DLA ENTERPRISE FIRE PROTECTION CONTROL SYSTEMS (FPCS)
Solicitation number
SP4702-24-R-0005
Issued by

About this file

This is a Quality Assurance Surveillance Plan (QASP) for the Defense Logistics Agency (DLA) Fire Protection Control Systems (FPCS) contract. The QASP outlines how the government will monitor and evaluate contractor performance under the Performance Based Service Contract standards and subsequent task orders.

The plan details five performance rating levels (Exceptional, Very Good, Satisfactory, Marginal, and Unsatisfactory) that determine monthly payment amounts, with 100% payment for Exceptional through Satisfactory performance, 85% for Marginal performance, and withheld payment for Unsatisfactory performance pending cure notice resolution. The QASP establishes surveillance methods including random sampling, 100% inspection, periodic inspection, and customer feedback. It defines roles and responsibilities for the Contracting Officer, Functional Services Manager, and Contracting Officer's Representative in monitoring performance. The contractor is required to implement their own quality control program while the government conducts surveillance through monitoring forms, monthly performance assessments, and review meetings to ensure service quality standards are met for the FPCS program across DLA facilities.

View the file

Other files

File Type Posted
Amendment 0005.pdf PDF
Site Visit Roster.pdf PDF
RFP Questions from vendor.xlsx XLSX spreadsheet
Amendment - 0004_Signed.pdf PDF
Inventory from Host Site.pdf PDF
Service Call Work Authorization.pdf PDF
Attachment 2 - Updated FPCS Pricing Sheet.xlsx XLSX spreadsheet
FPCS PWS.pdf PDF
PWS Acronym List.pdf PDF
Attachment 3 - Updated FPCS Eval Factor 3 Sample TO PWS.pdf PDF
Purdue Level Information.pptx PPTX presentation
SP4702-24-R-0005 - FPCS OT Pillar.pdf PDF
Amendment - 0003.pdf PDF
Amendment - 0002.pdf PDF
Amendment - 001.pdf PDF
Attachment 3 - FPCS Eval Factor 3 Sample TO PWS.pdf PDF
Attachment 1 - FPCS PWS.pdf PDF
SP4702-24-R-0005 - FPCS OT Pillar.pdf PDF
Attachment 4 - Cross Reference.xlsx XLSX spreadsheet
Attachment 7 - Contractor NDA.docx DOCX document
Attachment 5 - KTR Experience Questionnaire.xlsx XLSX spreadsheet
Attachment 2 - FPCS Pricing Sheet.xlsx XLSX spreadsheet
Attachment 6 - Key Personnel Resume Template.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

Defense Logistics Agency (DLA) Fire Protection Control Systems

(FPCS)

This Quality Assurance Surveillance Plan (QASP) is a Government developed and applied document used to make sure the systematic quality assurance methods are used in the administration of the Performance Based Service Contract (PBSC) standards included in this contract and if applicable, in subsequent task orders. The intent is to ensure that the contractor performs in accordance with the performance metrics and the Government receives the quality of services called for in the contract.

A properly executed QASP will assist the Government in achieving the objectives of this procurement.

TABLE OF CONTENTS

1 INTRODUCTION

1.1 Purpose

1.2 Performance Management Approach

1.3 Performance Management Strategy

2 ROLES AND RESPONSIBILITIES

2.1 The Contracting Officer

2.1 The Functional Services Manager(s)

2.3 The Contracting Officer’s Representative

3 IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS

4 METHODOLOGIES TO MONITOR PERFORMANCE

4.1 Surveillance Techniques

4.2 Customer Feedback

4.3 Acceptable Quality Levels

5 QUALITY ASSURANCE DOCUMENTATION

5.1 The Performance Management Feedback Loop

5.2 Monitoring Forms

6 ANALYSIS OF QUALITY ASSURANCE ASSESSMENT

6.1 Determining Performance

6.2 Reporting

6.3 Reviews and Resolution

ATTACHMENT 1: PERFORMANCE REQUIREMENTS SUMMARY

ATTACHMENT 2: SAMPLE QUALITY ASSURANCE MONITORING FORM

QUALITY ASSURANCE SURVEILLANCE PLAN

(QASP)

1 INTRODUCTION

This quality assurance surveillance plan (QASP) is pursuant to the requirements listed in the performance work statement (PWS) entitled Defense Logistics Agency (DLA) Enterprise Fire Protection Control Systems (FPCS). This plan sets forth the procedures and guidelines DLA Information Operations Enterprise Capabilities Portfolio (J62B), Installation Support Program Management Office (PMO) (J62BK) and DLA Installation Management (DM) will use in ensuring the required performance standards or services levels are achieved by the contractor for the Indefinite Delivery Indefinite Quantity (IDIQ) contract and subsequent Task Orders (TOs).

1.1 Purpose

1.1.1 The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards/quality levels identified in the PWS and the contractor’s quality control plan (QCP), and to ensure that the government pays only for the level of services received.

1.1.2 This QASP defines the roles and responsibilities of all members of the integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.

1.2 Performance Management Approach

1.2.1 The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by DLA J62B/J62BK and DM to monitor and manage the contractor’s performance to ensure the expected outcomes or performance objectives communicated in the PWS are achieved. Performance management rests on developing a capability to review and analyze information generated through performance assessment. The ability to make decisions based on the analysis of performance data is the cornerstone of performance management; this analysis yields information that indicates whether expected outcomes for the project are being achieved by the contractor.

1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach migrates away from scrutiny of compliance with the processes and practices used to achieve the outcome. A performance-based approach enables the contractor to play a large role in how the work is performed, as long as the proposed processes are within the stated constraints.

The only exceptions to process reviews are those required by law (federal, state, and local) and compelling business situations, such as safety and health. A “results” focus provides the contractor flexibility to continuously improve and innovate over the course of the contract as long as the critical outcomes expected are being achieved and/or the desired performance levels are being met.

1.3 Performance Management Strategy

1.3.1 The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QC) program. QC is work output, not workers, and therefore includes all work performed under this contract regardless of whether the work is performed by contractor employees or by subcontractors. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. The contractor will develop and implement a performance management system with processes to assess and report its performance to the designated government representative. The contractor’s QCP will set forth the staffing and procedures for self-inspecting the quality, timeliness, responsiveness, customer satisfaction, and other performance requirements in the PWS. This QASP enables the government to take advantage of the contractor’s QC program.

1.3.2 The government representative(s) will monitor performance and review performance reports furnished by the contractor to determine how the contractor is performing against communicated performance objectives. The government will make determination regarding incentives based on performance measurement metric data and notify the contractor of those decisions. The contractor will be responsible for making required changes in processes and practices to ensure performance is managed effectively.

2 ROLES AND RESPONSIBILITIES

2.1 The Contracting Officer

The contracting officer (CO) is responsible for monitoring contract compliance, contract administration, and cost control and for resolving any differences between the observations documented by the contracting officer’s representative (COR) / contracting officer’s technical representative (COTR) and the contractor.

The CO will designate one full-time COR as the government authority for performance management of the IDIQ contract. The CO will designate additional representatives as COR/COTR for each Task Order awarded under the IDIQ, as needed, The number of additional representatives serving as technical inspectors depends on the complexity of the services measured, as well as the contractor’s performance, and must be identified and designated by the CO.

2.2 The Functional Services Manager(s) (FSM)

The FSM serves as the DLA lead for requirements validation in accordance with this Manual and developing, coordinating, & resourcing their service acquisition requirements and overseeing them through the acquisition process which includes budget, cost, schedule, & performance from cradle to grave.

The Customer will designate one full-time FSM to obtain and maintain the required credentials IAW DLAM 5000.74. At a minimum, the FSM is responsible for implementing effective risk management and tracking for acquisition of services to include:

(a) Identification of all known risks.

(b) Key assumptions.

(c) Probability of occurrence.

(d) Consequences of risk occurrence (in terms of cost, schedule, and performance) if not mitigated.

(e) Analysis of mitigation options.

(f) Decisions about actions to mitigate risk, and execution of those actions.

2.3 The Contracting Officer’s Representative / Contracting Officer’s Technical Representative

The contracting officer’s representative (COR) / contracting officer’s technical representative (COTR) is designated in writing by the CO to act as their authorized representative to assist in administering a contract.

COR/COTR limitations are contained in the written appointment letter. The COR/COTR is responsible for technical administration of the project and ensures proper government surveillance of the contractor’s performance. The COR/COTR is not empowered to make any contractual commitments or to authorize any contractual changes on the government’s behalf. Any changes that the contractor deems may affect contract price, terms, or conditions shall be referred to the CO for action. The COR/COTR will have the responsibility for completing QA monitoring forms used to document the inspection and evaluation of the contractor’s work performance. Government surveillance may occur under the inspection of services clause for any service relating to the contract.

3 IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS

The required performance standards and/or quality levels are included in the PWS and in Attachment 1, “Performance Requirements Summary.” If the contractor meets the required service or performance level, it will be paid the monthly invoice amount or amount agreed on in the contract/TO. Failure to meet the required service or performance level will result in a deduction from the monthly invoice amount or amount agreed on in the contract/TO.

4 METHODOLOGIES TO MONITOR PERFORMANCE

4.1 Surveillance Techniques

In an effort to minimize the performance management burden, simplified surveillance methods shall be used by the government to evaluate contractor performance when appropriate. The primary methods of surveillance are:

Random monitoring, which shall be performed by the COTR/COR designated inspector.

100% Inspection – Each month, the COTR/COR, shall review the generated documentation and enter summary results into the Surveillance Activity Checklist.

Periodic Inspection – COTR/COR typically performs the periodic inspection on a monthly basis.

4.2 Customer Feedback

The contractor is expected to establish and maintain professional communication between its employees and customers. The primary objective of this communication is customer satisfaction. Customer satisfaction is the most significant external indicator of the success and effectiveness of all services provided and can be measured through customer complaints.

Performance management drives the contractor to be customer focused through initially and internally addressing customer complaints and investigating the issues and/or problems but the customer always has the option to communicate complaints to the COR/COTR, as opposed to the contractor.

Customer complaints, to be considered valid, must set forth clearly and in writing the detailed nature of the complaint, must be signed, and must be forwarded to the COTR/COR. The COTR/COR will accept those customer complaints and investigate using the Quality Assurance Monitoring Form – Customer Complaint Investigation, identified in Attachment 3.

Customer feedback may also be obtained either from the results of formal customer satisfaction surveys or from random customer complaints.

4.3 Acceptable Quality Levels

The acceptable quality levels (AQLs) included in Attachment 1, Performance Requirements Summary Table, for contractor performance are structured to allow the contractor to manage how the work is performed while providing negative incentives for performance shortfalls. For certain critical activities such as those involving quality assurance and timeliness, the desired performance level is established at 100 percent. Other levels of performance are keyed to the relative importance of the task to the overall mission performance of the DLA Enterprise FPCS.

5 QUALITY ASSURANCE DOCUMENTATION

5.1 The Performance Management Feedback Loop

The performance management feedback loop begins with the communication of expected outcomes.

Performance standards are expressed in the PWS and are assessed using the performance monitoring techniques shown in Attachment 1.

5.2 Monitoring Forms

The government’s QA surveillance, accomplished by the COR/COTR, will be reported using the monitoring form in Attachment 2. The forms, when completed, will document the government’s assessment of the contractor’s performance under the contract to ensure that the required results quality assurance and timeliness are being achieved.

5.2.1 The COR/COTR will retain a copy of all completed QA surveillance forms.

6 ANALYSIS OF QUALITY ASSURANCE ASSESSMENT

6.1 Determining Performance

6.1.1 Government shall use the monitoring methods cited to determine whether the performance standards/service levels/AQLs have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels. Failure to meet the AQL may result in a deduction from the monthly payment, using the deduction percentages shown in Attachment 1.

6.2 Reporting

6.2.1 At the end of each month, the COR/COTR/FSM will prepare a written report for the summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report, which includes the contractor’s submitted monthly report and the completed quality assurance monitoring forms (Attachment 2), will become part of the QA documentation. It will enable the government to demonstrate whether the contractor is meeting the stated objectives and/or performance standards, including cost/technical/scheduling objectives.

6.3 Reviews and Resolution

6.3.1 The COR/COTR may require the contractor’s project manager, or a designated alternate, to meet with the COR/COTR and other government IPT personnel as deemed necessary to discuss performance evaluation. The COR/COTR will define a frequency of in-depth reviews with the contractor, including appropriate self-assessments by the contractor; however, if the need arises, the contractor will meet with the COR/COTR as often as required or per the contractor’s request. The agenda of the reviews may include:

Monthly performance assessment data and trend analysis

Issues and concerns of both parties

Projected outlook for upcoming months and progress against expected trends, including a corrective action plan analysis

Recommendations for improved efficiency and/or effectiveness

Issues arising from the performance monitoring processes

6.3.2 The COR/COTR must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.

6.3.3 The IDIQ COR and Task Order COR and COTR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service levels, procedures, and metrics will be incorporated as a contract modification at the convenience of the CO.

ATTACHMENT 1:

Performance standards and ratings are designed to determine if performance exceeds, meets, or does not meet a given metric and acceptable quality level. The application of these performance ratings or failure of the Government to apply these performance ratings does not waive any of the Government’s rights to damages under this contract.

Based on the general acceptance criteria and goals, the Contractor will be given a monthly rating by the COR/COTR of Exceptional, Very Good, Satisfactory, Marginal, or Unsatisfactory. Performance Payments will be applied based on these ratings.

a. Exceptional – Performance meets contractual requirements and exceeds many to the government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective. The COR/COTR will make a determination to pay the vendor 100% of the monthly invoice amount.

b. Very Good – Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective. The COR/COTR will make a determination to pay the vendor 100% of the monthly invoice amount.

c. Satisfactory – Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory. The COR/COTR will make a determination to pay the vendor 100% of the monthly invoice amount.

d. Marginal – Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented. The COR/COTR will make a determination to pay the vendor 85% of the monthly invoice amount.

e. Unsatisfactory – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective. Payment for the month will be withheld pending resolution of cure notice(s). Upon satisfactory resolution of issues related to the cure notice(s), payment for the month in question will be made at the Marginally Acceptable rate. If issues are not resolved, no payment will be made. Continual monthly performance at the unacceptable level will be at a level where a termination will be considered if the performance is not improved.

The performance will be rated each month by the COR/COTR and documented on a Monthly Status Report Certification form. These findings will be the basis for the amount paid for that month. The ratings, as described above, will be based on the performance of the offeror on the timeliness and quality of the services provided.

ATTACHMENT 2: SAMPLE QUALITY ASSURANCE

MONITORING FORM

SERVICE or STANDARD:

SURVEY PERIOD:

SURVEILLANCE METHOD (Check):

Random Sampling 100% Inspection Periodic Inspection Customer Complaint

LEVEL OF SURVEILLANCE (Check):

Monthly Quarterly As needed

PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: ______ %

ANALYSIS OF RESULTS:

Observed Service Provider Performance Measurement Rate: ______%

Service Provider’s Performance (Check): Meets Standards

Does Not Meet Standards

Narrative of Performance During Survey Period:

PREPARED BY: ___________________________________ DATE: _________________

1 INTRODUCTION
1.1 Purpose
1.1.1 The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting th...
1.1.2 This QASP defines the roles and responsibilities of all members of the integrated project team (IPT), identifies the performance objectives, defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality a...
1.2 Performance Management Approach
1.2.1 The PWS structures the acquisition around “what” service or quality level is required, as opposed to “how” the contractor should perform the work (i.e., results, not compliance). This QASP will define the performance management approach taken by...
1.2.2 Performance management represents a significant shift from the more traditional quality assurance (QA) concepts in several ways. Performance management focuses on assessing whether outcomes are being achieved and to what extent. This approach mi...
1.3 Performance Management Strategy
1.3.1 The contractor is responsible for the quality of all work performed. The contractor measures that quality through the contractor’s own quality control (QC) program. QC is work output, not workers, and therefore includes all work performed under ...
2 ROLES AND RESPONSIBILITIES
2.1 The Contracting Officer
2.2 The Functional Services Manager(s) (FSM)
2.3 The Contracting Officer’s Representative / Contracting Officer’s Technical Representative
3 IDENTIFICATION OF REQUIRED PERFORMANCE STANDARDS/QUALITY LEVELS
4 METHODOLOGIES TO MONITOR PERFORMANCE
4.1 Surveillance Techniques
4.2 Customer Feedback
4.3 Acceptable Quality Levels
5 QUALITY ASSURANCE DOCUMENTATION
5.1 The Performance Management Feedback Loop
5.2 Monitoring Forms
5.2.1 The COR/COTR will retain a copy of all completed QA surveillance forms.
6 ANALYSIS OF QUALITY ASSURANCE ASSESSMENT
6.1 Determining Performance
6.1.1 Government shall use the monitoring methods cited to determine whether the performance standards/service levels/AQLs have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to sh...
6.2 Reporting
6.2.1 At the end of each month, the COR/COTR/FSM will prepare a written report for the summarizing the overall results of the quality assurance surveillance of the contractor’s performance. This written report, which includes the contractor’s submit...
6.3 Reviews and Resolution
6.3.1 The COR/COTR may require the contractor’s project manager, or a designated alternate, to meet with the COR/COTR and other government IPT personnel as deemed necessary to discuss performance evaluation. The COR/COTR will define a frequency of in...
6.3.2 The COR/COTR must coordinate and communicate with the contractor to resolve issues and concerns regarding marginal or unacceptable performance.
6.3.3 The IDIQ COR and Task Order COR and COTR and contractor should jointly formulate tactical and long-term courses of action. Decisions regarding changes to metrics, thresholds, or service levels should be clearly documented. Changes to service le...
ATTACHMENT 1:
ATTACHMENT 2: SAMPLE QUALITY ASSURANCE MONITORING FORM