Administrative Technical Specifications for 680 Underground.pdf

PDF 302 KB Posted

Attached to
Circuit 680 UG Cable Replacement Construction Services
Solicitation number
1412223678
Issued by
Duval County, Florida

About this file

This is an Administrative Technical Specification document issued by JEA (Jacksonville Electric Authority) for construction services related to Circuit 680 underground cable replacement in Jacksonville, Florida. The project involves the replacement of approximately 1,200 feet of 69 kV underground cable originating from the Dillion Substation, with work occurring within the substation, generation facility, and City of Jacksonville right-of-way along Talleyrand Avenue and Wigmore Street. The scope includes installation of opencut concrete-encased duct banks, HDD duct banks, pulling and installation of 69 kV EPR cable, modifications to overhead transmission riser poles and substation termination structures, removal of existing direct-buried 69 kV cable, site restoration, and traffic maintenance. Construction is scheduled to begin February 1, 2028, with all cables pulled and terminated by April 12, 2028. Normal work hours are 7 A.M. to 4 P.M., Monday through Friday, with requests for additional work requiring written approval from the JEA Project Manager at least seven days in advance. A mandatory pre-bid conference and site visit will be held, and the contractor must coordinate jobsite access with the JEA Project Representative.

The contractor is responsible for providing all material, equipment, labor, and supervision necessary to complete the work, including inspection, receipt, unloading, and installation of JEA-supplied materials. The contractor must obtain necessary permits, including an NPDES permit for stormwater discharge and develop a Stormwater Pollution Prevention Plan compliant with local, state, and federal requirements. Personnel requirements include JEA Substation Entry Class certification for all crewmembers, authorization as an "Authorized Person" to request hold tags (requiring successful completion of JEA's "Principles of Hold Tags and Grounding for Contractors" course), JEA Safety Qualification submission within ten business days of bid opening, drug testing at least thirty days prior to work commencement, and appointment of an Environmental Health and Safety Coordinator with OSHA HAZWOPER training. All contractor employees must obtain JEA contractor badges with appropriate access levels, and the contractor is responsible for site security, all access arrangements, damage repairs to public right-of-way and JEA property, and compliance with FDOT, City of Jacksonville, and CSX Railroad regulations.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL SPECIFICATION

GENERAL ADMINISTRATIVE

1. General Description:

1.1. Intent: The Contractor shall provide all material, equipment, labor and supervision to accomplish the work as specified herein and on the construction plans, unless otherwise noted. The JEA supplied materials to accomplish the work of this project is specified herein and on the construction plans. The Contractor is responsible under this contract to pick up, inspect, receive, unload and install these items at the job site.

1.2. Location of Project: The work is located within the City of Jacksonville, FL The exact location will be shown on the contract drawings. The contractor shall repair any damage public right of way or JEA property caused during construction. The repairs shall match the existing construction

1.5 JEA Project Manager: JEA Construction Inspector:

Jonathan Maywood Jay Hockett 225 North Pearl Street 225 North Pearl Street Jacksonville, FL 32202 Jacksonville, FL 32202 Transmission and Substation Projects Transmission and Substation Projects Phone: (904) 625-5974 Phone: (904) 603-1987 Email: maywjw2@jea.com Email: hockhj@jea.com

Transmission Design:

Freeman Bass, PE 501 Riverside Ave. Suite 501 Jacksonville, FL 32202 Phone: (813) 830-8185 Email: fbass@chenmoore.com

1.6 Pre-Construction Conference and Site Visit: A mandatory pre-bid conference and site visit will be held for the benefit of communication and coordination. Such meeting or visit will be scheduled by the Project Manager (JEA).

1.7 Sequence of Work and Project Schedule: All work shall be performed in an orderly and workmanlike manner.

Sequence of work may be scheduled at the discretion of the contractor within the guidelines of these specifications.

Normal duty hours for work are from 7 A.M. until 4 P.M., Monday through Friday. Requests for additional work requires written approval from the JEA Project Manager 7 days in advance of the proposed work period.

1.7.1 Access to the work site: The Contractor shall coordinate with the JEA Project Representative for jobsite access on the JEA property and Oakwood Villa Substation

1.7.2 Public Access: The Contractor shall minimize blocking travel lanes, business or private driveways, and other vehicular access by materials, equipment, or construction activities.

The Contractor shall observe all scheduled JEA holidays, unless approved by the JEA Project Manager.

Construction shall begin on 2/1/28 with all cables pulled and terminated by 4/12/28.

1.8 Permits: Contractor shall comply with all permit requirements accompanying these specifications and shall obtain additional permits, if required, at no additional cost to the JEA.

1.8.1 NPDES Permit: The Contractor shall obtain as necessary a Generic Permit for Storm water Discharge from Large and Small Construction Activities (CGP) and shall develop a Storm water Pollution Prevention Plan (SWPPP) compliant with local, state, and federal rules, laws, and ordinances. Company shall be responsible for implementing the SWPPP, installing and maintaining in a functional manner structural and nonstructural best management practices as described therein, evaluating the effectiveness of the best management practices, and employing additional performance based best management practices as may be deemed necessary by JEA. The Company, at its own expense, shall revise, or include as addendum to the SWPPP measures as may be required by a local, state, or federal authority to remain compliant with local, state, and federal rules, laws, and ordinances. See the solicitation for additional details. The permit can be applied for online at https://floridadep.gov/Water/Stormwater

1.9 Schedule of Values: Contractor to submit a SOV and proposed Monthly Cash Flow to track project billing.

1.10 Material Availability: Any material supplied by JEA will be made available at the beginning of the project and will be issued to the Contractor at JEA’s Commonwealth Service Center, 6674 Commonwealth Ave.

1.11 Electrical Clearances (Outages):

1.11.1 Hold Tags - Authorized Person Requirements: If outages are needed, the contractor will be required to request hold tags. In order for the contractor to request a hold tag on the JEA system, the individual requesting the hold tag must be an Authorized Person as determined by JEA. The contractor will be required to have a knowledgeable employee, preferably a foreman, take and successfully pass the JEA course “Principles of Hold Tags and Grounding for Contractors”. The course will be provided at JEA’s Westside Service Center, and will take one (1) full day to complete. The prerequisite for the course is “JEA’s Substation Entry Training”, See section 1.19 of these specifications for additional details. Hold Tag Courses will be administered by Allyn Jones (contact information is below).The contractor must have his employees sign up for the course(s) by contacting the JEA Project Manager upon winning the bid.

Scott Nordeng: nordsc@jea.com Office: 904-665-6728 Cell: 904-591-5232

1.11.2 Recall of Line Clearances or Hold Tags: In the event that a transmission or distribution hold tag on an energized or de-energized line must be recalled due to a system emergency, as determined by the JEA, the contractor shall complete only the work necessary to clear the line or equipment, clear his personnel, and release his hold tag as quickly as possible. Any recall shall not constitute a just cause by the contractor for a claim for extras.

1.12 Security: Contractor shall be responsible at all times for providing security to the work site, equipment and materials. In addition, the Contractor shall provide site security for contractor worker safety.

1.13 Access to the Work: Access to perform all work is the responsibility of the Contractor. The Contractor shall display all signs and follow all Florida Department of Transportation (FDOT), City of Jacksonville and CSX Railroad rules and regulations when gaining access to the work. Flagmen shall be used, if required. The Contractor shall repair any damage to all roads, R/W’s and adjacent property as directed by and to the satisfaction of JEA. Access to the Transmission Right-Of-Way will be from Public Roads. Any access arrangements crossing private property will be the responsibility of the Contractor.

1.13.1 Access to Substation: Prior to construction, it is the responsibility of the Contractor to have every crewmember attend the JEA issued Substation Entry Class prior to performing any work within the substation. The class is offered every month and is coordinated by Jim Ayers, with contact information as follows: AYERJL@jea.com 904-665-5362

1.13.1.1 NOTE: Contracted personnel may not work inside the station without attending this class.

1.13.2 Badging: A JEA contractor’s badge will be required to gain entry onto any JEA Substation. Every Employee working at the construction site needs to have a JEA contractor’s badge so that they may open and close the gates at a JEA substation. Even if the contactor has a JEA contractor’s badge from a previous project, the contractor needs to provide to the JEA Project Engineer the name’s, phone numbers, and emails of the employees whom he wishes to have a JEA contractor’s badge with access to a JEA substation for this project. Access rights will need to be added by JEA to any badge so that it functions. The process of granting access may take up to three (3) weeks, therefore the request for badge access should be made as soon as possible.

1.13.3 Parking: The Contractor will not be able to park any vehicle overnight within the substation, additionally, no personal vehicles will be allowed within the fenced substation property.

1.13.4 Environmental Requirements

1.13.4.1 Contractor shall provide a competent professional defined as a practicing environmental scientist or engineer with current Title 29 of the Code of Federal Regulations (29 CFR) Part 1910.120 (OSHA HAZWOPER) training, as the Environmental Health and Safety Coordinator (EH&S Coordinator) for the purpose of assuring and documenting compliance with this SGMP. The qualified professional must also be on the JEA RBL WE-11. The EH&S Coordinator shall brief employees on the hazards associated with the potential exposure and components of the SGMP. The EH&S Coordination shall also be on-Site during work activities to monitor work conditions and workspace for potential exposures to Site contaminants and assisting with the field screening, sampling, and proper disposition of excavated soil and recovered groundwater, if any.

Workers must be provided Site-specific health and safety training compliant with Federal and State requirements relative to work in areas where incidental contact with potentially contaminated soil, groundwater, and/or air may occur. The EH&S Coordinator shall have the authority to stop any and all work and require contractors to implement modifications to their work and/or perform additional measures to ensure compliance with this SGMP.

1.14 General Safety Information:

1.14.1 Please visit the following site to learn more about JEA’s safety related information:

https://www.jea.com/About/Procurement/Contractor_Safety/

1.14.2 The winning bid contractor will need to become JEA Safety Qualified at least ten (10) business days after the bid opening by submitting the “Contractor Safety Qualification Questionnaire” found in the link above.

1.14.3 Contractor must abide by the JEA Contractor Safe Work Practices Manual.

https://www.jea.com/About/Procurement/Become_a_Vendor/Contractor_Safety/Contractor_Safety _Manual/

1.14.4 The contractor’s employees need to be drug tested at least thirty (30) days prior to the start of any work. JEA may request for proof of the drug testing before and during the construction.

1.14.5 The contractor’s employees will need to take safety orientation and/ or training as described in the following link:

https://www.jea.com/About/Procurement/Become_a_Vendor/Contractor_Safety/Safety_Orientation _Training/

1.14.6 For any questions regarding JEA’s safety requirements, please contact Curtis Stothers (contact information below):

Safety & Health Specialist:

Manager of Safety and Health Services Curtis Stothers 21 West Church Street, T-3 Jacksonville, FL, 32202 Office: (904) 665-7736 Cell: (850) 855-6177 Email: stotct@jea.com