1412223678 Schedule of Values.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Circuit 680 UG Cable Replacement Construction Services
Solicitation number
1412223678
Issued by
Duval County, Florida

About this file

This Schedule of Values document is associated with the Circuit 680 UG Cable Replacement Construction Services project for the City of Jacksonville, Florida. The project encompasses approximately 1,200 feet of 69 kV underground cable replacement originating from the Dillion Substation. Work activities include installation of an open-cut, concrete-encased duct bank; installation of a horizontal directional drilling (HDD) duct bank; pulling and installation of 69 kV EPR cable; modifications to an overhead transmission riser pole and substation termination structures; removal of existing direct-buried 69 kV cable; site restoration; and maintenance of traffic. The project spans multiple locations including the substation, generation facility, and the City of Jacksonville right-of-way along Talleyrand Avenue and Wigmore Street. A mandatory pre-response meeting was scheduled for October 5, 2026, with solicitation responses due October 27, 2026.

The Schedule of Values document provides the contractor's itemized breakdown of costs for various construction activities and materials associated with the underground cable replacement project. This pricing structure allows for transparent cost allocation across different work components and phases of the project. The document serves as the basis for payment requisitions and progress billing throughout the contract execution, ensuring alignment between the contractor's proposed costs and the work performed on this infrastructure improvement project.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Schedule of Values
Scope#ITEM DESCRIPTIONUOMQuantityUnit PriceExtended Price
Mob / Demob / Bond11.1 MOBILIZATIONLump Sum1$ - 0
21.2 DEMOBILIZATIONLump Sum1$ - 0
31.3 BID BONDLump Sum1$ - 0
41.4 PERMITSLump Sum1$ - 0
51.5 SITE SERVICES & SECURITYLump Sum1$ - 0
Site Preparation62.1 SURVEYING - LAYOUT PROPOSED BORE PATHLump Sum1$ - 0
72.2 SURVEYING - STAKE PROPOSED MANHOLE LOCATION AND EXTENTS OF EXCAVATIONLump Sum1$ - 0
82.2 SURVEYING - STAKE BOUNDARIES OF PERMANENT AND TEMPORARY EASEMENTSLump Sum1$ - 0
Transmission Structures, Cable and Ductbank Installation/ removal93.1 TRANSPORTATION OF JEA PLATING MATERIALS TO JOB SITELump Sum1$ - 0
103.2 RETURN UNUSED JEA MATERIALS AND RECYCLE UNWANTED SCRAPLump Sum1$ - 0
113.3 RECEIVE, UNLOAD AND SET MANHOLELump Sum1$ - 0
123.4 INSTALLATION OF GROUND RODSLump Sum1$ - 0
133.5 HORIZONTAL DIRECTIONAL DRILL OF (4) 6" AND (1) 2" CONDUITSLump Sum1$ - 0
143.6 TRENCH INSTALLATION OF (4) 6" AND (1) 2" CONDUITSLump Sum1$ - 0
153.7 DEMOLITION OF EXISTING CONCRETE CAP AND CABLE IN CONFLICT WITH NEW CABLE INSTALLATIONLump Sum1$ - 0
163.8 MATERIAL COST OF 2000KCM EPR CABLE PLUS SHIPPING TO SITEFT5,070$ - 0
173.9 INSTALLATION OF 2000KCM CABLE AND GROUND CONTINUITY CABLELump Sum1$ - 0
183.10 BONDING AND GROUNDING OF UG ELECTRICAL MATERIALS AT TRANSITION RISER STRUCTURE & SUBSTATION TERMINATION STRUCTURESLump Sum1$ - 0
193.11 REMOVAL OF EXISTING UG POTHEAD/TERMINATIONS/LIGHTNING ARRESTERS AT TRANSITION RISER STRUCTURE & SUBSTATION TERMINATION STRUCTURESLump Sum1$ - 0
203.12 TESTING AND PROOFING OF INSTALLED DUCT BANKSLump Sum1$ - 0
213.13 BUILD OUT MANHOLE AND INSTALL SPLICESLump Sum1$ - 0
223.14 FRAME POLE RISER INCLUDING INSTALLATION TERMINATORS AND ARRESTORSLump Sum1$ - 0
233.15 FRAME SUBSTATION INCLUDING INSTALLATION TERMINATORS AND ARRESTORSLump Sum1$ - 0
243.16 BUILD JUMPERSLump Sum1$ - 0
253.17 INSTALL GALVANIZED STEEL CABLE GUARDLump Sum1$ - 0
263.18 DEWATERINGLump Sum1$ - 0
273.19 CABLE VLF TESTINGLump Sum1$ - 0
Civil Materials
(UG Contractor is responsible for procuring sufficient quantity of these items to construct the project to completion in accordance with the drawings and specifications provided)284.1 6-INCH SCHEDULE 40 PVC CONDUITSLump Sum1$ - 0
294.2 2-INCH SCHEDULE 40 PVC CONDUITSLump Sum1$ - 0
304.3 PVC FITINGS, PRIMER, GLUELump Sum1$ - 0
314.4 MULE TAPE (PER SPECIFICATIONS)Lump Sum1$ - 0
324.5 DUCT SPACERS - DUCT BANKLump Sum1$ - 0
334.6 CONCRETE FOR DUCT BANKLump Sum1$ - 0
344.7 BACKFILL FOR DUCT BANKLump Sum1$ - 0
354.8 6-INCH HDPE SIDR CONDUITLump Sum1$ - 0
364.9 2-INCH HDPE SIDR CONDUITLump Sum1$ - 0
374.10 HIGH PERFORMANCE 3/4" X 0.04" EMBOSSED POLYESTER CONDUIT BUNDLE STRAPPINGLump Sum1$ - 0
384.11 WARNING TAPELump Sum1$ - 0
394.12 ALL OTHER CIVIL MATERIALS UNDER THIS SCOPE OF WORKLump Sum1$ - 0
Electrical Materials
(UG Contractor is responsible for procuring sufficient quantity of these items to construct the project to completion in accordance with the drawings and specifications provided)405.1 6 CABLE CLAMPS AND MOUNTING HARDWARE AS REQUIRED FOR MOUNTING CABLE TO EXISTING UG CABLE RISER POLELump Sum1$ - 0
415.2 GALVANIZED STEEL CABLE GUARDLump Sum1$ - 0
425.3 GROUNDING AND BONDING CONENCTION MATERIALSLump Sum1$ - 0
435.4 ALL OTHER ELECTRICAL MATERIALS UNDER THIS SCOPE OF WORKLump Sum1$ - 0
Miscellaneous446.1 RESTORATIONLump Sum1$ - 0
456.2 AS-BUILT DRAWINGSLump Sum1$ - 0
466.3 SILT FENCE, EROSION AND SEDIMENT CONTROL ASSEMBLY, INSTALLATION, AND REMOVALLump Sum1$ - 0
476.4 ADDITIONAL GROUND RODS (FOR EACH ADDITIONAL GROUND ROD, REQUIRED OVER THE BASE SCOPE OF FOUR (4))Per Rod6$ - 0
486.6 MOT TO BE USED FOR ALL MAINTENANCE OF TRAFFICLump Sum1$ - 0
Subtotal Line 1 - 48 Above$ - 0
SWA (10% of Subtotal)$ - 0
Total Bid Price (Enter this amount on line 1 of the Bid Form)$ - 0

File details come from the government source that posted it. Updated .