RFIs 2025 07 09 36C24825R0127 22N2S.xlsx

XLSX spreadsheet 34 KB Posted

Attached to
BB Correct Patient Privacy Deficiencies 2N/2S Lake City, FL Project # 573A4-18-603
Solicitation number
36C24825R0127
Issued by

About this file

This Request for Information (RFI) pertains to a Department of Veterans Affairs project to correct patient privacy deficiencies at the Lake City, FL facility (Project #573A4-18-603). The solicitation (36C24825R0127) is a resolicitation open to small businesses, replacing a previous SDVOSB solicitation.

The RFI document contains a detailed comment matrix with multiple substantive questions from Blue Cord Design and Construction regarding project specifications, including roof access, construction phasing, lead-based paint abatement, concrete reinforcement details, and patient headwall elevations. Key technical clarifications include confirmation of roof access procedures, a 30-day transition period between construction phases, lead paint assumptions for interior walls, and specific guidance on concrete scanning and demolition work. The VA provided specific responses to each technical inquiry, demonstrating willingness to provide contractor clarity and potentially negotiate alternative approaches that support project success.

View the file

Other files

File Type Posted
PRIOR SOLICITATION 36C24825R0067 573A418603 Site Visit.pdf PDF
36C24825R0127 0001.pdf PDF
36C24825R0127 CLAUSE SHEET.docx DOCX document
Sheet AE452 Headwall Interior Elevations.pdf PDF
2025 06 24 Site Visit 573A4-18-603.pdf PDF
SOLICITATION 36C24825R0127 BB Correct PT Privacy Def 2N 2S LC VAMC.pdf PDF
2024 01 29 Drawings Mechanical.pdf PDF
RFIs 36C24825R0067 Correct Patient Privacy.pdf PDF
AE302.pdf PDF
Specifications Vol 2.pdf PDF
Specifications Vol 1.pdf PDF
SAM DBA 05_02_25.pdf PDF
Exhibit D Contract Progress Schedule.pdf PDF
Exhibit I Price Matrix.xlsx XLSX spreadsheet
Exhibit E Performance Relevancy Survey v2.docx DOCX document
2024 01 29 Drawings Electrical.pdf PDF
Exhibit B LOS Certification Solicitation Version.doc DOC document
2024 01 29 Drawings Fire Protection.pdf PDF
Exhibit A QA RFIs.xlsx XLSX spreadsheet
2024 01 29 Drawings Architectural.pdf PDF
SOLICITATION 36C24825R0127 BB Correct PT Privacy Def 2N 2S LC VAMC.pdf PDF
2024 01 29 Drawings Plumbing.pdf PDF
RFIs 36C24825R0067 Correct Patient Privacy.xlsx XLSX spreadsheet
AE709.pdf PDF
Visitor Sign In 36C24825R0067 573A418603.pdf PDF
AE503.pdf PDF
Exhibit C EMR.docx DOCX document
2024 01 29 Drawings Structural.pdf PDF
Exhibit F Past and Present Performance Questionnaire.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MATRIX

ITEM #SECTION or ATTACHMENT #DOCUMENT NAMECOMMENT TYPE
(Select from drop down)Received DateQUESTIONS / COMMENTS
(With justification of why considered source selection sensitive if applicable)VA ResponseResponse DateVA

Response

FromCompany Name
SubstantiveWill the VA please consider adding FAR 52.225, and it's applicable subsections, to the solicitation documents to confirm this project must conform to the Buy American Act?Missing Clauses Included.7/7/25MiltonBlue Cord Design and Construction
SubstantiveIf no to the question above, will the VA please confirm this project must meet the Buy American Act?Buy American Act Required7/72025MiltonBlue Cord Design and Construction
SubstantiveIs it the VA's intention to give access to the north and south roof elevations through the main building or shall contractors provide a stair scaffolding system for access?The GC may use the staff elevators. The superintendent may be issued a roof access key. However, if GC wishes to install stair scaffolding for its convenience, this may be permitted.7/7/25DrakeBlue Cord Design and Construction
S102-103, S301SubstantivePlease clarify if the supplemental beam shear rebar locations will be installed from the top or the bottom. Both details are provided but the plan view does not differenciate.Both details are provided. Either detail can be used by contractor at their option.7/7/25BarrentineBlue Cord Design and Construction
S102-103, S301SubstantivePlease clarify if the contractor is to GPR all locations of shear reinforcement ahead of install.Scan existing concrete for embedded items utilizing radar. Do not proceed with demolition work of the affected area until authorized to do so by the Government.7/7/25MasseyBlue Cord Design and Construction
SubstantivePlease confirm the turnaround time after phase 2 South is completed before the Contractor receives full access to 2 North.Anticipate 30 day transition period.7/7/25DrakeBlue Cord Design and Construction
SubstantivePlease clarify the adjacent areas that will be occupied during construction along with any additional phasing, beyond the phasing defined in the contract documents, that may be required to facilitate safe ingress and egressLevel 1 below, Level 3 above. Contract document phasing is suggestive, VA PM will consider alternative phasing suggestions if in the best interest of project success.7/7/25DrakeBlue Cord Design and Construction
SubstantiveIt has been observed that the majority of main corridor walls and interior walls at the building’s exterior perimeter are constructed of plaster on wire lath, with some instances incorporating gypsum pyroblock. Testing of original paint layers has confirmed the presence of lead-based paint.
For the purposes of level bidding, please confirm whether the contractor should assume that all corridor walls and interior walls at the exterior perimeter contain lead-based paint. This assumption will impact the scope and pricing of lead abatement efforts.yes, that is the assumption. Tests have revealed positive results for the underlying paint layers to contain lead. Presumably the interior walls might be cut into sections, or blocks, for demolition which mght reduce the level of abatement effort for all surfaces. the VA PM would permit the use of a window opening for extrication of said material, thus reducing the transport concerns for moving old material through patient areas.7/7/25DrakeBlue Cord Design and Construction
SubstantiveThere are no elevations in the drawings showing the patient headwalls. Will the VA please provide cut sheets?Drawing Sheet AE452 Headwall Interior Elevations7/7/25MasseyBlue Cord Design and Construction

DIRECTIONS

TAILORED COMMENT MATRIX

THIS DOCUMENT MUST BE RETURNED IN A MICROSOFT EXCEL FILE FORMAT. DO NOT RETURN YOUR RESPONSES IN ANY DIFFERENT FILE FORMAT.

Directions & Explanation of TAILORED COMMENT MATRIX
This Tailored Comment Matrix is provided in order for potential offerors to provide feedback, comments, and ask questions with regard to the released RFP.

The sheet labeled "DIRECTIONS" explains this document, and provides directions for its use.

The sheet labeled "MATRIX" contains a table with all labeled and numbered elements from the RFP. This table is where potential offerors may respond to the Government with feedback, comments, or ask questions.

Directions and explanation of sheet labeled "MATRIX"
The MATRIX sheet can be reached by clicking the "MATRIX" Tab at the bottom of this spreadsheet. Add rows as necessary under the applicable item.
MATRIX COLUMN DESCRIPTIONS:
Column A:Contains the Item reference number for this item. This number is used for organizational purposes, when referring to this document only.

Column B: Contains the section number that each element is labeled, within their respective documents. The section number relates directly to the item's location in the RFP.

Column C: Contains the written title for the corresponding item/section number.

Column D:Contains a drop down box for selecting the type of comment. Available options are "Critical" "Substantive" or "Administrative".
Critical: Violations of law -or- Unnecessary risks to safety, life & limb, or VA Material; waste or abuse of VHA appropriations; unreasonable burden on resources.
Substantive: Appears or is potentially unnecessary, incorrect, misleading, confusing, or inconsistent with other sections; disagree with proposed responsibilities, requirements, and/or procedures.
Administrative: Address typographical, grammatical, and formatting errors (grammar, punctuation, style, etc.)

Column E: Contains recieved date of offerors' comments/questions/responses.

Column F: Contains space for potential offerors' comments/questions/responses.

Column G: Contains space for VHA comments/questions/responses.

Column H: Contains response date for VHA comments/questions/responses.

Column I: Contains VHA Section/ POC shop comments/questions/response

Column J: Contains Contractor Name requesting /questions/responses.

THIS DOCUMENT MUST BE RETURNED IN A MICROSOFT EXCEL FILE FORMAT. DO NOT RETURN YOUR RESPONSES IN ANY DIFFERENT FILE FORMAT.