This document is a comprehensive specification for asbestos abatement and lead-based paint removal at the Lake City VA Medical Center in Florida, focusing on patient privacy deficiencies in the 2 North and 2 South areas. The project involves detailed requirements for safely removing asbestos-containing materials and lead-based paint, including strict protocols for worker protection, containment, air monitoring, waste disposal, and decontamination procedures. Key specifications include using specialized personal protective equipment, establishing negative air pressure systems, conducting air quality testing, implementing rigorous cleaning and disposal methods, and ensuring comprehensive worker training and medical monitoring.

The project requires a certified industrial hygienist to oversee operations, with specific requirements for respiratory protection, medical surveillance, and waste management. The abatement work involves removing approximately 825 square feet of flooring and mastic, 300 linear feet of duct with black mastic, 75 linear feet of aircell pipe insulation, and 25 linear feet of black mastic on hard pipe elbows. The contractor must comply with OSHA, EPA, and other federal regulations, use specialized equipment like HEPA filtration systems, and follow detailed procedures for containment, removal, and final clearance testing to ensure safe and thorough asbestos and lead-based paint removal.

View the file

Other files

File Type Posted
RFIs 2025 07 09 36C24825R0127 22N2S.xlsx XLSX spreadsheet
36C24825R0127 CLAUSE SHEET.docx DOCX document
Sheet AE452 Headwall Interior Elevations.pdf PDF
2025 06 24 Site Visit 573A4-18-603.pdf PDF
36C24825R0127 0001.pdf PDF
PRIOR SOLICITATION 36C24825R0067 573A418603 Site Visit.pdf PDF
SOLICITATION 36C24825R0127 BB Correct PT Privacy Def 2N 2S LC VAMC.pdf PDF
Exhibit A QA RFIs.xlsx XLSX spreadsheet
2024 01 29 Drawings Structural.pdf PDF
AE503.pdf PDF
Exhibit C EMR.docx DOCX document
Exhibit F Past and Present Performance Questionnaire.docx DOCX document
RFIs 36C24825R0067 Correct Patient Privacy.pdf PDF
2024 01 29 Drawings Architectural.pdf PDF
2024 01 29 Drawings Mechanical.pdf PDF
Specifications Vol 2.pdf PDF
Exhibit E Performance Relevancy Survey v2.docx DOCX document
Visitor Sign In 36C24825R0067 573A418603.pdf PDF
SOLICITATION 36C24825R0127 BB Correct PT Privacy Def 2N 2S LC VAMC.pdf PDF
2024 01 29 Drawings Electrical.pdf PDF
2024 01 29 Drawings Fire Protection.pdf PDF
2024 01 29 Drawings Plumbing.pdf PDF
AE302.pdf PDF
AE709.pdf PDF
SAM DBA 05_02_25.pdf PDF
Exhibit B LOS Certification Solicitation Version.doc DOC document
Exhibit D Contract Progress Schedule.pdf PDF
Exhibit I Price Matrix.xlsx XLSX spreadsheet
RFIs 36C24825R0067 Correct Patient Privacy.xlsx XLSX spreadsheet
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Correct Patient Privacy Deficiencies at the

Lake City VA Medical Center Lake City, Florida

Specifications Bid Documents

Volume I

September 29, 2023 Project Number: 573A4‐18‐603

(THIS PAGE LEFT INTENTIONALLY BLANK)

Lake City VA Medical Center, Lake City, FL 04-01-23

00 01 10 - 1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21 01 33 23 Shop Drawings, Product Data, and Samples 02-23 01 33 23.10 Submittal Register Engineering Form 4288-R 01 35 26 Safety Requirements 10-22 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 45 35.10 Schedule of Special Inspections 01 45 35.20 Statement of Special Inspections 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 04-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17 02 82 13 Asbestos Abatement 01-21 02 82 13.10 Asbestos Abatement Plan AA-1 02 82 13.20 Asbestos Abatement Plan AA-2 02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

DIVISION 03 – CONCRETE

03 30 53 (Short-Form) Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 01 00 Maintenance of Masonry 01-21 04 05 13 Masonry Mortaring 10-17

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 36 00 Composite Metal Decking 01-21 05 50 00 Metal Fabrications 08-18

00 01 10 - 2

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21 07 22 00 Roof and Deck Insulation 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 17 10 Integrated Door Assemblies 01-21 08 32 13 ICU Sliding Glass Doors 01-21 08 71 00 Door Hardware 05-22 08 80 00 Glazing 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 30 13 Ceramic/Porcelain Tiling 01-21 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16 Resilient Sheet Flooring 06-22 09 65 19 Resilient Tile Flooring 05-18 09 67 23.20 Resinous Epoxy Base With Vinyl Chip Broadcast (RES 2) 12-21 09 68 00 Carpeting 01-21 09 91 00 Painting 01-21 09 96 59 Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard, and Block CMU (RES-W1, RES-W2) 01-21

DIVISION 10 – SPECIALTIES

10 11 13 Chalkboards and Markerboards 01-21 10 11 23 Tackboards 01-21 10 14 00 Signage 01-21 10 21 23 Cubicle Curtain Tracks 01-21 10 25 13 Patient Bed Service Walls 05-23 10 26 00 Wall and Door Protection 01-21 10 28 00 Toilet, Bath, and Laundry Accessories 01-21 10 44 13 Fire Extinguisher Cabinets 08-18

00 01 10 - 3

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 11 – EQUIPMENT

11 73 00 Ceiling Mounted Patient Lift System 08-20

DIVISION 12 – FURNISHINGS

12 32 00 Manufactured Wood Casework 01-21 12 36 61.16 Solid Surfacing Countertops

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components 01-21

DIVISION 14– CONVEYING EQUIPEMENT

Not Required

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 01-23 22 05 19 Meters and Gages for Plumbing Piping 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 12-22 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 03-23

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

03-23

23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 09 23 Direct-Digital Control System for HVAC 03-23 23 21 23 Hydronic Pumps 03-23 23 22 13 Steam and Condensate Heating Piping 04-23

23 31 00 HVAC Ducts and Casings 03-23

00 01 10 - 4

SECTION NO DIVISION AND SECTION TITLES DATE

23 34 00 HVAC Fans 03-23 23 36 00 Air Terminal Units 03-23 23 37 00 Air Outlets and Inlets 03-23 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-23 23 81 00 Decentralized Unitary HVAC Equipment 03-23 23 81 43 Air-Source Unitary Heat Pumps 03-23

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 24 16 Panelboards 11-22 26 27 26 Wiring Devices 11-22 26 29 11 Motor Controllers 11-22 26 51 00 Interior Lighting 11-22

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 15 00 Communications Structured Cabling 01-16 27 41 31 Master Antenna Television Equipment and Systems 06-15 27 52 23 Nurse Call and Code Blue Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 13 00 Physical Access Control System 10-11 28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11

Lake City VAMC, Lake City, FL 05-01-20

00 01 15 - 1

SECTION 00 01 15

LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No. Title

GENERAL

GI001 COVER SHEET

GI002 NOTES, ABBREVIATIONS AND LEGEND

GI003 PHASING PLANS

LIFE SAFETY

LS101 LIFE SAFETY PLAN – SECOND FLOOR

LS102 LIFE SAFETY PLAN – THIRD FLOOR

ARCHITECTURAL

AD101 SECOND FLOOR DEMOLITION PLAN

AD102 PARTIAL THIRD FLOOR DEMOLITION PLAN

AD111 SECOND FLOOR DEMOLITION RCP

AD112 PARTIAL THIRD FLOOR DEMOLITION RCP

AE101 SECOND FLOOR PLAN - OVERALL

AE102 SECOND FLOOR FIRE ALARM PLAN – AREA B

AE103 SECOND FLOOR FIRE ALARM PLAN – AREA B

AE104 THIRD FLOOR PLAN - OVERALL

AE105 ENLARGED THIRD FLOOR PLAN

AE111 SECOND FLOOR RCP

AE112 THIRD FLOOR RCP

AE201 FRONT BUILDING ELEVATION

AE401 ENLARGED PLAN - TYPICAL PATIENT ROOMS

AE402 ENLARGED PLAN - NURSE STATION AREA

AE403 ENLARGED PLAN - THIRD FLOOR ENLARGED PLANS

AE451 INTERIOR ELEVATIONS

AE501 DETAILS

AE502 DETAILS

AE601 DOOR SCHEDULE, DETAILS, AND TYPES

AE602 FINISH SCHEDULE

AE801 TYPICAL PATIENT ROOMS - EQUIPMENT PLANS

AE802 TYPICAL EQUIPMENT PLANS AND SCHEDULE

00 01 15 - 2

STRUCTURAL

S001 STRUCTURAL NOTES

S001 STRUCTURAL NOTES

S101 FLOOR FRAMING PLAN

S102 PARTIAL THIRD FLOOR FRAMING PLAN (SOUTH)

S103 PARTIAL THIRD FLOOR FRAMING PLAN (NORTH)

S104 2nd FLOOR FRAMING PLAN AHU 1 & 3

S105 2nd FLOOR FRAMING PLAN AHU 2 & 4

S301 CONCRETE DETAILS

S501 STEEL DETAILS

S502 STEEL DETAILS

MECHANICAL

M-001 MECHANICAL LEGEND AND NOTES

MD101 SECOND FLOOR PLAN - OVERALL DEMOLITION

MD102 THIRD FLOOR - OVERALL DEMOLITION

MH101 SECOND FLOOR PLAN – OVERALL

MH102 SECOND FLOOR PLAN – SOUTH

MH103 SECOND FLOOR PLAN – NORTH

MH104 THIRD FLOOR PLAN - OVERALL

MH105 THIRD FLOOR PARTIAL PLAN – 3 CENTRAL CORE

MH106 ROOF PLAN

MP101 LOWER LEVEL AND PENTHOUSE A PIPING PLANS

MP102 SECOND FLOOR PIPING PLAN – 2 SOUTH

MP103 SECOND FLOOR PIPING PLAN – 2 NORTH

MP104 THIRD FLOOR PARTIAL PIPING PLAN – 3 CENTRAL CORE

M-501 DETAILS

M-502 DETAILS

M-503 DETAILS

M-601 SCHEDULES

M-602 SCHEDULES

M-701 CONTROL DIAGRAMS

M-702 CONTROL DIAGRAMS

M-703 CHILLED WATER FLOW & CONTROL DIAGRAM

M-704 STEAM & HEATING WATER FLOW & CONTROL DIAGRAMS

00 01 15 - 3

PLUMBING

P-001 LEGENDS AND GENERAL NOTES

PD-100 FIRST FLOOR DEMOLITION PLAN - NORTH

PD-101 FIRST FLOOR DEMOLITION PLAN – SOUTH

PD-102 SECOND FLOOR DEMOLITION PLAN – 2 NORTH

PD-103 SECOND FLOOR DEMOLITION PLAN – 2 SOUTH

PD-104 THIRD FLOOR PARTIAL DEMOLITION PLAN – 3 CENTRAL CORE

PD-101 ENLARGED THIRD FLOOR DEMOLITION PLAN

PL-100 FIRST FLOOR DRAINAGE PLAN – NORTH

PL-101 FIRST FLOOR DRAINAGE PLAN – SOUTH

PL-102 SECOND FLOOR DRAINAGE PLAN – 2 NORTH

PL-103 SECOND FLOOR DRAINAGE PLAN – 2 SOUTH

PL-104 THIRD FLOOR DRAINAGE PLAN – 3 CENTRL CORE

PP-102 SECOND FLOOR SUPPLY PLAN – 2 NORTH

PP-103 SECOND FLOOR SUPPLY PLAN – 2 SOUTH

PP-104 THIRD FLOOR PARTIAL SUPPLY PLAN – 3 CENTRAL CORE

PP-105 SECOND FLOOR MED GAS PLAN – 2 NORTH

PP-106 SECOND FLOOR MED GAS PLAN – 2 SOUTH

PP-300 RISER DIAGRAMS

PP-301 RISER DIAGRAMS

PP-302 RISER DIAGRAMS

PP-303 RISER DIAGRAMS

PP-304 RISER DIAGRAMS

PP-305 RISER DIAGRAMS

PP-500 SCHEDULES

FIRE PROTECTION

F-001 FIRE PROTECTION LEGEND NOTES AND DETAILS

FD101 SECOND FLOOR FIRE PROTECTION DEMOLITION PLAN

FD102 THIRD FLOOR FIRE PROTECTION DEMOLITION PLAN

FA101 SECOND FLOOR FIRE ALARM PLAN 2 NORTH

FA102 SECOND FLOOR FIRE ALARM PLAN 2 SOUTH

FA103 THIRD FLOOR FIRE ALARM PLAN

FX101 SECOND FLOOR SPRINKLER PLAN 2 NORTH

FX102 SECOND FLOOR SPRINKLER PLAN 2 SOUTH

FX103 THIRD FLOOR SPRINKLER PLAN

FX701 SPRINKLER PIPE DIAGRAMS

00 01 15 - 4

ELECTRICAL

E-001 ELECTRICAL LEGEND, NOTES AND ABBREVIATIONS

ED101 SECOND FLOOR DEMOLITION PLAN - LIGHTING

ED102 THIRD FLOOR DEMOLITION PLAN – LIGHTING

ED103 SECOND FLOOR DEMOLITION PLAN – POWER/TELECOM

ED104 THIRD FLOOR DEMOLTION PLAN – POWER/TELECOM

EL101 SECOND FLOOR PLAN – LIGHTING – 2 NORTH

EL102 SECOND FLOOR PLAN – LIGHTING – 2 NORTH

EL103 THIRD FLOOR PLAN - LIGHTING

EL501 LIGHT FIXTURE SCHEDULE AND DETAILS

EP101 LOWER LEVEL AND FIRST FLOOR PLANS - POWER

EP102 SECOND FLOOR PLAN – POWER – 2 NORTH

EP103 SECOND FLOOR PLAN – POWER – 2 SOUTH

EP104 THIRD FLOOR PLAN - POWER

EP105 ROOF PLAN - POWER

EP501 EQUIPMENT CONNECTION SCHEDULE AND DETAILS

EP601 PANEL BOARD SCHEDULES

EP602 PANEL BOARD SCHEDULES

EP701 POWER RISER DIAGRAM

TT101 SECOND FLOOR PLAN – TELECOM – 2 NORTH

TT102 SECOND FLOOR PLAN – TELECOM – 2 SOUTH

TT103 THIRD FLOOR PLAN – TELECOM

TT501 TELECOM DETAILS

- - - END - - -

Lake City VA Medical Center, Lake City, FL 11-01-21

01 00 00 - 1

SECTION 01 00 00

GENERAL REQUIREMENTS

GENERAL

1.1 SAFETY REQUIREMENTS

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Correct Patient Privacy

Deficiencies as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the

Medical Center Engineering Officer.

C. Offices of Toland Mizell Molnar, LLC, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, interior alterations, exterior and interior steel framing modifications, repair and refinishing, roof-mounted HVAC equipment, roof membrane repair, brick work and mortar repointing, and necessary removal of existing structures and construction and certain other items.

01 00 00 - 2

B. ALTERNATE NO.1: BASE BID except delete all costs to install roof mounted air handling unit, associated ductwork and roof support platform for the 3 North Air Handling Unit.

C. ALTERNATE NO.2: ALTERNATE 1 except delete all costs to install roof mounted air handling unit, associated ductwork and roof support platform for the 3 South Air Handling Unit.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work, the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project

01 00 00 - 3 including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71

00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of

“sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.

Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting

Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document

Management Software (EDMS).

Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the

EDMS system.

“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours

01 00 00 - 4 before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the

Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the

Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the

Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting

Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting

Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting

Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The

Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that

01 00 00 - 5 transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of

Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

H. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measures to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to: abatement, interior and selective building demolition, and building construction.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building

01 00 00 - 6 or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of the building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, , COR and

Contractor, as follows:

Phase I:

Phase I will include all work on 2-South and the following spaces within the Second Floor Central Core area as follows: Multi-purpose, Staff Toilet, Clean Linen, Telecom Room, Elevator

Vestibule, Family Lounge, Family Toilets and Corridor C2-8A. Work will also include steel framing repair and refinishing for the 3-

South screened porch. Work in this phase will be performed between 6:30 AM and 3:30 PM. Upon completion and acceptance of

Phase I work, the VA will occupy 2 South, relocating patients and staff from 2-North.

Phase II:

Phase II will include all work on 2-North and Equipment Storage in the Second Floor Central Core area. Work will also include steel framing repair and refinishing for the 3-North screened porch. Work in this phase will be performed between 6:30 AM and

3:30 PM. Upon completion and acceptance of Phase I work, work will commence in Phase IIA.

Phase IIA:

Phase IIA will include all work in Corridor C2-5. Work in this phase will be performed over weekends. Access to Stair 3 and

Elevator Vestibule C2-1 must be maintained from 2 North. Upon completion and acceptance of Phase IIA work, work will commence in Phase IIB.

Phase IIB:

Phase IIB will include all work in Elevator Vestibule C2-1 and

Corridor C2-9. Work in this phase will be performed over weekends. Access to Stair 3 and Elevator Vestibule C2-2 must be maintained from 2-North.

Access to Elevator Vestibule C2-2 and Stair 1 must be maintained from 2-South. Upon completion and acceptance of Phase IIB work, work will commence in Phase III.

Phase III:

01 00 00 - 7

Phase III will include all work in the Third Floor Central Core area as follows: Staff lounges and toilet rooms, Serenity Room, Laundry, Telecom Room, Social Worker office, Nurse Educator office, Equipment Storage and passage leading to and including 3-

North screened balcony. Upon completion and acceptance of Phase

III work, work will commence in Phase IIIA.

Phase IIIA:

Phase IIIA will include all work in the Elevator Vestibule C3-1 and Corridor C3-9. Work in this phase will be performed over weekends. Access to elevator Vestibule C3-2 and Stair 3 must be maintained from 3-North. Access to Elevator Vestibule C3-2 and

Stair 1 must be maintained from 3-South. Upon completion and acceptance of Phase IIIA work, work will commence in Phase IIIA.

Phase IIIB:

Phase IIIB will include all work in Corridor C3-5. Work in this phase will be performed over weekends. Access to elevator

Vestibule C3-2 and Stair 3 must be maintained from 3-North.

Access to Elevator Vestibules C3-1 and C3-2 and Stairs 1, 2 and 3 must be maintained from 3-North and 3-South. Upon completion and acceptance of Phase IIIB work, work will commence in Phase IIIC.

Phase IIIC:

Phase IIIC will include all work in Elevator Vestibule C3-2, Dining Room and 3-South screened balcony. Work in this phase will be performed over weekends. Access to Elevator Vestibule C3-2 and Stairs 1, 2 and 3 must be maintained from 3-North and 3-

South.

I. Part of Building 64 will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to

Proceed and turned over to Contractor.

J. Building No. _64_ will be occupied during performance of work; but immediate areas of alterations will be vacated.

1. Certain areas of Building No. _64_ will be occupied by Medical

Center personnel for various periods as listed below:

AREA PERIOD

(a)First Floor __ Project Duration____

(b)Second Floor - North __ Phase I Duration____

(c)Third Floor - North ___Project Duration___

(d)Third Floor - South ___Project Duration___

01 00 00 - 8

2. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of

Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of

Veterans Affairs so that Medical Center operations will continue during the construction period.

3. Immediate areas of alterations not mentioned in preceding

Subparagraph 1 will be temporarily vacated while alterations are performed.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.

Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm

(one inch) above grade. Remove the fence when directed by COR.

L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from

Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for Medical

Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.

01 00 00 - 9

Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.

When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR

COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR

ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to

COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be

01 00 00 - 10 removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of

Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR

01 00 00 - 11 and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by

Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE

CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of

Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations

01 00 00 - 12 in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS (FAR 52.236-9)

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the

Contractor fails or refuses to repair the damage promptly, the

Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and

"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

01 00 00 - 13

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the

COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged.

Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"

(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, and C shall also apply to all shop drawings.

01 00 00 - 14

1.12 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the

Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

01 00 00 - 15

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance and Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure

01 00 00 - 16 to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for

Contractor response, and other details deemed necessary by the

Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.

This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

E. Following oral or written notification by the Contracting Officer, the

Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.

Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the

Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

01 00 00 - 17

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a) Code 1-Life Safety Systems

Fire suppression systems.

Fire alarm system(s).

b) Code 1-Air Conditioning Systems

Air conditioning leak in part of the building, if causing damage.

Air conditioning system not cooling properly.

c) Code 1 Doors

Overhead doors not operational, causing a security, fire or safety problem.

1) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d) Code 3-Doors

Overhead doors not operational.

Interior/exterior personnel doors or hardware not functioning properly.

e) Code 1-Electrical

Power failure (entire area or any building operational after

1600 hours).

Security lights.

Smoke detectors.

f) Code 2-Electrical

Power failure (no power to a room or part of building).

Receptacle and lights not operational (in a room or part of building).

g) Code 3-Electrical

Exterior lights not operational.

h) Code 1-Gas

Leaks and pipeline breaks.

i) Code 1-Heat

Power failure affecting heat.

j) Code 1-Plumbing

Hot water heater failure.

2) Leaking water supply pipes

01 00 00 - 18

k) Code 2-Plumbing

Flush valves not operating properly

Fixture drain, supply line or any water pipe leaking.

Toilet leaking at base.

l) Code 3- Plumbing

Leaky faucets.

m) Code 3-Interior

Floors damaged.

Paint chipping or peeling.

Casework damaged.

n) Code 1-Roof Leaks

Damage to property is occurring.

o) Code 2-Water (Exterior)

No water to facility.

p) Code 2-Water (Hot)

No hot water in portion of building listed.

q) Code 3

All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting

Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

01 00 00 - 19

Warranty Tags

Telephone number

Warranty response time priority code

1.13 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical

Center property When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.

B. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto must be completed and available for use at time set for completion of such buildings or parts thereof.

1.14 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevator for handling building materials and

Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of existing service elevator to be designated for his or her use. The COR will ascertain that elevators are in proper condition. Contractor may use elevators Nos. _S-1 or S-2 in Building No. 64for daily use between the hours of 6:00 AM and 3:00 PM and assigned and scheduled with the

COR and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.

2. Contractor covers and provides maximum protection of following elevator components:

a) Entrance jambs, heads soffits and threshold plates.

b) Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c) Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are…