This is a pricing template spreadsheet for the DLA Enterprise Fire Protection Control Systems (FPCS) IDIQ contract containing both task order and IDIQ-level pricing sheets. The template covers a base period (5/23/2025 - 5/22/2026) and four option years through 5/22/2030.
The task order pricing sheet includes labor categories like Project Manager (416 hours), Project Superintendent (832 hours), Site Safety and Health Officer (700 hours), Sprinkler Fitter/Pipefitter (2,080 hours), and Fire Alarm System Mechanic/Electrician (2,080 hours), with a not-to-exceed material cost of $130,000 per year. The IDIQ-level pricing includes 17 defined labor categories across 5 task areas with specified hours, including Program Manager (900 hours), Fire Alarm Technician (6,000 hours), Sprinkler Technician (7,045 hours), and various engineering and technical roles, with estimated materials costs ranging from $1.8M to $3.7M per year for a total of approximately $14.7M over the contract period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0005.pdf | ||
| Site Visit Roster.pdf | ||
| RFP Questions from vendor.xlsx | XLSX spreadsheet | |
| Amendment - 0004_Signed.pdf | ||
| Inventory from Host Site.pdf | ||
| Service Call Work Authorization.pdf | ||
| Attachment 2 - Updated FPCS Pricing Sheet.xlsx | XLSX spreadsheet | |
| Attachment 3 - Updated FPCS Eval Factor 3 Sample TO PWS.pdf | ||
| Purdue Level Information.pptx | PPTX presentation | |
| FPCS PWS.pdf | ||
| PWS Acronym List.pdf | ||
| Attachment 8 - FPCS IDIQ_QASP.pdf | ||
| SP4702-24-R-0005 - FPCS OT Pillar.pdf | ||
| Amendment - 0003.pdf | ||
| Amendment - 0002.pdf | ||
| Amendment - 001.pdf | ||
| Attachment 3 - FPCS Eval Factor 3 Sample TO PWS.pdf | ||
| Attachment 1 - FPCS PWS.pdf | ||
| SP4702-24-R-0005 - FPCS OT Pillar.pdf | ||
| Attachment 4 - Cross Reference.xlsx | XLSX spreadsheet | |
| Attachment 7 - Contractor NDA.docx | DOCX document | |
| Attachment 5 - KTR Experience Questionnaire.xlsx | XLSX spreadsheet | |
| Attachment 6 - Key Personnel Resume Template.docx | DOCX document |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TO Pricing Sheet FPCS Maintenance Company Name:
| Base Period (5/23/2025 - 5/22/2026) | |||||
| CLIN | Cost element / Labor Categories | Site | Est Hours | Rate | Total |
| TBD | Project Manager | Contractor | 416 | $ - 0 | |
| TBD | Project Superintendent | Contractor | 832 | $ - 0 | |
| TBD | Site Safety and Health Officer | Contractor | 700 | $ - 0 | |
| TBD | Sprinkler Fitter/Pipefitter | Contractor | 2080 | $ - 0 | |
| TBD | Fire Alarm System Mechanic/Electrician | Contractor | 2080 | $ - 0 | |
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| Add additional appropriate LCATS or DELETE this line. | |||||
| TBD | Est. Material Cost (Not to Exceed) | $130,000.00 | |||
| TOTAL | 6108 |
| Option 1 Period ((5/23/2026 - 5/22/2027) | |||||
| CLIN | Cost element / Labor Categories | Site | Est Hours | Rate | Total |
| TBD | Project Manager | Contractor | 416 | $ - 0 | |
| TBD | Project Superintendent | Contractor | 832 | $ - 0 | |
| TBD | Site Safety and Health Officer | Contractor | 700 | $ - 0 | |
| TBD | Sprinkler Fitter/Pipefitter | Contractor | 2080 | $ - 0 | |
| TBD | Fire Alarm System Mechanic/Electrician | Contractor | 2080 | $ - 0 | |
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Est. Material Cost (Not to Exceed) | $130,000.00 | |||
| TOTAL | 6108 | ||||
| Option 2 Period ((5/23/2027 - 5/22/2028) | |||||
| CLIN | Cost element / Labor Categories | Site | Est Hours | Rate | Total |
| TBD | Project Manager | Contractor | 416 | $ - 0 | |
| TBD | Project Superintendent | Contractor | 832 | $ - 0 | |
| TBD | Site Safety and Health Officer | Contractor | 700 | $ - 0 | |
| TBD | Sprinkler Fitter/Pipefitter | Contractor | 2080 | $ - 0 | |
| TBD | Fire Alarm System Mechanic/Electrician | Contractor | 2080 | $ - 0 | |
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Est. Material Cost (Not to Exceed) | $130,000.00 | |||
| TOTAL | 6108 |
| Option 3 Period ((5/23/2028 - 5/22/2029) | |||||
| CLIN | Cost element / Labor Categories | Site | Est Hours | Rate | Total |
| TBD | Project Manager | Contractor | 416 | $ - 0 | |
| TBD | Project Superintendent | Contractor | 832 | $ - 0 | |
| TBD | Site Safety and Health Officer | Contractor | 700 | $ - 0 | |
| TBD | Sprinkler Fitter/Pipefitter | Contractor | 2080 | $ - 0 | |
| TBD | Fire Alarm System Mechanic/Electrician | Contractor | 2080 | $ - 0 | |
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Est. Material Cost (Not to Exceed) | $130,000.00 | |||
| TOTAL | 6108 | ||||
| Option 4 Period ((5/23/2029 - 5/22/2030) | |||||
| CLIN | Cost element / Labor Categories | Site | Est Hours | Rate | Total |
| TBD | Project Manager | Contractor | 416 | $ - 0 | |
| TBD | Project Superintendent | Contractor | 832 | $ - 0 | |
| TBD | Site Safety and Health Officer | Contractor | 700 | $ - 0 | |
| TBD | Sprinkler Fitter/Pipefitter | Contractor | 2080 | $ - 0 | |
| TBD | Fire Alarm System Mechanic/Electrician | Contractor | 2080 | $ - 0 | |
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Government | $ - 0 | |||
| TBD | Est. Material Cost (Not to Exceed) | $130,000.00 | |||
| TOTAL | 6108 | ||||
| 5-YEAR TOTAL | |||||
| NOTE: No travel expected for this location. |
&F &A
SOURCE SELECTION INFORMATION – SEE FAR 2.101 AND 3.104
IDIQ ROM Summary
| Rought Order of Magnitude | ||||||
| Summary | ||||||
| Base Year | Opt. Year 1 | Opt. Year 2 | Opt. Year 3 | Opt. Year 4 | Total | |
| Labor Total per Year | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Materials (Estimated) | $1,846,519 | $2,942,002 | $3,101,420 | $3,051,302 | $3,752,489 | $ 14,693,732.00 |
| Yearly Totals |
Grand Total
NOTE: No separate reimbursement CLIN for travel, it should be inclued in FFP at the Task Order level.
&F &A
SOURCE SELECTION INFORMATION – SEE FAR 2.101 AND 3.104
IDIQ LCATs - Base
| Base Year 1 | Contractor to fill in green highlighted cells. | ||||
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount | |
| Program Manager | 1, 2, 3, 4, 5 | 900 | $ - 0 | ||
| Project Manager | 1, 2, 3, 4, 5 | 1,350 | $ - 0 | ||
| Quality Control Manager | 1, 2, 3, 4, 5 | 750 | $ - 0 | ||
| Engineer | 2 | 4,075 | $ - 0 | ||
| Inspection and testing technician | 2 | 4,025 | $ - 0 | ||
| Lead Fire Protection Engineer | 2, 3, 4 | 3,475 | $ - 0 | ||
| CADD Specialist | 2, 3, 4, 5 | 4,829 | $ - 0 | ||
| Fire Alarm Technician | 3 | 6,000 | $ - 0 | ||
| Sprinkler Technician | 3, 4 | 7,045 | $ - 0 | ||
| Special Hazards Technician | 3, 4 | 1,720 | $ - 0 | ||
| Fire Systems Engineer | 4 | 1,045 | $ - 0 | ||
| Senior Fire Alarm Technician | 4 | 1,045 | $ - 0 | ||
| Systems Administration | 5 | 517 | $ - 0 | ||
| Network Engineer | 5 | 517 | $ - 0 | ||
| Senior IT Security Engineer | 5 | 707 | $ - 0 | ||
| IT Security Engineer | 5 | 707 | $ - 0 | ||
| Fire Technician | 5 | 58 | $ - 0 |
SUBTOTALS: 38765 $ - 0
add additional labor categories & rates as needed.
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount |
| Safety and Health Program Manager | 1, 2, 3, 4, 5 | TBD | ||
| Site Safety and Health Officer | 2, 3, 4 | TBD | ||
| Sprinkler Fitter | 3, 4 | TBD | ||
| Project Superintendent | 3, 4 | TBD | ||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD |
| SUBTOTALS: | $ - 0 |
| BASE YEAR TOTAL | $ - 0 |
&F &A
SOURCE SELECTION INFORMATION – SEE FAR 2.101 AND 3.104
IDIQ LCATS OPT Y1
| Option Year 1 | Contractor to fill in green highlighted cells. | ||||
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount | |
| Program Manager | 1, 2, 3, 4, 5 | 900 | $ - 0 | ||
| Project Manager | 1, 2, 3, 4, 5 | 1,350 | $ - 0 | ||
| Quality Control Manager | 1, 2, 3, 4, 5 | 750 | $ - 0 | ||
| Engineer | 2 | 4,075 | $ - 0 | ||
| Inspection and testing technician | 2 | 4,025 | $ - 0 | ||
| Lead Fire Protection Engineer | 2, 3, 4 | 3,475 | $ - 0 | ||
| CADD Specialist | 2, 3, 4, 5 | 4,829 | $ - 0 | ||
| Fire Alarm Technician | 3 | 6,000 | $ - 0 | ||
| Sprinkler Technician | 3, 4 | 7,045 | $ - 0 | ||
| Special Hazards Technician | 3, 4 | 1,720 | $ - 0 | ||
| Fire Systems Engineer | 4 | 1,045 | $ - 0 | ||
| Senior Fire Alarm Technician | 4 | 1,045 | $ - 0 | ||
| Systems Administration | 5 | 517 | $ - 0 | ||
| Network Engineer | 5 | 517 | $ - 0 | ||
| Senior IT Security Engineer | 5 | 707 | $ - 0 | ||
| IT Security Engineer | 5 | 707 | $ - 0 | ||
| Fire Technician | 5 | 58 | $ - 0 |
SUBTOTALS: 38765 $ - 0
add additional labor categories & rates as needed.
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount |
| Safety and Health Program Manager | 1, 2, 3, 4, 5 | TBD | ||
| Site Safety and Health Officer | 2, 3, 4 | TBD | ||
| Sprinkler Fitter | 3, 4 | TBD | ||
| Project Superintendent | 3, 4 | TBD | ||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD |
| SUBTOTALS: | $ - 0 |
| OPT YEAR 1 TOTAL | $ - 0 |
&F &A
SOURCE SELECTION INFORMATION – SEE FAR 2.101 AND 3.104
IDIQ LCATS OPT Y2
| Option Year 2 | Contractor to fill in green highlighted cells. | ||||
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount | |
| Program Manager | 1, 2, 3, 4, 5 | 900 | $ - 0 | ||
| Project Manager | 1, 2, 3, 4, 5 | 1,350 | $ - 0 | ||
| Quality Control Manager | 1, 2, 3, 4, 5 | 750 | $ - 0 | ||
| Engineer | 2 | 4,075 | $ - 0 | ||
| Inspection and testing technician | 2 | 4,025 | $ - 0 | ||
| Lead Fire Protection Engineer | 2, 3, 4 | 3,475 | $ - 0 | ||
| CADD Specialist | 2, 3, 4, 5 | 4,829 | $ - 0 | ||
| Fire Alarm Technician | 3 | 6,000 | $ - 0 | ||
| Sprinkler Technician | 3, 4 | 7,045 | $ - 0 | ||
| Special Hazards Technician | 3, 4 | 1,720 | $ - 0 | ||
| Fire Systems Engineer | 4 | 1,045 | $ - 0 | ||
| Senior Fire Alarm Technician | 4 | 1,045 | $ - 0 | ||
| Systems Administration | 5 | 517 | $ - 0 | ||
| Network Engineer | 5 | 517 | $ - 0 | ||
| Senior IT Security Engineer | 5 | 707 | $ - 0 | ||
| IT Security Engineer | 5 | 707 | $ - 0 | ||
| Fire Technician | 5 | 58 | $ - 0 |
SUBTOTALS: 38765 $ - 0
add additional labor categories & rates as needed.
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount |
| Safety and Health Program Manager | 1, 2, 3, 4, 5 | TBD | ||
| Site Safety and Health Officer | 2, 3, 4 | TBD | ||
| Sprinkler Fitter | 3, 4 | TBD | ||
| Project Superintendent | 3, 4 | TBD | ||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD |
| SUBTOTALS: | $ - 0 |
| OPT YEAR 2 TOTAL | $ - 0 |
&F &A
SOURCE SELECTION INFORMATION – SEE FAR 2.101 AND 3.104
IDIQ LCATs OPT Y3
| Option Year 3 | Contractor to fill in green highlighted cells. | ||||
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount | |
| Program Manager | 1, 2, 3, 4, 5 | 900 | $ - 0 | ||
| Project Manager | 1, 2, 3, 4, 5 | 1,350 | $ - 0 | ||
| Quality Control Manager | 1, 2, 3, 4, 5 | 750 | $ - 0 | ||
| Engineer | 2 | 4,075 | $ - 0 | ||
| Inspection and testing technician | 2 | 4,025 | $ - 0 | ||
| Lead Fire Protection Engineer | 2, 3, 4 | 3,475 | $ - 0 | ||
| CADD Specialist | 2, 3, 4, 5 | 4,829 | $ - 0 | ||
| Fire Alarm Technician | 3 | 6,000 | $ - 0 | ||
| Sprinkler Technician | 3, 4 | 7,045 | $ - 0 | ||
| Special Hazards Technician | 3, 4 | 1,720 | $ - 0 | ||
| Fire Systems Engineer | 4 | 1,045 | $ - 0 | ||
| Senior Fire Alarm Technician | 4 | 1,045 | $ - 0 | ||
| Systems Administration | 5 | 517 | $ - 0 | ||
| Network Engineer | 5 | 517 | $ - 0 | ||
| Senior IT Security Engineer | 5 | 707 | $ - 0 | ||
| IT Security Engineer | 5 | 707 | $ - 0 | ||
| Fire Technician | 5 | 58 | $ - 0 |
SUBTOTALS: 38765 $ - 0
add additional labor categories & rates as needed.
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount |
| Safety and Health Program Manager | 1, 2, 3, 4, 5 | TBD | ||
| Site Safety and Health Officer | 2, 3, 4 | TBD | ||
| Sprinkler Fitter | 3, 4 | TBD | ||
| Project Superintendent | 3, 4 | TBD | ||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD |
| SUBTOTALS: | $ - 0 |
| OPT YEAR 3 TOTAL | $ - 0 |
&F &A
SOURCE SELECTION INFORMATION – SEE FAR 2.101 AND 3.104
IDIQ LCATs OPT Y4
| Option Year 4 | Contractor to fill in green highlighted cells. | ||||
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount | |
| Program Manager | 1, 2, 3, 4, 5 | 900 | $ - 0 | ||
| Project Manager | 1, 2, 3, 4, 5 | 1,350 | $ - 0 | ||
| Quality Control Manager | 1, 2, 3, 4, 5 | 750 | $ - 0 | ||
| Engineer | 2 | 4,075 | $ - 0 | ||
| Inspection and testing technician | 2 | 4,025 | $ - 0 | ||
| Lead Fire Protection Engineer | 2, 3, 4 | 3,475 | $ - 0 | ||
| CADD Specialist | 2, 3, 4, 5 | 4,829 | $ - 0 | ||
| Fire Alarm Technician | 3 | 6,000 | $ - 0 | ||
| Sprinkler Technician | 3, 4 | 7,045 | $ - 0 | ||
| Special Hazards Technician | 3, 4 | 1,720 | $ - 0 | ||
| Fire Systems Engineer | 4 | 1,045 | $ - 0 | ||
| Senior Fire Alarm Technician | 4 | 1,045 | $ - 0 | ||
| Systems Administration | 5 | 517 | $ - 0 | ||
| Network Engineer | 5 | 517 | $ - 0 | ||
| Senior IT Security Engineer | 5 | 707 | $ - 0 | ||
| IT Security Engineer | 5 | 707 | $ - 0 | ||
| Fire Technician | 5 | 58 | $ - 0 |
SUBTOTALS: 38765 $ - 0
add additional labor categories & rates as needed.
| Labor Categories | Task Areas | Estimated Number of Hours | Ceiling Labor Rate for CONUS | Amount |
| Safety and Health Program Manager | 1, 2, 3, 4, 5 | TBD | ||
| Site Safety and Health Officer | 2, 3, 4 | TBD | ||
| Sprinkler Fitter | 3, 4 | TBD | ||
| Project Superintendent | 3, 4 | TBD | ||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD | ||||
| TBD |
| SUBTOTALS: | $ - 0 |
| OPT YEAR 4 TOTAL | $ - 0 |
&F &A
SOURCE SELECTION INFORMATION – SEE FAR 2.101 AND 3.104
File details come from the government source that posted it. Updated .