Section 01 45 35 Schedule of Special Inspections.docx

DOCX document 52 KB Posted

Attached to
Y1DA--614-22-700 EHRM Infrastructure Upgrades Construction Memphis TN Federal contract opportunity
Solicitation number
36C77624B0013_1
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document is a Schedule of Special Inspections for a federal construction contract. It details the required inspections and verifications to be performed by a special inspector during the construction of a steel-framed building, including welding, bolting, non-destructive testing, steel deck installation, cold-formed steel framing, concrete placement, masonry construction, and related structural and architectural components.

The related federal contract opportunity is for EHRM Infrastructure Upgrades Construction at the Memphis, TN VA Medical Center. This is a solicitation issued by the Department of Veterans Affairs Technology Acquisition Center Austin. The document does not provide additional details about the specific construction project or contract requirements beyond the inspections outlined in the Schedule.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--614-22-700 EHRM Infrastructure Upgrades Construction Memphis TN, newest first.
File Type Posted
36C77624B0013 Amendment 0004.docx DOCX document
00 01 15 - List of Drawing Sheets.pdf PDF
614-700_Sheet List_20240702.pdf PDF
36C77624B0013 Amendment 0003.docx DOCX document
ENG FORM 4288-R 1-97.pdf PDF
CS501 Addendum _1.pdf PDF
614-700.ET_R21.pdf PDF
S06 - Wage rates Memphis 5.31.24.pdf PDF
Technical Questions Tracking Spreadsheet - Memphis IU Construction 6.20.24.docx DOCX document
S06 - 36C77624B0013 Amendment 0002.docx DOCX document
36C77624B0013 Amendment 0001.docx DOCX document
Site Visit Sign-in Sheets - EHRM Infra - Memphis.pdf PDF
Drawing Vol 1-5-3 Architectural 614-700-AE-20231011.pdf PDF
Drawing Vol 1-9 Electrical 614-700-EP-20231011.pdf PDF
Drawing Vol 1-3 Civil 614-700-CS-20231011.pdf PDF
Site Visit Instructions.docx DOCX document
Wage Rates - Memphis 3.22.24.pdf PDF
VHA ICRA 614-22-700TR-03 EHRM Infrastructure TR Build-Out Level IV - High Risk.pdf PDF
VHA ICRA 614-22-700CD-03 EHRM Infrastructure Cable-Drops Level IV - High Risk.pdf PDF
VHA ICRA 614-22-700CD-02 EHRM Infrastructure Cable-Drops Level III - Medium Risk.pdf PDF
VHA ICRA 614-22-700CD-01 EHRM Infrastructure Cable-Drops Level II - Low Risk.pdf PDF
VHA ICRA 614-22-700TR-01 EHRM Infrastructure TR Build-Out Level II - Low Risk.pdf PDF
Limitations on Subcontracting - Construction.docx DOCX document
Drawing Vol 1-5-4 Architectural 614-700-AE-20231011.pdf PDF
Drawing Vol 1-5-2 Architectural 614-700-AE-20231011.pdf PDF
Drawing Vol 1-1 General 614-700-GI-20231011.pdf PDF
Drawing Vol 1-5-6 Architectural 614-700-AE-20231011.pdf PDF
Drawing Vol 1-7 Fire Protection 614-700-FX-20231011.pdf PDF
Drawing Vol 1-4 Structural 614-700-SF-20231011.pdf PDF
Drawing Vol 2-2 Technology 614-700-TJ-20231011.pdf PDF
VHA ICRA 614-22-700CD-04 EHRM Infrastructure Cable-Drops Level IV - Highest Risk.pdf PDF
VHA ICRA 614-22-700TR-04 EHRM Infrastructure TR Build-Out Level IV - Highest Risk.pdf PDF
VHA PCRA 31May2023-EHRM Infrastructure.pdf PDF
VHA ICRA 614-22-700TR-02 EHRM Infrastructure TR Build-Out Level III - Medium Risk.pdf PDF
Drawing Vol 2-1 Telecommunication 614-700-TN-20231011.pdf PDF
Drawing Vol 1-8 Mechanical 614-700-MH-20231011.pdf PDF
Drawing Vol 1-6 Plumbing 614-700-PL-20231011.pdf PDF
Brand Name Justification Memphis EHRM.pdf PDF
36C77624B0013_1.docx DOCX document
Drawing Vol 1-5-1 Architectural 614-700-AE-20231011.pdf PDF
Drawing Vol 1-5-5 Architectural 614-700-AE-20231011.pdf PDF
Specifications - Final.pdf PDF
Drawing Vol 1-2 Hazardous 614-700-HA-20231011.pdf PDF
Section 01 45 35 Statement of SI Template.xlsx XLSX spreadsheet
Show all 44

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF SPECIAL INSPECTIONS (01 45 35) REVISED FOR IBC 2015 ON 9/30/16

SCHEDULE OF SPECIAL INSPECTIONS

Reference 01 45 35 for all requirements not noted as part of this schedule.

INSPECTION DEFINITIONS:

PERFORM: Perform these tasks for each weld, fastener or bolted connection, and noted verification.

OBSERVE: Observe these items randomly during the course of each work day to insure that applicable requirements are being met. Operations need not be delayed pending these inspections at contractor’s risk.

DOCUMENT: Document, with a report, that the work has been performed in accordance with the contract documents. This is in addition to any other reports required in the Special Inspections guide specification.

CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.

DESIGNER NOTES (to be deleted after reviewing):

1. This schedule contains minimum requirements. Do not delete applicable inspection tasks unless notes in blue indicate it is acceptable to do so.

2. Blue text = designers notes. The designer must review and edit all blue text in this schedule prior to inserting this schedule into the special inspections spec (UFGS 01 45 35).

3. Check section boxes with ANY inspection tasks applicable to your project. You may choose to delete unchecked sections or leave them in the scheduled unchecked.

4. Individual rows/tasks that that are not applicable to the project may be left in the section, as the inspector can determine whether they occur/apply (e.g. metal trusses in the light gauge framing section for example).

5. Design discipline sections are color coded for easier reference by designers. This schedule does NOT need to be printed in color.

6. When finished editing, delete this note box and save this schedule as a PDF and insert into the project specifications (special inspections section).

A. STRUCTURAL - STEEL – WELDING SECTION

THIS SECTION APPLICABLE IF BOX IS CHECKED: ☒

STEEL INSPECTION PRIOR TO WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 360-10: Table C-N5.4-1

TASK
INSPECTION TYPE[footnoteRef:1] [1: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

1. Verify that the welding procedures specification (WPS) is available
PERFORM
2. Verify manufacturer certifications for welding consumables are available
PERFORM
3. Verify material identification
PERFORM
Type and grade.
4. Welder Identification System
PERFORM
The fabricator or erector, as applicable, shall maintain a system by which a welder who has welded a joint or member can be identified. Stamps, if used, shall be the low-stress type.
5. Fit-up of groove welds (including joint geometry)
OBSERVE
· Joint preparation

· Dimensions (alignment, root opening, root face, bevel)

· Cleanliness (condition of steel surfaces)

· Tacking (tack weld quality and location)

· Backing type and fit (if applicable)

6. Configuration and finish of access holes
OBSERVE
7. Fit-up of fillet welds
OBSERVE
· Dimensions (alignment, gaps at root)

· Cleanliness (condition of steel surfaces)

· Tacking (tack weld quality and location)

STEEL INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 360-10: Table C-N5.4-2

TASK
INSPECTION TYPE
DESCRIPTION
8. Use of qualified welders
PERFORM
Welding by welders, welding operators, and tack welders who are qualified in conformance with requirements.
9. Control and handling of welding consumables
OBSERVE
· Packaging

· Electrode atmospheric exposure control

10. No welding over cracked tack welds
OBSERVE
11. Environmental conditions
OBSERVE
· Wind speed within limits

· Precipitation and temperature

12. Welding Procedures Specification followed
OBSERVE
· Settings on welding equipment

· Travel speed

· Selected welding materials

· Shielding gas type/flow rate

· Preheat applied

· Interpass temperature maintained (min./max.)

· Proper position (F, V, H, OH)

· Intermix of filler metals avoided

13. Welding techniques
OBSERVE
· Interpass and final cleaning

· Each pass within profile limitations

· Each pass meets quality requirements

A.

STRUCTURAL - STEEL – WELDING SECTION (CONTINUED)

STEEL INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 2015 1705.2.1, AISC 360-10: Table C-N5.4-3

TASK
INSPECTION TYPE [footnoteRef:2] [2: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.]

DESCRIPTION

14. Welds cleaned
OBSERVE
15. Size, length, and location of all welds
PERFORM
Size, length, and location of all welds conform to the requirements of the detail drawings.
16. Welds meet visual acceptance criteria
PERFORM AND

DOCUMENT

· Crack prohibition

· Weld/base-metal fusion

· Crater cross section

· Weld profiles

· Weld size

· Undercut

· Porosity

17. Arc strikes
PERFORM
18. k-area
PERFORM
When welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, visually inspect the web k-area for cracks. (AISC 360 – Table N5.4-3)
19. Backing removed, weld tabs removed and finished, and fillet welds added where required
PERFORM
20. Repair activities
PERFORM AND DOCUMENT
21. Document acceptance or rejection of welded joint or member
PERFORM

END SECTION

B. STRUCTURAL - STEEL – BOLTING SECTION

THIS SECTION APPLICABLE IF BOX IS CHECKED: ☒

STEEL INSPECTION TASKS PRIOR TO BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 360-10: Table C-N5.6-1

TASK
INSPECTION TYPE [footnoteRef:3] [3: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.]

DESCRIPTION

1. Manufacture’s certifications available for fastener materials
PERFORM
2. Fasteners marked in accordance with ASTM requirements
OBSERVE
3. Proper fasteners selected for joint detail (grade, type, bolt length if threads are to be excluded from shear plane)
OBSERVE
4. Proper bolting procedure selected for joint detail
OBSERVE
5. Connecting elements, including appropriate faying surface condition and hole preparation, if specified, meet applicable requirements
OBSERVE
6. Proper storage provided for bolts, nuts, washers, and other fastener components
OBSERVE

STEEL INSPECTION TASKS DURING BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 360-10: Table C-N5.6-2

TASK
INSPECTION TYPE 1
DESCRIPTION
7. Fastener assemblies of suitable condition, placed in all holes and washers (if required) are positioned as required
OBSERVE
8. Joint brought to the snug-tight condition prior to pretensioning operation
OBSERVE
9. Fastener component not turned by the wrench prevented from rotating
OBSERVE
10. Bolts are pretensioned in accordance with RCSC Specification, progressing systematically from the most rigid point toward the free edges
OBSERVE

STEEL INSPECTION TASKS AFTER BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 360-10: Table C-N5.6-3

TASK
INSPECTION TYPE 1
DESCRIPTION
11. Document acceptance or rejection of all bolted connections
DOCUMENT

C. STRUCTURAL - STEEL - NON DESTRUCTIVE TESTING SECTION

NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 360-10: Section N5.5

TASK
INSPECTION TYPE [footnoteRef:4] [4: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

1. Use of qualified nondestructive testing personnel
PERFORM
Visual weld inspection and nondestructive testing (NDT) shall be conducted by personnel qualified in accordance with AWS D1.8 clause 7.2
2. CJP groove welds
OBSERVE
[NOTE: DOR must delete this row if section D (SEISMIC PROVISIONS SECTION) is checked]

Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 20% of CJP groove welds for materials greater than 5/16” (8mm) thick. Testing rate must be increased to 100% if greater than 5% of welds tested have unacceptable defects.

3. Welded joints subject to fatigue
OBSERVE
Dye penetrant testing (DT) and Ultrasonic testing (UT) shall be performed on 100% of welded joints identified on contract drawings as being subject to fatigue.
4. Weld tab removal sites
OBSERVE
At the end of welds where weld tabs have been removed, magnetic particle testing shall be performed on the same beam-to-column joints receiving UT

D. STRUCTURAL - STEEL – AISC 341 REQUIREMENTS (SEISMIC PROVISIONS) SECTION

NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 341-10: Section J6.2

TASK
INSPECTION TYPE [footnoteRef:5] [5: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.]

DESCRIPTION

[NOTE: DOR may uncheck this section for projects NOT designed in accordance with AISC 341 (Seismic Provisions) or for projects designed according to AISC 341, but using an R value equal to 3]

5. CJP groove welds
OBSERVE
Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 100% of CJP groove welds for materials greater than 5/16” thick (8mm).
6. Beam cope and access hole.
OBSERVE
At welded splices and connections, thermally cut surfaces of beam copes and access holes shall be tested using magnetic particle testing (MT) or dye penetrant testing (DT), when the flange thickness exceeds 1 1/2 in. for rolled shapes, or when the web thickness exceeds 1 1/2 in. for built-up shapes.
7. K-area NDT (AISC 341)
PERFORM
Where welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, the web shall be tested for cracks using magnetic particle testing (MT). The MT inspection area shall include the k-area base metal within 3-inches of the weld. The MT shall be performed no sooner than 48 hours following completion of the welding.
8. Placement of reinforcing or contouring fillet welds
DOCUMENT

E. STRUCTURAL - STEEL - COMPOSITE CONSTRUCTION [footnoteRef:6] [6: See Concrete Construction Section for all concrete related inspection of composite steel construction.]

COMPOSITE CONSTRUCTION PRIOR TO PLACING CONCRETE – VERIFY THE FOLLOWING ARE IN COMPLIANCE IBC 1705.2.1, AISC 360-10: Table N6.1, AISC 341-10: Table J9-1

TASK
INSPECTION TYPE 2
DESCRIPTION
1. Placement and installation of steel headed stud anchors
PERFORM
2. Material identification of reinforcing steel (Type/Grade)
OBSERVE
3. Determination of carbon equivalent for reinforcing steel other than ASTM A706
OBSERVE
4. Proper reinforcing steel size, spacing, clearances, support, and orientation
OBSERVE
5. Reinforcing steel has been tied and supported as required
OBSERVE

F. STRUCTURAL - STEEL - OTHER INSPECTIONS

OTHER STEEL INSPECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.1, AISC 341-10: Tables J8-1 & J10-1

TASK
INSPECTION TYPE [footnoteRef:7] [7: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.]

DESCRIPTION

1. Anchor rods and other embedments supporting structural steel
PERFORM
Verify the diameter, grade, type, and length of the anchor rod or embedded item, and the extent or depth of embedment prior to placement of concrete.
2. Fabricated steel or erected steel frame
OBSERVE
Verify compliance with the details shown on the construction documents, such as braces, stiffeners, member locations and proper application of joint details at each connection.
3. Reduced beam sections (RBS) where/if occurs
DOCUMENT
· Contour and finish

· Dimensional tolerances

4. Protected zones
DOCUMENT
No holes or unapproved attachments made by fabricator or erector
5. H-piles where/if occurs
DOCUMENT
No holes or unapproved attachments made by the responsible contractor

G. STRUCTURAL - COLD-FORMED METAL DECK - PLACEMENT SECTION

METAL DECK INSPECTION PRIOR TO DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.1

TASK
INSPECTION TYPE [footnoteRef:8] [8: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.]

DESCRIPTION

1. Verify compliance of materials (deck and all deck accessories) with construction documents, including profiles, material properties, and base metal thickness
PERFORM
2. Document acceptance or rejection of deck and deck accessories
DOCUMENT

METAL DECK INSPECTION DURING DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.2

TASK
INSPECTION TYPE 1
DESCRIPTION
3. Verify compliance of deck and all deck accessories installation with construction documents
PERFORM
4. Verify deck materials are represented by the mill certifications that comply with the construction documents
PERFORM
5. Document acceptance or rejection of installation of deck and deck accessories
DOCUMENT

METAL DECK INSPECTION AFTER DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.3

TASK
INSPECTION TYPE 1
DESCRIPTION
6. Welding procedure specification (WPS) available
PERFORM
7. Manufactures certifications for welding consumables available
OBSERVE
8. Material identification (type/grade)
OBSERVE
9. Check welding equipment
OBSERVE

H. STRUCTURAL - COLD-FORMED METAL DECK – WELDING SECTION

METAL DECK INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

SDI QA/QC-2011, Appendix 1, Table 1.4

TASK
INSPECTION TYPE [footnoteRef:9] [9: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.]

DESCRIPTION

1. Use of qualified welders
OBSERVE
2. Control and handling of welding consumables
OBSERVE
3. Environmental conditions (wind speed, moisture, temperature)
OBSERVE
4. WPS followed
OBSERVE

METAL DECK INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE

SDI QA/QC-2011, Appendix 1, Table 1.5

TASK
INSPECTION TYPE 1
DESCRIPTION
5. Verify size and location of welds, including support, sidelap, and perimeter welds.
PERFORM
6. Welds meet visual acceptance criteria
PERFORM
7. Verify repair activities
PERFORM
8. Document acceptance or rejection of welds
DOCUMENT

I. STRUCTURAL - COLD-FORMED METAL DECK – FASTENING SECTION

METAL DECK INSPECTION BEFORE MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.6

TASK
INSPECTION TYPE 1
DESCRIPTION
1. Manufacturer installation instructions available for mechanical fasteners
OBSERVE
2. Proper tools available for fastener installation
OBSERVE

METAL DECK INSPECTION DURING MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.7

TASK
INSPECTION TYPE 1
DESCRIPTION
3. Fasteners are positioned as required
OBSERVE
4. Fasteners are installed in accordance with manufacturer's instructions
OBSERVE

METAL DECK INSPECTION AFTER MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.8

TASK
INSPECTION TYPE [footnoteRef:10] [10: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.]

DESCRIPTION

5. Check spacing, type, and installation of support fasteners
PERFORM
6. Check spacing, type, and installation of sidelap fasteners
PERFORM
7. Check spacing, type, and installation of perimeter fasteners
PERFORM
8. Verify repair activities
PERFORM
9. Document acceptance or rejection of mechanical fasteners
DOCUMENT

J. STRUCTURAL - LIGHT GAUGE STEEL FRAMING AND/OR LIGHT GAUGE TRUSSES SECTION

LIGHT GAUGE STEEL CONSTRUCTION AND CONNECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.2.2, 1705.11.2, 1705.11.3, UFC 4 023 03

TASK
INSPECTION TYPE[footnoteRef:11] [11: PERFORM:Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

1. Trusses spanning 60-feet or greater where/if applies
PERFORM
Verify that temporary and permanent truss restraint/bracing is installed in accordance with approved truss submittal package.
2. Welded connections (seismic and/or wind resisting system)
OBSERVE
Visually inspect all welds composing part of the main wind or seismic force resisting system, including shearwalls, braces, collectors (drag struts), and hold-downs.

[NOTE: DOR must identify critical wind and/or seismic force resisting welds in the contract drawings so that the special inspector can confirm compliance.]

3. Connections (seismic and/or wind resisting system)
OBSERVE
Visually inspect all screw attachment, bolting, anchoring and other fastening of components within the main wind or seismic force resisting system, including roof deck, roof framing, exterior wall covering, wall to roof/floor connections, braces, collectors (drag struts) and hold-downs.

[NOTE: DOR must identify critical wind and/or seismic force resisting connection/fastener components in the contract drawings so that the special inspector can confirm compliance.]

4. Cold-formed steel (progressive collapse resisting system where/if applies)
OBSERVE
Verify proper welding operations, screw attachment, bolting, anchoring and other fastening of components within the progressive collapse resisting system, including horizontal tie force elements, vertical tie force elements and bridging elements (UFC 4 023 03).

[NOTE: DOR must identify critical progressive collapse resisting connection/fastener components in the contract drawings so that the special inspector can confirm compliance.]

K. STRUCTURAL - OPEN-WEB STEEL JOISTS SECTION

OPEN-WEB STEEL JOISTS AND JOIST GIRDERS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC TABLE 1705.2.3

TASK
INSPECTION TYPE 1
DESCRIPTION
1. Installation of open-web steel joists and joist girders
OBSERVE
· End connections – welded or bolted

· Bridging – horizontal and diagonal

L. STRUCTURAL - CONCRETE CONSTRUCTION SECTION

CONCRETE CONSTRUCTION, INCLUDING COMPOSITE DECK – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC TABLE 1705.3 (ACI 318 REFERENCES NOTED IN IBC TABLE)

TASK
INSPECTION TYPE [footnoteRef:12] [12: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.
CONTINUOUS:Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.]

DESCRIPTION

1. Inspect reinforcement, including prestressing tendons, and verify placement.
OBSERVE
Verify prior to placing concrete that reinforcing is of specified type, grade and size; that it is free of oil, dirt and unacceptable rust; that it is located and spaced properly; that hooks, bends, ties, stirrups and supplemental reinforcement are placed correctly; that lap lengths, stagger and offsets are provided; and that all mechanical connections are installed per the manufacturer’s instructions and/or evaluation report.
2. Reinforcing bar welding
OBSERVE
· Verify weldability of reinforcing bars other than ASTM A 706

· Inspect single-pass fillet welds, maximum 5/16” in accordance with AWS D1.4

3. All other welding
CONTINUOUS
Visually inspect all welds in accordance with AWS D1.4
4. Cast in place anchors and post installed drilled anchors (downward inclined)
OBSERVE
Verify prior to placing concrete that cast in place anchors and post installed drilled anchors have proper embedment, spacing and edge distance.
5. Post-installed adhesive anchors in horizontal or upward inclined orientations
CONTINUOUS AND DOCUMENT
· Inspect as required per approved ICC-ES report

· Verify that installer is certified for installation of horizontal and overhead installation applications

· Inspect proof loading as required by the contract documents (IBC Table 1705.3, 4)

6. Verify use of required mix design
OBSERVE
Verify that all mixes used comply with the approved construction documents(IBC Table 1705.3, 5)
7. Prior to concrete placement, fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete
CONTINUOUS
At the time fresh concrete is sampled to fabricate specimens for strength test verify these tests are performed by qualified technicians.
8. Inspect concrete and/or shotcrete placement for proper application techniques
CONTINUOUS
Verify proper application techniques are used during concrete conveyance and depositing avoids segregation or contamination. Verify that concrete is properly consolidated.
9. Verify maintenance of specified curing temperature and technique
OBSERVE
Inspect curing, cold weather protection, and hot weather protection procedures.
10. Pre-stressed concrete
CONTINUOUS
Verify application of prestressing forces and grouting of bonded prestressing tendons.

CONTINUED ON FOLLOWING PAGE

K. STRUCTURAL - CONCRETE CONSTRUCTION (CONTINUED)

CONCRETE CONSTRUCTION, INCLUDING COMPOSITE DECK – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC TABLE 1705.3 (ACI 318 REFERENCES NOTED IN IBC TABLE)

TASK
INSPECTION TYPE [footnoteRef:13] [13: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT:Document in a report that the work has been performed as required. This is in addition to all other required reports.
CONTINUOUS:Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.]

DESCRIPTION

11. Inspect erection of precast concrete members
OBSERVE
12. Verify in-situ concrete strength, prior to stressing of tendons in post-tensioned concrete and prior to removal of shores and forms from beams and structural slabs.
OBSERVE
13. Inspect formwork for shape, location and dimensions of the concrete member being formed.
OBSERVE

M. STRUCTURAL - MASONRY CONSTRUCTION SECTION (ALL RISK CATEGORIES)

MASONRY CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE AT START OF CONSTRUCTION

IBC 1705.4 (ACI 530-13 TABLE 3.1.2 & 3.1.3)

TASK
INSPECTION TYPE [footnoteRef:14] [14: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
CONTINUOUS:Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.]

DESCRIPTION

1. Compliance with approved submittals prior to start
OBSERVE
2. Proportions of site-mixed mortar.
OBSERVE
3. Grade and type of reinforcement, anchor bolts, and prestressing tendons and anchorages
OBSERVE
4. Prestressing technique
OBSERVE
5. Properties of thin bed mortar for AAC masonry
OBSERVE

MASONRY CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE PRIOR TO GROUTING

IBC 1705.4 (ACI 530-13 TABLE 3.1.2 & 3.1.3)

TASK
INSPECTION TYPE 1
DESCRIPTION
6. Grout space
OBSERVE

CONTINUOUS

[NOTE: DOR must either delete ‘OBSERVE’ for Risk Category IV/V, or delete ‘CONTINUOUS’ for Risk Categories I/II/ III]

7. Proportions of site-prepared grout and prestressing grout for bonded tendons
OBSERVE
8. Proportions of site-mixed grout and prestressing grout for bonded tendons
OBSERVE
9. Placement of masonry units and mortar joints
OBSERVE
10. Welding of reinforcement
CONTINUOUS

MASONRY CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE DURING CONSTRUCTION

IBC 1705.4 (ACI 530-13 TABLE 3.1.2 & 3.1.3)

TASK
INSPECTION TYPE 1
DESCRIPTION
11. Size and location of structural elements is in compliance
OBSERVE
12. Preparation, construction, and protection of masonry during cold weather (temperature below 40oF (4.4oc) or hot weather (temp above 90oF (32.2oC))
OBSERVE
13. Application and measurement of prestressing force
CONTINUOUS
14. Placement of grout and prestressing grout for bonded tendons
CONTINUOUS
15. Placement of AAC masonry units and construction of thin bed mortar joints
CONTINUOUS
Continuous for first 5000 square feet only (465 square meters).
16. Observe preparation of grout specimens, mortar specimens, and/or prisms
OBSERVE
17. Type, size and placement of reinforcement, connectors, anchor bolts and prestressing tendons and anchorages, including details of anchorage of masonry to structural members, frames, or other construction
OBSERVE

CONTINUOUS

[NOTE: DOR must either delete ‘OBSERVE’ for Risk Category IV/V, or delete ‘CONTINUOUS’ for Risk Categories I/II/III]

N. STRUCTURAL - WOOD CONSTRUCTION – SPECIALTY ITEMS SECTION

WOOD CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.5

TASK
INSPECTION TYPE [footnoteRef:15] [15: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

1. High-load diaphragms where applicable
OBSERVE
Verify thickness and grade of sheathing, size of framing members at panel edges, nail diameters and length, and the number of fastener lines and that fastener spacing is per approved contract documents.
2. Metal-plate connected wood trusses spanning 60 feet or greater
OBSERVE
Verify that the temporary installation restraint/bracing and the permanent individual truss member restraint/bracing are installed in accordance with the approved truss submittal package

O. STRUCTURAL - WOOD CONSTRUCTION - SEISMIC & WIND SECTION

WOOD CONSTRUCTION SEISMIC AND WIND – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.5

TASK
INSPECTION TYPE 1
DESCRIPTION

[NOTE: DOR may uncheck this section where sheathing nailing/fasteners (both shearwall and roof) are consistently greater than 4” on center, or if the design wind speed is less than 110 mph (49 meters/sec) AND the seismic design category is A or B]

1. Nailing, bolting, anchoring and other fastening of elements of the main wind/seismic force-resisting system
OBSERVE
Includes connectors for: shearwall sheathing, roof/floor sheathing, drag struts/collectors, braces, hold downs, roof and floor framing connections to exterior walls.

P. STRUCTURAL – ISOLATION AND ENERGY DISSIPATION SYSTEMS SECTION

ISOLATION AND ENERGY DISSIPATION SYSTEMS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC TABLE 1705.2.3

TASK
INSPECTION TYPE 1
DESCRIPTION
1. Fabrication and installation
OBSERVE
Verify that fabrication and installation of isolator units and energy dissipation devices conform to manufacturer’s recommendations and approved construction documents

Q. GEOTECHNICAL - SOILS INSPECTION SECTION

SOILS INSPECTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.6

TASK
INSPECTION TYPE [footnoteRef:16] [16: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
CONTINUOUS:Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.]

DESCRIPTION

1. Materials below shallow foundations are adequate to achieve the design bearing capacity.
OBSERVE
2. Excavations are extended to proper depth and have reached proper material
OBSERVE
3. Verify use of proper materials, densities and lift thicknesses during placement and compaction of compacted fill
CONTINUOUS
4. Prior to placement of compacted fill, inspect subgrade and verify that site has been prepared properly.
OBSERVE
During fill placement, the special inspector shall verify that proper materials and procedures are used in accordance with the provisions of the approved geotechnical report

R. GEOTECHNICAL - DRIVEN DEEP FOUNDATION ELEMENTS SECTION

DEEP DRIVEN FOUNDATION CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.5

TASK
INSPECTION TYPE 1
DESCRIPTION
1. Verify element materials, sizes and lengths comply with requirements
CONTINUOUS
2. Inspect driving operations and maintain complete and accurate records for each element
CONTINUOUS
3. Verify placement locations and plumbness, confirm type and size of hammer, record number of blows per foot of penetration, determine required penetrations to achiever design capacity, record tip and butt elevations and document ay damage to foundation element
CONTINUOUS

S. GEOTECHNICAL - HELICAL PILE FOUNDATIONS SECTION

HELICAL PILE FOUNDATIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.9

TASK
INSPECTION TYPE 1
DESCRIPTION
1. Record installation equipment used, pile dimensions, tip elevations, final depth, final installation torque and other pertinent installation data. The approved geotechnical report and the contract documents shall be used to determine compliance
CONTINUOUS

T. GEOTECHNICAL - CAST IN PLACE DEEP FOUNDATION ELEMENTS SECTION

CAST IN PLACE DEEP FOUNDATION ELEMENTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.8

TASK
INSPECTION TYPE [footnoteRef:17] [17: CONTINUOUS:Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.]

DESCRIPTION

1. Inspect drilling operations and maintain complete and accurate records for each element.
CONTINUOUS
2. Verify placement locations and plumbness, confirm element diameters, bell diameters (if applicable), lengths, embedment into bedrock (if applicable and adequate end-bearing strata capacity. Record concrete or grout volumes
CONTINUOUS

U. FIRE PROTECTION - SPRAYED FIRE-RESISTANT MATERIALS SECTION

SPRAYED FIRE RESISTANT MATERIALS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.14

TASK
INSPECTION TYPE [footnoteRef:18] [18: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

1. Surface condition
OBSERVE

Prior to application confirm that surface has been prepared per the approved fire-resistance design and manufacturer’s instructions.

2. Application
OBSERVE
Prior to application confirm that the substrate meets the minimum ambient temperature per the approved fire-resistance design and manufacturer’s instructions.
3. Material thickness
OBSERVE
Verify that the thickness of the SFRM to structural elements is not less than the thickness require by the fire-resistant design in more that 10 percent of the measurement, but in no case less than minimum allowable thickness required by 1705.14.
4. Material density
OBSERVE
Verify that the thickness of the SFRM to structural elements is not less than the thickness require by the fire-resistant design in more than 10 percent of the measurement, but in no case less than minimum allowable thickness required by IBC 1705.14.5
5. Bond strength
OBSERVE
Verify cohesive/adhesive bond strength of the cured SFRM applied to the structural element is not less than 150psf and according to IBC 1705.14.6

V. FIRE PROTECTION - MASTIC AND INTUMESCENT COATINGS SECTION

THIS SECTION APPLICABLE IF BOX IS CHECKED: ☒

MASTIC AND INTUMESCENT FIRE-RESISTANT COATINGS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.15

TASK
INSPECTION TYPE 1
DESCRIPTION
1. Surface preparation
OBSERVE

Inspections shall be performed in accordance with AWCI 12-B and the contract documents

W. FIRE PROTECTION – FIRE RESISTANT PENETRATIONS AND JOINTS SECTION

THIS SECTION APPLICABLE IF BOX IS CHECKED: ☒

FIRE RESISTANT PENETRATIONS AND JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.17

TASK
INSPECTION TYPE 1
DESCRIPTION
1. Inspections of penetration firestop systems conducted in accordance with ASTM E 2174.
OBSERVE

[NOTE: This section applies to Risk Category III, IV, & V only. DOR may choose to uncheck this section where project is assigned to Risk Category I or II. Confirm Risk Category with Structural Engineer]

2. Inspections of fire-resistant joint systems conducted in accordance with ASTM E 2393
OBSERVE

X. FIRE PROTECTION – SMOKE CONTROL SECTION

THIS SECTION APPLICABLE IF BOX IS CHECKED: ☒

SMOKE CONTROL – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.17

TASK
INSPECTION TYPE [footnoteRef:19] [19: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

1. Verify device locations and perform leakage testing
OBSERVE

Perform during erection of ductwork and prior to concealment

2. Pressure difference testing, flow measurements and detection and control verification
OBSERVE

Perform prior to occupancy and after sufficient completion

Y. ARCHITECTURAL - EXTERIOR INSULATION AND FINISH SYSTEMS SECTION

EXTERIOR INSULATION AND FINISH SYSTEMS (EIFS) – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.16

TASK
INSPECTION TYPE [footnoteRef:20] [20: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

1. Water resistive barrier coating applied over a sheathing substrate.
OBSERVE

Verify that water resistive barrier coating complies with ASTM E 2570.

[NOTE: not applicable to masonry or concrete wall applications. Uncheck this section in those cases]

Z. ARCHITECTURAL – ARCHITECTURAL COMPONENTS

ARCHITECTURAL COMPONENTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE

IBC 1705.12.5, 1705.12.7

TASK
INSPECTION TYPE 1
DESCRIPTION

[NOTE: This section is not applicable to Seismic Design Categories A, B, & C. Uncheck this section if one of those categories applies. Confirm Seismic Design Category with the structural engineer]

1. Erection and fastening of exterior cladding and interior and exterior veneer.
OBSERVE

Verify appropriate materials, fasteners and attachment at commencement of work and at completion. Inspector Note: Inspection not required if height is less than 30 feet or weight is less than 5psf

2. Interior and exterior non-load bearing walls
OBSERVE
Verify appropriate materials, fasteners and attachment at commencement of work and at completion. Inspector Note: Inspection not required if height is less than 30 feet. Also, Interior non-load bearing walls need not be inspected if weighing less than 15psf
3. Access floors
OBSERVE
Verify that anchorage complies with approved construction documents. Inspection of post-installed anchors shall comply with approved ICC-ES report
4. Storage racks
OBSERVE
Verify that anchorage complies with approved construction documents. Inspection of post-installed anchors shall comply with approved ICC-ES report. Inspector Note: Not required for racks less than 8 feet in height

AA. PLUMBING/MECHANICAL/ELECTRICAL DESIGNATED SEISMIC SYSTEMS SECTION

PLUMBING, MECHANICAL AND ELECTRICAL - DESIGNATED SEISMIC SYSTEMS

IBC 1705.12.4

TASK
INSPECTION TYPE [footnoteRef:21] [21: OBSERVE:Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.]

DESCRIPTION

[NOTE: This section is not applicable to Seismic Design Categories A or B. Uncheck this section if one of those categories applies. Confirm Seismic Design Category with structural engineer]

1. Designated Seismic Systems equipment verification
OBSERVE

· Verify model number and serial number are in conformance with project specific seismic qualification (PSSQ)

· Verify Tag ID is correct and installed per specifications

2. Designated Seismic Systems equipment Mounting
OBSERVE
· Verify that Anchor Base Bolting is installed per PSSQ

· Verify that Equipment Bracing is Installed per PSSQ

· Verify that Bracing Attachments are installed per PSSQ

3. Designated Seismic Systems utility Conduit/Piping
OBSERVE
· Verify that Conduit/Piping is connected to the equipment per PSSQ (flex or rigid)

· Verify that Conduit/Piping is seismically supported independently of equipment and in accordance with PSSQ support requirements

4. Designated Seismic Systems clearance
OBSERVE
· Adjacent Equipment – Verify that there is adequate gap to eliminate possibility of pounding

· Conduit/Piping - Verify that there is adequate gap to eliminate possibility of pounding

File details come from the government source that posted it. Updated .