SITE CHILLED WATER, STEAM & NATURAL GAS METERING at NIST GAITHERSBURG
Solicitation number
SB1341-14-RP-0017
Issued by

About this file

SB1341-14-RP-0017 Site Metering

View the file

Other files

File Type Posted
Amendment_003_Metering_Project.pdf PDF
1352.215-70_Proposal_Preparation_(updated_30_May_2014).pdf PDF
Sign-In_Sheet-Site_Visit.pdf PDF
Section_J_(updated_30_May_2014).docx DOCX document
Amendment_002_Metering_Project.pdf PDF
Attachment_5_Questions_ _Answers_(Final_Round).doc DOC document
Attachment_4_Questions_ _Answers_(Initial_Round).pdf PDF
Amendment_001_Metering_Project.pdf PDF
Revised_Drawings.zip ZIP file
Specifications-Revised_15_May_2014.pdf PDF
BUILDING235-PLOTFILE.pdf PDF
BUILDING302-PLOTFILE.pdf PDF
BUILDING202-PLOTFILE.pdf PDF
BUILDING226-PLOTFILE.pdf PDF
BUILDING224-PLOTFILE.pdf PDF
BUILDING225-PLOTFILE.pdf PDF
BUILDING236-PLOTFILE.pdf PDF
BUILDING203-PLOTFILE.pdf PDF
BUILDING245-PLOTFILE.pdf PDF
BUILDING237-PLOTFILE.pdf PDF
Attachment_2_GUIDELINES_FOR_OFPM_CONTRACTORS.doc DOC document
BUILDING320-PLOTFILE.pdf PDF
BUILDING312-PLOTFILE.pdf PDF
BUILDING301-PLOTFILE.pdf PDF
BUILDING222-PLOTFILE.pdf PDF
BUILDING223-PLOTFILE.pdf PDF
BUILDING101-PLOTFILE.pdf PDF
Attachment_1_SAFETY_PROCEDURES_5-13-09.doc DOC document
BUILDING303-PLOTFILE.pdf PDF
Specifications.pdf PDF
BUILDING231-PLOTFILE.pdf PDF
BUILDING233-PLOTFILE.pdf PDF
BUILDING206-PLOTFILE.pdf PDF
BUILDING221-PLOTFILE.pdf PDF
BUILDING220-PLOTFILE.pdf PDF
BUILDING304-PLOTFILE.pdf PDF
BUILDING227-PLOTFILE.pdf PDF
BUILDING230-PLOTFILE.pdf PDF
BUILDING215-PLOTFILE.pdf PDF
Attachment_3_Pricing_Worksheet_for_SB1341-14-RP-0017.xlsx XLSX spreadsheet
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

11. The contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

NSN 7540-01-155-3212 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

See Attached

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 4-85) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 253(c) ( )

20b. SIGNATURE 20c. OFFER DATE

SCHEDULE Continued

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

PAGE 3 OF 63 SB1341-14-RP-0017

The total period of performance for the contract will be 18 months from the date of award. The period of performance for each CLIN specifies the time the work for that CLIN must be performed. The period of performances specified for each CLIN does NOT extend the total period of performance for the contract.

BASE BID BUILDINGS

0001 Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for following Base Bid buildings:

Buildings 236, 301, 303 and 312.

Period of performance for base bid will be 180 days from

NTP

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

FOB : Destination

1.00 JB

Health and Safety Plan

0002 Contractor shall provide a project specific Construction Health and Safety Plan within 14 days of contract award.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

1.00 EA

OPTION 1

0003 Option-1 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 101

Period of performance will be 100 days from the start date specified in the Notice to Proceed (NTP) issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 2

PAGE 4 OF 63 SB1341-14-RP-0017

0004 Option-2 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 202

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 3

0005 Option-3 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 203 ( SRM warehouse )

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 4

0006 Option-4 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 215

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 5

0007 Option-5 to be awarded prior to Sept 30, 2014 1.00 JB

PAGE 5 OF 63 SB1341-14-RP-0017

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 220

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 6

0008 Option-6 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 227

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 7

0009 Option-7 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 230

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 8

0010 Option-8 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached

PAGE 6 OF 63 SB1341-14-RP-0017

statement work, specifications and construction drawings for Building 221

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

OPTION 9

0011 Option-9 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 222

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 10

0012 Option-10 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 223

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 11

0013 Option-11 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for

PAGE 7 OF 63 SB1341-14-RP-0017

Building 224

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

OPTION 12

0014 Option-12 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 225

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 13

0015 Option-13 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 226

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 14

0016 Option-14 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 231

PAGE 8 OF 63 SB1341-14-RP-0017

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

OPTION 15

0017 Option-15 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 233

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 16

0018 Option-16 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 235

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 17

0019 Option-17 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 237

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PAGE 9 OF 63 SB1341-14-RP-0017

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

OPTION 18

0020 Option-18 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 245

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 19

0021 Option-19 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 302

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 20

0022 Option-20 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 304

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

PAGE 10 OF 63 SB1341-14-RP-0017

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

OPTION 21

0023 Option-21 to be awarded prior to Sept 30, 2014

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 320

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 22

0024 Option-22 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 221

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 23

0025 Option-23 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 222

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

PAGE 11 OF 63 SB1341-14-RP-0017

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

OPTION 24

0026 Option-24 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 223

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 25

0027 Option-25 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 224

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 26

0028 Option-26 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 225

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

PAGE 12 OF 63 SB1341-14-RP-0017

OPTION 27

0029 Option-27 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 226

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 28

0030 Option-28 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 231

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 29

0031 Option-29 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 233

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

PAGE 13 OF 63 SB1341-14-RP-0017

OPTION 30

0032 Option-30 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 235

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 31

0033 Option-31 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 237

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 32

0034 Option-32 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 245

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 33

PAGE 14 OF 63 SB1341-14-RP-0017

Option-33 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 302

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 34

0036 Option-34 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 304

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

OPTION 35

0037 Option-35 to be awarded prior to Sept 30, 2015

Contractor shall provide all materials, labor and equipment to perform construction services per attached statement work, specifications and construction drawings for Building 320

Period of performance will be 100 days from the start date specified in the NTP issued for this option.

PR NUMBER: NB195000-14-01247

SHIP TO:

NATIONAL INST OF STDS AND TECHNOLOGY

BUILDING 301 SHIPPING AND RECEIVING

100 BUREAU DRIVE

GAITHERSBURG MD 20899-0001

Table of Contents

PAGE 15 OF 63 SB1341-14-RP-0017

SECTION B SUPPLIES OR SERVICES AND PRICES/COSTS

B. 1 Disclosure of the Magnitude of Construction Projec

SECTION C DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C. 1 Section C-Statment of Work

SECTION E INSPECTION AND ACCEPTANCE

E. 1 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

E. 2 1352.246-70 PLACE OF ACCEPTANCE (APR 2010)

SECTION F DELIVERIES OR PERFORMANCE

F. 1 1352.270-70 PERIOD OF PERFORMANCE (APR 2010)

F. 2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

F. 3 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

SECTION G CONTRACT ADMINISTRATION DATA

G. 1 1352.201-70 CONTRACTING OFFICER?s AUTHORITY (APR 2010)

G. 2 1352.201-72 CONTRACTING OFFICER?s REPRESENTATIVE (C0R) (APR 2010)

SECTION H SPECIAL CONTRACT REQUIREMENTS

H. 1 1352.208-70 RESTRICTIONS ON PRINTING AND DUPLICATING (APR 2010)

H. 2 1352.209-73 COMPLIANCE WITH THE LAWS (APR 2010)

H. 3 1352.228-72 DEDUCTIBLES UNDER REQUIRED INSURANCE COVERAGE- FIXED PRICE (APR 2010)

H. 4 1352.228-70 INSURANCE COVERAGE (APR 2010)

H. 5 1352.237-75 KEY PERSONNEL (APR 2010)

H. 6 General Decision Number MD130057.pdf

SECTION I CONTRACT CLAUSES

I. 1 52.202-1 DEFINITIONS (NOV 2013)

I. 2 52.203-3 GRATUITIES (APR 1984)

I. 3 52.203-5 COVENANT AGAINST CONTINGENT FEES (APR 1984)

I. 4 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006)

I. 5 52.203-7 ANTI-KICKBACK PROCEDURES (OCT 2010)

I. 6 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY

(JAN 1997)

I. 7 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (JAN 1997)

I. 8 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT 2010)

I. 9 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011)

I. 10 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

I. 11 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (JULY 2013). 35

I. 12 52.209-6 PROTECTING THE GOVERNMENT` INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (AUG 2013)

I. 13 52.215-2 AUDIT AND RECORDS--NEGOTIATION (OCT 2010)

I. 14 52.215-8 ORDER OF PRECEDENCE--UNIFORM CONTRACT FORMAT (OCT 1997)

I. 15 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (JUL 2013)

I. 16 52.219-14 LIMITATIONS ON SUBCONTRACTING (NOV 2011)

I. 17 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REPRESENTATION (JUL 2013)

I. 18 52.222-1 NOTICE TO THE GOVERNMENT OF LABOR DISPUTES (FEB 1997)

I. 19 52.222-3 CONVICT LABOR (JUN 2003)

I. 20 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT--OVERTIME COMPENSATION (JUL 2005).. 36

I. 21 52.222-6 DAVIS-BACON ACT (JUL 2005)

PAGE 16 OF 63 SB1341-14-RP-0017

I. 22 52.222-7 WITHHOLDING OF FUNDS (FEB 1988)

I. 23 52.222-8 PAYROLLS AND BASIC RECORDS (JUN 2010)

I. 24 52.222-9 APPRENTICES AND TRAINEES (JUL 2005)

I. 25 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)

I. 26 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (JUL 2005)

I. 27 52.222-12 CONTRACT TERMINATION--DEBARMENT (FEB 1988)

I. 28 52.222-13 COMPLIANCE WITH DAVIS-BACON AND RELATED ACT REGULATIONS (FEB 1988)

I. 29 52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)

I. 30 52.222-15 CERTIFICATION OF ELIGIBILITY (FEB 1988)

I. 31 52.222-21 PROHIBITION OF SEGREGATED FACILITIES (FEB 1999)

I. 32 52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999)

I. 33 52.222-26 EQUAL OPPORTUNITY (MAR 2007)

I. 34 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (FEB 1999)

I. 35 52.222-35 EQUAL OPPORTUNITY FOR VETERANS. [SEP 2010]

I. 36 52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES (OCT 2010

I. 37 52.222-37 EMPLOYMENT REPORTS VETERANS (SEP 2010)

I. 38 52.222-38 COMPLIANCE WITH VETERANs` EMPLOYMENT REPORTING REQUIREMENTS (SEP 2010)

I. 39 52.222-50 COMBATING TRAFFICKING IN PERSONS (FEB 2009)

I. 40 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (AUG 2012)

I. 41 52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)

I. 42 52.223-6 DRUG-FREE WORKPLACE (MAY 2001)

I. 43 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (AUG 2011). 37

I. 44 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)

I. 45 52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)

I. 46 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (DEC 2007)

I. 47 52.227-4 PATENT INDEMNITY--CONSTRUCTION CONTRACTS (DEC 2007)

I. 48 52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)

I. 49 52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)

I. 50 52.228-11 PLEDGES OF ASSETS (JAN 2012)

I. 51 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (OCT 1995)

I. 52 52.228-14 IRREVOCABLE LETTER OF CREDIT (DEC 1999)

I. 53 52.228-15 PERFORMANCE AND PAYMENT BONDS--CONSTRUCTION (OCT 2010)

I. 54 52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)

I. 55 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEP 2002)

I. 56 52.232-17 INTEREST (OCT 2010)

I. 57 52.232-18 AVAILABILITY OF FUNDS (APR 1984)

I. 58 52.232-23 ASSIGNMENT OF CLAIMS (JAN 1986)

I. 59 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JUL 2013)

I. 60 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER--SYSTEM FOR AWARD MANAGEMENT (JUL 2013)... 39

I. 61 52.233-1 DISPUTES (JUL 2002)

I. 62 52.233-3 PROTEST AFTER AWARD (AUG 1996)

I. 63 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)

I. 64 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

I. 65 52.236-2 DIFFERING SITE CONDITIONS (APR 1984)

I. 66 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)

I. 67 52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)

I. 68 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)

I. 69 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)

I. 70 52.236-8 OTHER CONTRACTS (APR 1984)

I. 71 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND

IMPROVEMENTS (APR 1984)

PAGE 17 OF 63 SB1341-14-RP-0017

I. 72 52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)

I. 73 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)

I. 74 52.236-12 CLEANING UP (APR 1984)

I. 75 52.236-13 ACCIDENT PREVENTION (NOV 1991)

I. 76 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)

I. 77 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)

I. 78 52.236-17 LAYOUT OF WORK (APR 1984)

I. 79 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)

I. 80 52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)

I. 81 52.242-13 BANKRUPTCY (JUL 1995)

I. 82 52.242-14 SUSPENSION OF WORK (APR 1984)

I. 83 52.243-4 CHANGES (JUN 2007)

I. 84 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (DEC 2013)

I. 85 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

I. 86 52.248-3 VALUE ENGINEERING--CONSTRUCTION (OCT 2010)

I. 87 52.249-2 I TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012)--

ALTERNATE I (SEP 1996)

I. 88 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)

I. 89 52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

I. 90 52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)

I. 91 52.222-5 DAVIS-BACON ACT -- SECONDARY SITE OF THE WORK (JUL 2005)

I. 92 52.225-9 BUY AMERICAN ACT--CONSTRUCTION MATERIALS (SEP 2010)

I. 93 52.228-1 BID GUARANTEE (SEP 1996)

I. 94 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

I. 95 NIST LOCAL-04 BILLING INSTRUCTIONS

SECTION J LIST OF ATTACHMENTS

J. 1 Section J

SECTION K REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS

K. 1 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT

OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

K. 2 52.236-28 PREPARATION OF PROPOSALS--CONSTRUCTION (OCT 1997)

K. 3 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2014)

K. 4 52.215-6 PLACE OF PERFORMANCE (OCT 1997)

SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

L. 1 52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013)

L. 2 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)

L. 3 52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)

L. 4 52.215-1 INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION (JAN 2004)

L. 5 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

L. 6 1352.242-70 POSTAWARD CONFERENCE (APR 2010)

L. 7 52.216-1 TYPE OF CONTRACT (APR 1984)

L. 8 52.222-5 DAVIS-BACON ACT -- SECONDARY SITE OF THE WORK (JUL 2005)

L. 9 52.225-10 NOTICE OF BUY AMERICAN ACT REQUIREMENT--CONSTRUCTION MATERIALS (FEB 2009)

L. 10 52.225-12 NOTICE OF BUY AMERICAN ACT REQUIREMENT--CONSTRUCTION MATERIALS UNDER TRADE

AGREEMENTS (FEB 2009)

L. 11 52.233-2 SERVICE OF PROTEST (SEP 2006)

L. 12 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

L. 13 1352.215-72 INQUIRIES (APR 2010)

PAGE 18 OF 63 SB1341-14-RP-0017

L. 14 1352.233-70 AGENCY PROTESTS (APR 2010)

L. 15 1352.233-71 GAO AND COURT OF FEDERAL CLAIMS PROTESTS (APR 2010)

L. 16 1352.270-71 PRE-BID / PRE-PROPOSAL CONFERENCE AND SITE VISIT (APR 2010)

L. 17 1352.215-70 Proposal Preparation

SECTION M EVALUATION FACTORS FOR AWARD

M. 1 1352.215-75 Evaluation criteria

PAGE 19 OF 63 SB1341-14-RP-0017

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

B. 1 Disclosure of the Magnitude of Construction Projec

36.204 Disclosure of the Magnitude of Construction Projects

The estimated price for this requirement as described in terms of the following price ranges is:

( ) Less than $25,000.

( ) Between $25,000 and $100,000.

( ) Between $100,000 and $250,000.

( ) Between $250,000 and $500,000.

( ) Between $500,000 and $1,000,000.

(X) Between $1,000,000 and $5,000,000.

( ) Between $5,000,000 and $10,000,000.

( ) More than $10,000,000

PAGE 20 OF 63 SB1341-14-RP-0017

SECTION C

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

C. 1 Section C-Statment of Work

Section C:

Below attachments are hereby incorporated by reference.

Specifications.pdf

BUILDING101-PLOTFILE.pdf

BUILDING202-PLOTFILE.pdf

BUILDING203-PLOTFILE.pdf

BUILDING206-PLOTFILE.pdf

BUILDING215-PLOTFILE.pdf

BUILDING220-PLOTFILE.pdf

BUILDING221-PLOTFILE.pdf

BUILDING222-PLOTFILE.pdf

BUILDING223-PLOTFILE.pdf

BUILDING224-PLOTFILE.pdf

BUILDING225-PLOTFILE.pdf

BUILDING226-PLOTFILE.pdf

BUILDING227-PLOTFILE.pdf

BUILDING230-PLOTFILE.pdf

BUILDING231-PLOTFILE.pdf

BUILDING233-PLOTFILE.pdf

BUILDING235-PLOTFILE.pdf

BUILDING236-PLOTFILE.pdf

BUILDING237-PLOTFILE.pdf

BUILDING245-PLOTFILE.pdf

BUILDING301-PLOTFILE.pdf

PAGE 21 OF 63 SB1341-14-RP-0017

BUILDING302-PLOTFILE.pdf

BUILDING303-PLOTFILE.pdf

BUILDING304-PLOTFILE.pdf

BUILDING312-PLOTFILE.pdf

BUILDING320-PLOTFILE.pdf

PAGE 22 OF 63 SB1341-14-RP-0017

SECTION E

INSPECTION AND ACCEPTANCE

E. 1 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

(Reference 52.246-12)

E. 2 1352.246-70 PLACE OF ACCEPTANCE (APR 2010)

(Reference 1352.246-70)

PAGE 23 OF 63 SB1341-14-RP-0017

SECTION F

DELIVERIES OR PERFORMANCE

F. 1 1352.270-70 PERIOD OF PERFORMANCE (APR 2010)

(Reference 1352.270-70)

F. 2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to

(a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 180 calendar days after date of Notice to Proceed for CLIN 0001 and within the number of days specified under each option CLIN when/if exercised. The time stated for completion shall include final cleanup of the premises.

(End of Clause)

ADDENDUM TO 52.211-12

The liquidated damages rate is for EACH CLIN based on the NTP if/when issued for that CLIN.

F. 3 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of a one time legal fee of $392.81 and $203.35 for EACH CLIN for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor`s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

PAGE 24 OF 63 SB1341-14-RP-0017

SECTION G

CONTRACT ADMINISTRATION DATA

G. 1 1352.201-70 CONTRACTING OFFICER?s AUTHORITY (APR 2010)

(Reference 1352.201-70)

G. 2 1352.201-72 CONTRACTING OFFICER?s REPRESENTATIVE (C0R) (APR 2010)

(a) TBD is hereby designated as the Contracting Officer?s Representative (COR). The COR may be changed at any time by the Government without prior notice to the contractor by a unilateral modification to the contract. The COR is located at:

National Institute of Standards and Technology, 100 Bureau Drive, Gaithersburg, MD 20899-1604 Phone Number: 301-975-XXXX Email: TBD@nist.gov

(b) The responsibilities and limitations of the COR are as follows:

(1) The COR is responsible for the technical aspects of the contract and serves as technical liaison with the contractor. The COR is also responsible for the final inspection and acceptance of all deliverables and such other responsibilities as may be specified in the contract.

(2) The COR is not authorized to make any commitments or otherwise obligate the Government or authorize any changes which affect the contract price, terms or conditions. Any contractor request for changes shall be referred to the Contracting Officer directly or through the COR. No such changes shall be made without the express written prior authorization of the Contracting Officer.

The Contracting Officer may designate assistant or alternate COR(s) to act for the COR by naming such assistant/alternate(s) in writing and transmitting a copy of such designation to the contractor.

(End of clause)

PAGE 25 OF 63 SB1341-14-RP-0017

SECTION H

SPECIAL CONTRACT REQUIREMENTS

H. 1 1352.208-70 RESTRICTIONS ON PRINTING AND DUPLICATING (APR 2010)

(Reference 1352.208-70)

H. 2 1352.209-73 COMPLIANCE WITH THE LAWS (APR 2010)

(Reference 1352.209-73)

H. 3 1352.228-72 DEDUCTIBLES UNDER REQUIRED INSURANCE COVERAGE- FIXED PRICE (APR 2010)

(Reference 1352.228-72)

H. 4 1352.228-70 INSURANCE COVERAGE (APR 2010)

(a) Workers Compensation and Employer?s Liability. The contractor is required to comply with applicable federal and state workers'' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer?s liability section of the insurance policy, except when contract operations are so commingled with a contractor?s commercial operations that it would not be practical to require this coverage. Employer?s liability coverage of at least $100,000 shall be required, except in states with exclusive or monopolistic funds that do not permit workers'' compensation to be written by private carriers.

(b) General liability.

(1) The contractor shall have bodily injury liability insurance coverage written on the comprehensive form of policy of at least $500,000 per occurrence.

(2) When special circumstances apply in accordance with FAR 28.307-2(b), Property Damage Liability Insurance shall be required in the amount of $500,000 .

(c) Automobile liability. The contractor shall have automobile liability insurance written on the comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract.

Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage.

(d) Aircraft public and passenger liability. When aircraft are used in connection with performing the contract, the contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger liability, and $200,000 per occurrence for property damage. Coverage for passenger liability bodily injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.

(e) Vessel liability. When contract performance involves use of vessels, the Contractor shall provide, vessel collision liability and protection and indemnity liability insurance as determined by the Government.

H. 5 1352.237-75 KEY PERSONNEL (APR 2010)

(a) The contractor shall assign to this contract the following key personnel:

ASME Certified Welder Number 1 ASME Certified Welder Number 2

(b) The contractor shall obtain the consent of the Contracting Officer prior to making key personnel substitutions. Replacements for key personnel must possess qualifications equal to or exceeding the qualifications of the personnel being replaced, unless an exception is approved by the Contracting Officer.

(c) Requests for changes in key personnel shall be submitted to the Contracting Officer at least 15 working days prior to making any permanent substitutions. The request should contain a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. The

PAGE 26 OF 63 SB1341-14-RP-0017

Contracting Officer will notify the contractor within 10 working days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes.

H. 6 General Decision Number MD130057.pdf

PAGE 27 OF 63 SB1341-14-RP-0017

General Decision Number: MD130057 08/23/2013 MD57

Superseded General Decision Number: MD20120081

State: Maryland

Construction Type: Building

County: Montgomery County in Maryland.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Modification Number Publication Date

0 01/04/2013

1 01/25/2013

2 02/01/2013

3 02/22/2013

4 03/29/2013

5 04/05/2013

6 05/10/2013

7 06/07/2013

8 06/28/2013

9 07/05/2013

10 07/12/2013

11 08/02/2013

12 08/23/2013

ASBE0024-007 10/01/2012

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 33.13 13.60

Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems

ASBE0024-010 10/01/2012

ASBESTOS WORKER: HAZARDOUS

MATERIAL HANDLER (Removal of hazardous material from ceilings, floors, mechanical systems, and walls)..............$ 20.86 5.61

BRMD0001-006 05/01/2011

TILE SETTER......................$ 25.29 9.89

PAGE 28 OF 63 SB1341-14-RP-0017

BRMD0001-009 05/01/2011

TILE FINISHER....................$ 20.48 8.74

BRMD0001-011 05/01/2012

BRICKLAYER (Excluding

Pointing, Caulking and

Cleaning)........................$ 27.89 7.76

BRMD0001-012 05/01/2011

MASON - STONE....................$ 32.88 13.99

CARP0132-017 05/01/2013

CARPENTER (Including

Acoustical Ceiling

Installation, Drywall

Hanging, Metal Stud

Installation and Form Work)......$ 26.81 8.13

CARP1831-002 04/01/2012

MILLWRIGHT.......................$ 27.96 12.20

ELEC0026-021 09/01/2012

ELECTRICIAN (Communication and Sound Equipment).............$ 25.55 3%+7.77

ELEC0026-022 06/03/2013

ELECTRICIAN (Including low voltage wiring for and installation of alarms, HVAC controls)........................$ 40.65 14.42+a a.PAID HOLIDAYS: New Year's Day, Inauguration Day, Martin

Luther King Jr.'s Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after

Thanksgiving Day and Christmas Day.

PAGE 29 OF 63 SB1341-14-RP-0017

ELEV0010-001 01/01/2013

ELEVATOR MECHANIC................$ 39.96 25.185+a+b

a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence

Day, Labor Day, Veterans' Day, Thanksgiving Day, Christmas

Day and the Friday after Thanksgiving.

b. VACATIONS: Employer contributes 8% of basic hourly rate for 5 years or more of service; 6% of basic hourly rate for

6 months to 5 years of service as vacation pay credit.

ENGI0077-018 05/01/2013

OPERATOR: Bulldozer.............$ 31.65 8.45+a

OPERATOR: Loader

Front End Loaders 3 1/2 cubic yards and above.......$ 32.40 8.45+a

Front End Loaders Below 3

1/2 cubic yards.............$ 31.65 8.45+a a.PAID HOLIDAYS: New Year's Day, Inaugural Day, Decoration

Day, Independence Day, Labor Day, Martin Luther King's

Birthday, Veterans' Day, Thanksgiving Day, Friday after

Thanksgiving and Christmas Day.

IRON0005-005 06/01/2013

IRONWORKER, STRUCTURAL AND

ORNAMENTAL.......................$ 30.00 16.04

IRON0201-006 05/01/2012

IRONWORKER, REINFORCING..........$ 26.50 16.68

LABO0657-017 06/01/2012

LABORER: Mason Tender -

Cement/Concrete..................$ 21.26 6.83

LABORER: Pipelayer..............$ 21.26 6.83

PAIN0051-014 06/01/2013

PAGE 30 OF 63 SB1341-14-RP-0017

GLAZIER

Glazing Contracts $2 million and under...........$ 24.30 9.61

Glazing Contracts over $2 million.....................$ 27.64 9.61

PAIN0051-019 06/01/2013

PAINTER

Brush, Roller, Spray and

Drywall Finisher/Taper......$ 24.89 8.91

Industrial..................$ 29.18 8.91

PLAS0891-005 07/01/2012

PLASTERER........................$ 28.33 5.85

PLAS0891-006 05/01/2010

CEMENT MASON/CONCRETE FINISHER...$ 27.15 9.58

PLAS0891-008 08/01/2011

PLASTERER (Fireproofing

Including Sprayer, Mixer, and

Handler)

Handler.....................$ 15.00 3.89

Mixer/Pump..................$ 17.00 3.89

Sprayer.....................$ 21.50 3.89

* PLUM0005-010 08/01/2013

PLUMBER..........................$ 38.17 16.25+a

a. PAID HOLIDAYS: Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving, Christmas Day, New Year's

Day, Martin Luther King's Birthday, Memorial Day and the

Fourth of July.

PLUM0602-011 08/01/2012

PIPEFITTER (Including HVAC

PAGE 31 OF 63 SB1341-14-RP-0017

Pipe and System Installation)....$ 37.62 18.07+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King's

Birthday, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day and the day after

Thanksgiving and Christmas Day.

ROOF0030-016 09/01/2012

ROOFER...........................$ 26.90 10.18

SFMD0669-001 07/01/2013

SPRINKLER FITTER (Fire

Sprinklers)......................$ 31.14 17.62

SHEE0100-015 07/01/2013

SHEET METAL WORKER (Including

HVAC Duct Installation)..........$ 39.93 15.38

SUMD2010-091 08/04/2010

LABORER

Common or General...........$ 14.15 2.30

Grade Checker...............$ 16.00 2.90

Landscape...................$ 9.23

Mason Tender - Brick........$ 13.00 0.00

Mason Tender - Stone........$ 14.03 0.00

Mason Tender for Pointing, Caulking and Cleaning.......$ 13.21

Mortar Mixer................$ 16.61 9.08

POINTER, CAULKER, CLEANER,

Includes pointing, caulking, cleaning of existing masonry, brick, stone and cement structures (restoration work); excludes pointing, caulking, cleaning of new or replacement masonry, brick, stone or cement...........................$ 19.19 0.00

POWER EQUIPMENT OPERATOR:

Asphalt Roller..............$ 21.35 5.38

Backhoe.....................$ 19.82 5.02

Bobcat/Skid Loader..........$ 18.05 8.78

PAGE 32 OF 63 SB1341-14-RP-0017

Boom........................$ 21.44 8.29

Crane.......................$ 20.95 6.18

Excavator...................$ 20.00 0.00

Forklift....................$ 16.00 5.12

Gradall.....................$ 20.50 8.42

Grader/Blade................$ 14.50 5.18

Paver.......................$ 17.47 6.36

Roller excluding Asphalt....$ 17.60 3.88

TERRAZZO WORKER/SETTER...........$ 19.94 6.54

TRUCK DRIVER

Dump Truck..................$ 15.90 1.12

Tractor Haul Truck..........$ 17.87 9.98

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.

Union Identifiers

An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.

The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.

Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the

PAGE 33 OF 63 SB1341-14-RP-0017

rates.

0000/9999: weighted union wage rates will be published annually each January.

Non-Union Identifiers

Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007

5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.

Survey wage rates will remain in effect and will not change until a new survey is conducted.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request

PAGE 34 OF 63 SB1341-14-RP-0017

review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .