use prior to bid opening, or alternatively 6,000 hours of documented field operation. The contractor must submit detailed shop drawings, product data, test reports, cable installation plans with pulling calculations, installer qualifications, and directional boring certifications. Cable installation requires manufacturer-approved lubricants and procedures, compliance with specified bending radii and pulling tensions, fireproofing of cables rated 2200 volts or higher, grounding systems with earth resistance not exceeding 10 ohms, and comprehensive field acceptance testing including visual inspections and electrical tests per NETA ATS standards. All work must comply with IEEE 81 grounding system testing and manufacturer recommendations throughout installation and commissioning.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 33 71 02.00
UNDERGROUND ELECTRICAL TRANSMISSION
08/26
1. GENERAL
1.1. REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS (AASHTO)
AASHTO HB-17 (2002; Errata 2003; Errata 2005, 17th Edition)
Standard Specifications for Highway Bridges
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 318M (2014; ERTA 2015) Building Code Requirements for
Structural Concrete & Commentary
ACI SP-66 (2004) ACI Detailing Manual AMERICAN
WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020) Structural Welding Code - Steel ASSOCIATION OF
EDISON ILLUMINATING COMPANIES (AEIC)
AEIC CS9 (2013) Specification for Extruded Insulation Power Cables and Their Accessories Rated Above 46kV thru 345kV
ASTM INTERNATIONAL (ASTM)
ASTM A48/A48M (2003; R 2012) Standard Specification for Gray Iron Castings
ASTM B1 (2013) Standard Specification for Hard-Drawn Copper
Wire
ASTM B3 (2013) Standard Specification for Soft or Annealed Copper Wire
ASTM B8 (2011; R 2017) Standard Specification for Concentric-Lay-Stranded Copper Conductors, Hard, Medium-Hard, or Soft
ASTM C857 (2016) Standard Practice for Minimum Structural Design Loading for Underground Precast Concrete Utility Structures
ASTM C990 (2009; R 2014) Standard Specification for Joints for Concrete Pipe, Manholes and Precast Box Sections Using Preformed Flexible Joint Sealants
ASTM F512 (2019) Standard Specification for Smooth-Wall Poly (Vinyl
Chloride) (PVC) Conduit and Fittings for Underground Installation
ASTM F2160 (2016) Standard Specification for Solid Wall High Density
Polyethylene (HDPE) Conduit Based on Controlled Outside Diameter (OD)
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 48 (2009) Standard for Test Procedures and Requirements for
Alternating-Current Cable Terminations Used on Shielded Cables Having Laminated Insulation Rated 2.5 kV through 765 kV or Extruded Insulation Rated 2.5 kV through 500 kV
IEEE 81 (2012) Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System
IEEE 386 (2016) Separable Insulated Connector Systems for Power Distribution Systems Rated 2.5 kV through 35 kV
IEEE 400.2 (2013) Guide for Field Testing of Shielded Power Cable Systems
Using Very Low Frequency (VLF)
IEEE 404 (2012) Standard for Extruded and Laminated Dielectric Shielded Cable Joints Rated 2500 V to 500,000 V
IEEE C2 (2017; Errata 1-2 2017; INT 1 2017) National Electrical Safety Code
IEEE Stds Dictionary (2009) IEEE Standards Dictionary: Glossary of Terms & Definitions
INSULATED CABLE ENGINEERS ASSOCIATION (ICEA)
ICEA S-108-720 (2013) Standard for Extruded Insulation Power Cables Rated Above 46kV through 500kV AC
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2017; Errata 2017) Standard for Acceptance Testing
Specifications for Electrical Power Equipment and Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI C119.1 (2016) Electric Connectors - Sealed Insulated Underground Connector Systems Rated 600 Volts
NEMA C119.4 (2011) Electric Connectors - Connectors for Use Between Aluminum-to-Aluminum or Aluminum-to-Copper Conductors Designed for Normal Operation at or Below 93 Degrees C and Copper-to-Copper Conductors Designed for Normal Operation at or Below 100 Degrees C
NEMA RN 1 (2005; R 2013) Polyvinyl-Chloride (PVC) Externally Coated
Galvanized Rigid Steel Conduit and Intermediate Metal Conduit
NEMA TC 2 (2013) Standard for Electrical Polyvinyl Chloride (PVC) Conduit
NEMA TC 3 (2016) Polyvinyl Chloride (PVC) Fittings for Use With Rigid PVC Conduit and Tubing
NEMA TC 6 & 8 (2013) Standard for Polyvinyl Chloride (PVC) Plastic Utilities
Duct for Underground Installations
NEMA TC 7 (2016) Smooth-Wall Coilable Electrical Polyethylene Conduit
NEMA TC 9 (2004) Standard for Fittings for Polyvinyl Chloride (PVC) Plastic Utilities Duct for Underground Installation
NEMA WC 70 (2009) Power Cable Rated 2000 V or Less for the Distribution of
Electrical Energy--S95-658
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2019; TIA 19-1; TIA 19-2; TIA 19-3; TIA 19-4; ERTA 1 2019)
National Electrical Code
SOCIETY OF CABLE TELECOMMUNICATIONS ENGINEERS (SCTE)
ANSI/SCTE 77 (2013) Specification for Underground Enclosure Integrity
TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)
TIA-758 (2012b) Customer-Owned Outside Plant Telecommunications Infrastructure Standard
U.S. DEPARTMENT OF AGRICULTURE (USDA)
RUS Bull 1751F-644 (2002) Underground Plant Construction
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
CID A-A-60005 (Basic; Notice 2) Frames, Covers, Gratings, Steps, Sump And Catch Basin, Manhole
UNDERWRITERS LABORATORIES (UL)
UL 6 (2007; Reprint Sep 2019) UL Standard for Safety Electrical Rigid Metal
Conduit-Steel
UL 44 (2018) UL Standard for Safety Thermoset-Insulated Wires and Cables
UL 83 (2017) UL Standard for Safety Thermoplastic-Insulated Wires and
Cables
UL 94 (2013; Reprint Sep 2017) UL Standard for Safety Tests for Flammability of Plastic Materials for Parts in Devices and Appliances
UL 467 (2013; Reprint Jun 2017) UL Standard for Safety Grounding and
Bonding Equipment
UL 486A-486B (2018) UL Standard for Safety Wire Connectors
UL 510 (2017) UL Standard for Safety Polyvinyl Chloride, Polyethylene and Rubber Insulating Tape
UL 514B (2012; Reprint Nov 2014) Conduit, Tubing and Cable Fittings
UL 651 (2011; Reprint Nov 2018) UL Standard for Safety Schedule 40, 80, Type EB and A Rigid PVC Conduit and Fittings
UL 854 (2020) Standard for Service-Entrance Cables
UL 1242 (2006; Reprint Mar 2014) Standard for Electrical Intermediate
Metal Conduit -- Steel
1.2. RELATED REQUIREMENTS
Sections 26 05 13.00 00 69kV Transmission Cable, 33 05 23.13 Utility Horizontal Directional Drilling applies to this section, with the additions and modifications specified herein.
1.3. DEFINITIONS
a. Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, are as defined in IEEE Stds Dictionary.
b. In the text of this section, the words conduit and duct are used interchangeably and have the same meaning.
1.4. SUBMITTALS
Engineer approval is required for all submittals. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Copper conductors Submit modified drawings and engineering calculations associated with design changes required for use of aluminum conductors.
Precast underground structures
SD-03 Product Data
Precast concrete structures
Sealing Material
Pulling-In Irons
Manhole frames and covers
Cable supports (racks, arms and insulators)
SD-06 Test Reports
Cable Installation Plan and Procedure
One copy of the information described below in 8-1/2 by 11-inch binders having a minimum of three rings from which material may readily be removed and replaced, including a separate section for each cable pull. Separate sections by heavy plastic dividers with tabs, with all data sheets signed and dated by the person supervising the pull.
a. Site layout drawing with cable pulls numerically identified.
b. A list of equipment used, with calibration certifications. The manufacturer and quantity of lubricant used on pull.
c. The cable manufacturer and type of cable.
d. The dates of cable pulls, time of day, and ambient temperature.
e. The length of cable pull and calculated cable pulling tensions.
f. The actual cable pulling tensions encountered during pull.
SD-07 Certificates
Cable Installer Qualifications
Directional Boring Certificate of Conformance
1.5. QUALITY ASSURANCE
1.5.1. Precast Underground Structures
Submittal required for each type used. Provide calculations and drawings for precast manholes and handholes bearing the seal of a registered professional engineer including:
a. Material description (i.e., f'c and Fy)
b. Manufacturer's printed assembly and installation instructions
c. Design calculations
d. Reinforcing shop drawings in accordance with ACI SP-66
e. Plans and elevations showing opening and pulling-in iron locations and details
1.5.2. Certificate of Competency for Cable Splicer/Terminator
See 26 05 13.00 00 69kV Transmission Cables for requirements.
1.5.3. Cable Installer Qualifications
See 26 05 13.00 00 69kV Transmission Cables for requirements.
1.5.4. Directional Boring Certificate of Conformance
Provide certification of compliance with the registered Professional Engineer's design requirements for each directional bore, including: HDPE conduit size and type, bend radius, elevation changes, vertical and horizontal path deviations, conductor size and type and any conductor derating due to depth of conduit.
Record location and depth of all directional-bore installed HDPE conduits using Global Positioning System (GPS) recording means with "resource grade" accuracy.
1.5.5. Regulatory Requirements
In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "must" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the JEA Project Manager. Equipment, materials, installation, and workmanship must be in accordance with the mandatory and advisory provisions of IEEE C2 and NFPA 70 unless more stringent requirements are specified or indicated.
1.5.6. Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship. Products must have been in satisfactory commercial or industrial use for 2 years prior to bid opening. The 2-year period must include applications of equipment and materials under similar circumstances and of similar size. The product must have been for sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period. Where two or more items of the same class of equipment are required, these items must be products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.
1.5.6.1. Alternative Qualifications
Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.5.6.2. Material and Equipment Manufacturing Date
Products manufactured more than 3 years prior to date of delivery to site are not acceptable, unless specified otherwise.
2. PRODUCTS
2.1. CONDUIT, DUCTS, AND FITTINGS
2.1.1. Plastic Conduit for Direct Burial and Riser Applications
UL 651 and NEMA TC 2, Schedule 40 or Schedule 80 as indicated.
2.1.2. High Density Polyethylene (HDPE) Electrical Conduit for Directional Boring
See Specification 35 05 23.13 Utility Horizontal Directional Drilling.
2.1.3. Duct Sealant
UL 94, Class HBF. Provide high-expansion urethane foam duct sealant that expands and hardens to form a closed, chemically and water resistant, rigid structure. Sealant must be compatible with common cable and wire jackets and capable of adhering to metals, plastics and concrete. Sealant must be capable of curing in temperature ranges of 35 degrees F to 95 degrees F. Cured sealant must withstand temperature ranges of -20 degrees F to 200 degrees F without loss of function.
2.1.4. Fittings
2.1.4.1. PVC Conduit Fittings
UL 514B, UL 651.
2.1.4.2. PVC Duct Fittings
NEMA TC 9.
2.2. LOW VOLTAGE INSULATED CONDUCTORS AND CABLES
Insulated conductors must be rated 600 volts and conform to the requirements of NFPA 70, including listing requirements. Wires and cables manufactured more than 12 months prior to date of delivery to the site are not acceptable.
2.2.1. Conductor Types
Cable and duct sizes indicated are for copper conductors and THHN/THWN unless otherwise noted.
Conductors No. 10 AWG and smaller must be solid. Conductors No. 8 AWG and larger must be stranded. All conductors must be copper.
2.2.2. Conductor Material
Unless specified or indicated otherwise or required by NFPA 70, wires in conduit, other than service entrance, must be 600-volt, Type THWN/THHN conforming to UL 83. Copper conductors must be annealed copper complying with ASTM B3 and ASTM B8.
2.2.3. In Duct
2.2.4. Cable Marking
Insulated conductors must have the date of manufacture and other identification imprinted on the outer surface of each cable at regular intervals throughout the cable length.
2.3. TAPE
2.3.1. Insulating Tape
UL 510, plastic insulating tape, capable of performing in a continuous temperature environment of 80 degrees C.
2.3.2. Buried Warning and Identification Tape
Provide detectable tape in accordance with Section 31 23 00.00 20 EXCAVATION AND FILL.
2.3.3. Fireproofing Tape
Provide tape equivalent to 3M 77-WHITE-3"X20'.
2.4. PULL ROPE
Plastic or flat pull line (bull line) that exceeds the contractors calculated tensions.
2.5. GROUNDING AND BONDING
2.5.1. Driven Ground Rods
Provide copper-clad steel ground rods conforming to UL 467 not less than 3/4 inch in diameter by 10 feet in length.
2.5.2. Grounding Conductors
Stranded-bare copper conductors must conform to ASTM B8, Class B, soft-drawn unless otherwise indicated.
Insulated conductors must be of the same material as phase conductors, except that conductors must be rated no more than 600 volts. Aluminum is not acceptable.
2.6. UNDERGROUND STRUCTURES
Provide precast concrete underground structures as indicated, conforming to ASTM C857 and ASTM C478. Top, walls, and bottom must consist of reinforced concrete. Walls and bottom must be of monolithic concrete construction.
Locate duct entrances and windows near the corners of structures to facilitate cable racking. Covers must fit the frames without undue play. Form steel and iron to shape and size with sharp lines and angles. Castings must be free from warp and blow holes that may impair strength or appearance. Exposed metal must have a smooth finish and sharp lines and arises. Provide necessary lugs, rabbets, and brackets. Set pulling-in irons and other built-in items in place before depositing concrete. Install a pulling-in iron in the wall opposite each duct line entrance. Cable racks, including rack arms and insulators, must be adequate to accommodate the cable.
2.6.1. Precast Concrete Structures, Risers and Tops
Precast units must be the product of a manufacturer regularly engaged in the manufacture of precast concrete products, including precast manholes.
2.6.1.1. General
Structures must be identified with the manufacturer's name embedded in or otherwise permanently attached to an interior wall face.
2.6.1.2. Design for Precast Structures
ACI 318M. Design for the following soil parameters/site conditions:
a. Vertical design loads must include full dead, superimposed dead, and live loads including a 30 percent magnification factor for impact. Live loads must consider all types and magnitudes of vehicular (automotive, industrial, or aircraft) traffic to be encountered. The minimum design vertical load must be for H20 highway loading per AASHTO HB-17.
b. Horizontal design loads must include full geostatic and hydrostatic pressures for the soil parameters, water table, and depth of installation to be encountered. Also, horizontal loads imposed by adjacent structure foundations, and horizontal load components of vertical design loads, including impact, must be considered, along with a pulling-in iron design load of 6000 pounds.
c. Each structural component must be designed for the load combination and positioning resulting in the maximum shear and moment for that particular component.
d. Design must also consider the live loads induced in the handling, installation, and backfilling of the manholes. Provide lifting devices to ensure structural integrity during handling and installation.
2.6.1.3. Construction
See drawings for details. Structure top, bottom, and wall must be of a uniform thickness of not less than 6 inches. Thin-walled knock-out panels for designed or future duct bank entrances are not permitted.
Provide quantity, size, and location of duct bank entrance windows as directed, and cast completely open by the precaster. Size of windows must exceed the nominal duct bank envelope dimensions by at least 12 inches vertically and horizontally to preclude in-field window modifications made necessary by duct bank misalignment. However, the sides of precast windows must be a minimum of 6 inches from the inside surface of adjacent walls, floors, or ceilings. Form the perimeter of precast window openings to have a keyed or inward flared surface to provide a positive interlock with the mating duct bank envelope.
Provide welded wire fabric reinforcing through window openings for in-field cutting and flaring into duct bank envelopes. Provide additional reinforcing steel comprised of at least two No. 4 bars around window openings. Provide drain sumps a minimum of 12 inches in diameter and 4 inches deep for precast structures.
2.6.1.4. Joints
Provide tongue-and-groove joints on mating edges of precast components. Shiplap joints are not allowed. Design joints to firmly interlock adjoining components and to provide waterproof junctions and adequate shear transfer. Seal joints watertight using preformed plastic strip conforming to ASTM C990.
Install sealing material in strict accordance with the sealant manufacturer's printed instructions. Provide waterproofing at conduit/duct entrances into structures, and where access frame meets the top slab, provide continuous grout seal.
2.6.2. Manhole Frames and Covers
Provide cast iron frames and covers for manholes conforming to CID A-A-60005. Cast the words "ELECTRIC" or in the top face of manhole covers.
2.7. CABLE SUPPORTS (RACKS, ARMS, AND INSULATORS)
The metal portion of racks and arms must be zinc-coated after fabrication.
2.7.1. Cable Rack Stanchions
Cable Rack Stanchions as required by the Contract Drawings.
2.7.2. Rack Arms
Cable rack arms must be steel.
2.7.3. Insulators
Insulators for metal rack arms must be dry-process glazed porcelain.
2.8. CABLE TAGS IN MANHOLES
Provide tags for each power cable located in manholes. The tags must be polyethylene. Do not provide handwritten letters. See detail in Construction drawings.
2.8.1. Polyethylene Cable Tags
Provide tags of polyethylene in accordance with Section 26 05 13.00 00 69Kv Cables.
2.9. SOURCE QUALITY CONTROL
2.9.1. Arc-Proofing Test for Cable Fireproofing Tape
Manufacturer must test one sample assembly consisting of a straight lead tube 12 inches long with a 2 1/2 inch outside diameter, and a 1/8-inch-thick wall, and covered with one-half lap layer of arc and fireproofing tape per manufacturer's instructions. The arc and fireproofing tape must withstand extreme temperature of a high-current fault arc 13,000 degrees K for 70 cycles as determined by using an argon directed plasma jet capable of constantly producing and maintaining an arc temperature of 13,000 degrees K. Temperature (13,000 degrees K) of the ignited arc between the cathode and anode must be obtained from a dc power source of 305 (plus or minus 5) amperes and 20 (plus or minus 1) volts. The arc must be directed toward the sample assembly accurately positioned 5 (plus or minus 1) millimeters downstream in the plasma from the anode orifice by fixed flow rate of argon gas (0.18 g per second). Each sample assembly must be tested at three unrelated points.
Start time for tests must be taken from recorded peak current when the specimen is exposed to the full test temperature. Surface heat on the specimen prior to that time must be minimal. The end point is established when the plasma or conductive arc penetrates the protective tape and strikes the lead tube. Submittals for arc-proofing tape must indicate that the test has been performed and passed by the manufacturer.
3. EXECUTION
3.1. INSTALLATION
Install equipment and devices in accordance with the manufacturer's published instructions and with the requirements and recommendations of NFPA 70 and IEEE C2 as applicable.
3.2. CABLE INSPECTION
Inspect each cable reel for correct storage positions, signs of physical damage, and broken end seals prior to installation. If end seal is broken, remove moisture from cable prior to installation in accordance with the cable manufacturer's recommendations.
3.3. CABLE INSTALLATION PLAN AND PROCEDURE
Obtain from the manufacturer an installation manual or set of instructions which addresses such aspects as cable construction, insulation type, cable diameter, bending radius, cable temperature limits for installation, lubricants, coefficient of friction, conduit cleaning, storage procedures, moisture seals, testing for and purging moisture, maximum allowable pulling tension, and maximum allowable sidewall bearing pressure. Perform pulling calculations and prepare a pulling plan and submit along with the manufacturer's instructions in accordance with SUBMITTALS.
Install cable strictly in accordance with the cable manufacturer's recommendations and the approved installation plan.
Calculations and pulling plan must include:
a. Site layout drawing with cable pulls identified in numeric order of expected pulling sequence and direction of cable pull.
b. List of cable installation equipment.
c. Lubricant manufacturer's application instructions.
d. Procedure for resealing cable ends to prevent moisture from entering cable.
e. Cable pulling tension calculations of all cable pulls.
f. Cable percentage conduit fill.
g. Cable sidewall bearing pressure.
h. Cable minimum bend radius and minimum diameter of pulling wheels used.
i. Cable jam ratio.
j. Maximum allowable pulling tension on each different type and size of conductor.
k. Maximum allowable pulling tension on pulling device.
3.4. UNDERGROUND STRUCTURE CONSTRUCTION
Provide precast construction as indicated on Construction Drawings. Horizontal concrete surfaces of floors must have a smooth trowel finish. Manhole locations, as indicated, are approximate.
3.4.1. Precast Concrete Construction
Set commercial precast structures on 12 inches of level, 90 percent compacted 57 stone, extending 18 inches beyond the structure on each side. Compact granular fill by a minimum of four passes with a plate type vibrator. Installation must additionally conform to the manufacturer's instructions. Contractor shall provide wellpoints minimum 48 hours in advance of installation of Precast Concrete structures and leave wellpoints for duration of installation until backfill is complete.
3.4.2. Cable Racks, Arms and Insulators
Cable racks, arms and insulators must be sufficient to accommodate the cables. Space racks in power manholes not more than 3 feet apart and provide each manhole wall with a minimum of three racks. Space racks in signal manholes not more than 16 1/2 inches apart with the end rack being no further than 12 inches from the adjacent wall.
3.5. UNDERGROUND CONDUIT AND DUCT SYSTEMS
3.5.1. Requirements
Run conduit in straight lines except where a change of direction is necessary. Provide numbers and sizes of ducts as indicated. Route grounding conductor into manholes with the conduit. Ducts must have a continuous slope downward toward underground structures, laid with a minimum slope of 4 inches per 100 feet. Depending on the contour of the finished grade, the high point may be at a terminal, a manhole, a handhole, or between manholes or handholes. Provide ducts with end bells whenever duct lines terminate in structures.
Perform changes in ductbank direction as follows:
a. Short-radius manufactured 90-degree duct bends may be used only for pole or equipment risers, unless specifically indicated as acceptable.
b. The minimum manufactured bend radius must be 36 inches for ducts of less than 3-inch diameter, and 60 inches for ducts 3 inches or greater in diameter.
c. As an exception to the bend radius required above, provide field manufactured long sweep bends having a minimum radius of 20 feet for a change of direction of more than 5 degrees, either horizontally or vertically, using a combination of curved and straight sections. Maximum manufactured curved sections: 30 degrees.
3.5.2. Treatment
Ducts must be kept clean of concrete, dirt, or foreign substances during construction. Field cuts requiring tapers must be made with proper tools and match factory tapers. A coupling recommended by the duct manufacturer must be used whenever an existing duct is connected to a duct of different material or shape. Ducts must be stored to avoid warping and deterioration with ends sufficiently plugged to prevent entry of any water or solid substances. Ducts must be thoroughly cleaned before being laid. Plastic ducts must be stored on a flat surface and protected from the direct rays of the sun.
3.5.3. Conduit Cleaning
As each conduit run is completed, for conduit sizes 3 inches and larger, draw a flexible testing mandrel approximately 12 inches long with a diameter less than the inside diameter of the conduit through the conduit. After which, draw a stiff bristle brush through until conduit is clear of particles of earth, sand and gravel; then immediately install conduit plugs. For conduit sizes less than 3 inches, draw a stiff bristle brush through until conduit is clear of particles of earth, sand and gravel; then immediately install conduit plugs.
3.5.4. Multiple Conduits
Separate multiple conduits by a minimum distance of 9 inches
3.5.5. Conduit Plugs and Pull Rope
New conduit indicated as being unused or empty must be provided with plugs on each end. Plugs must contain a weephole or screen to allow water drainage. Provide a plastic pull rope having 3 feet of slack at each end of unused or empty conduits.
3.5.6. Conduit and Duct Without Concrete Encasement
Depths to top of the conduit must be not less than 60 inches below finished grade. Provide not less than 6 inches clearance from the conduit to each side of the trench. Grade bottom of trench smooth; where rock, soft spots, or sharp-edged materials are encountered, excavate the bottom for an additional 3 inches, fill and tamp level with original bottom with sand or earth free from particles, that would be retained on a 1/4-inch sieve. The first 6-inch layer of backfill cover must be sand compacted as previously specified. The rest of the excavation must be backfilled and compacted in 3-to-6-inch layers. Provide color, type and depth of warning tape.
3.5.6.1. Directional Boring
Provide Directional boring in accordance with section 33 05 23.13 Utility Horizontal Directional Drilling.
3.5.7. Duct Sealing
Seal all electrical penetrations for radon mitigation, maintaining integrity of the vapor barrier, and to prevent infiltration of air, insects, and vermin.
3.6. CABLE PULLING
Pull cables down grade with the feed-in point at the manhole of the highest elevation. Use flexible cable feeds to convey cables through manhole opening and into duct runs. Do not exceed the specified cable bending radii when installing cable under any conditions. Cable must have a bending radius not less than 12 times the overall diameter of the completed cable. If basket-grip type cable-pulling devices are used to pull cable in place, cut off the section of cable under the grip before splicing and terminating.
3.6.1. Cable Lubricants
Use lubricants that are specifically recommended by the cable manufacturer for assisting in pulling jacketed cables.
3.7. CABLES IN UNDERGROUND STRUCTURES
Install cables utilizing the long wall between penetrations. Form cables to closely parallel walls, not to interfere with duct entrances, and support on brackets and cable insulators. Support cable splices in underground structures by racks on each side of the splice. Locate splices to prevent cyclic bending in the spliced sheath. Install cables at middle and bottom of cable racks, leaving top space open for future cables, except as otherwise indicated for existing installations. Provide one spare three-insulator rack arm for each cable rack in each underground structure.
3.7.1. Cable Tag Installation
Install cable tags in each manhole as specified, including each splice. Tag wire and cable provided by this contract. Install cable tags over the fireproofing, if any, and locate the tags so that they are clearly visible without disturbing any cabling or wiring in the manholes.
3.8. CABLE END CAPS
Cable ends must be sealed at all times with coated heat shrinkable end caps. Cables ends must be sealed when the cable is delivered to the job site, while the cable is stored and during installation of the cable. The caps must remain in place until the cable is spliced or terminated. Sealing compounds and tape are not acceptable substitutes for heat shrinkable end caps. Cable which is not sealed in the specified manner at all times will be rejected.
3.9. FIREPROOFING OF CABLES IN UNDERGROUND STRUCTURES
Fireproof (arc proof) wire and cables which will carry current at 2200 volts or more in underground structures.
3.9.1. Fireproofing Tape
Tightly wrap strips of fireproofing tape around each cable spirally in half-lapped wrapping. Install tape in accordance with manufacturer's instructions.
3.10. GROUNDING SYSTEMS
NFPA 70 and IEEE C2, except provide grounding systems with a resistance to solid earth ground not exceeding 10 ohms.
3.10.1. Grounding Electrodes
Provide cone pointed driven ground rods driven full depth plus 12 inches, installed to provide an earth ground of the appropriate value for the particular equipment being grounded. If the specified ground resistance is not met, an additional ground rod must be provided in accordance with the requirements of NFPA 70. Should the resultant (combined) resistance exceed the specified resistance, measured not less than 48 hours after rainfall, notify the JEA Project Manager immediately.
3.10.2. Grounding Connections
Make grounding connections which are buried or otherwise normally inaccessible, by exothermic weld.
Make exothermic welds strictly in accordance with the weld manufacturer's written recommendations. Welds which are "puffed up" or which show convex surfaces indicating improper cleaning are not acceptable. Mechanical connectors are not required at exothermic welds.
3.10.3. Grounding Conductors
Provide bare grounding conductors, except were installed in conduit with associated phase conductors. Ground cable sheaths, cable shields, conduit, and equipment with No. 4/0 AWG unless otherwise indicated. Ground other noncurrent-carrying metal parts and equipment frames of metal-enclosed equipment. Ground metallic frames and covers of handholes and pull boxes with a braided, copper ground strap with equivalent ampacity of No. 6 AWG. Provide direct connections to the grounding conductor with 600 v insulated, full-size conductor for each grounded neutral of each feeder circuit, which is spliced within the manhole.
3.10.4. Manhole Grounding
Loop a 4/0 AWG grounding conductor around the interior perimeter, see drawing details. Secure the conductor to the manhole walls at intervals not exceeding 36 inches. Connect the conductor to the manhole grounding electrode with 4/0 AWG conductor. Connect all incoming 4/0 grounding conductors to the ground loop adjacent to the point of entry into the manhole. Bond the ground loop to all cable shields, metal cable racks, and other metal equipment with a minimum 6 AWG conductor.
3.11. EXCAVATING, BACKFILLING, AND COMPACTING
Provide in accordance with NFPA 70. See Section 31 23 00.00 20.
3.11.1. Reconditioning of Surfaces
3.11.1.1. Unpaved Surfaces
Restore to their original elevation and condition unpaved surfaces disturbed during installation of duct. Preserve sod and topsoil removed during excavation and reinstall after backfilling is completed.
Replace sod that is damaged by sod of quality equal to that removed.
3.12. FIELD QUALITY CONTROL
3.12.1. Performance of Field Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations and include the following visual and mechanical inspections and electrical tests, performed in accordance with NETA ATS.
3.12.1.1. Grounding System
Visual and mechanical inspection Inspect ground system for compliance with contract plans and specifications.
Electrical tests Perform ground-impedance measurements utilizing the fall-of-potential method in accordance with IEEE 81. On systems consisting of interconnected ground rods, perform tests after interconnections are complete. On systems consisting of a single ground rod perform tests before any wire is connected.
Take measurements in normally dry weather, not less than 48 hours after rainfall. Use a portable ground resistance tester in accordance with manufacturer's instructions to test each ground or group of grounds. The instrument must be equipped with a meter reading directly in ohms or fractions thereof to indicate the ground value of the ground rod or grounding systems under test. Provide site diagram indicating location of test probes with associated distances and provide a plot of resistance vs.
distance.
3.12.1.2. Follow-Up Verification
Upon completion of acceptance checks and tests, show by demonstration in service that circuits and devices are in good operating condition and properly performing the intended function. As an exception to requirements stated elsewhere in the contract, the Contracting Officer must be given 5 working days advance notice of the dates and times of checking and testing.
File details come from the government source that posted it. Updated .