SAI SIR Section J.8 12.27.23.xlsx
XLSX spreadsheet 38 KB Posted
- Attached to
- Surface Awareness Initiative Federal contract opportunity
- Solicitation number
- 693KA7SAI
About this file
This document is a pricing template for a federal indefinite delivery, indefinite quantity contract solicitation for surface awareness services at five major airports. Offerors are required to provide pricing for base services including service operations and management, base stations, airport tower equipment, and site surveys. Pricing must be provided for each airport for five one-year base periods and five one-year option periods. Additional pricing is requested for enhanced capabilities. Labor rates must also be defined for five experience levels across three labor categories. Offerors must specify a maximum annual escalation rate to be applied to option period pricing. Responses are due in accordance with the solicitation instructions.
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| Instructions and Cautions |
| Offerors must provide prices in the subsequent tabs for all items shaded in blue as indicated in the cell to the right |
| Offerors must provide the quantity of base stations needed at the airports identified in the Configuration tab. The quantities are entered into cells shaded green as indicated in the cell to the right. |
| Offerors must define experience levels for T&M labor rates. Experience must encompass years of work experience as well as education requirements. These definitions are entered into cell shaded orange as indicated in the cell to the right |
| Offerors must propose a maximum escalation that will be applied to year 5 contract prices to bound prices for all subsequent option periods of the contract. The escalation factor must be entered in the cell shaded red as indicted in the cell to the right. |
| Offerors must not change the items in cells other than those shaded blue, green, orange or red. |
| Offerors must enter prices for all years requested. If a price is not entered, or entered as zero because a quantity for that price is zero, a zero price will be contractually binding. Since this is an IDIQ service contract, successful Offerors will be bound by the price established. This includes prices that are zero dollars. |
Configuration
| Airport | Number of Base Stations required to cover both movement and non-movement areas as well as the coverage requirements identified within Attachment J.1 |
| AUS | - 0 |
| BNA | - 0 |
| DAL | - 0 |
| IND | - 0 |
| TPA | - 0 |
SubCLIN1A
| SubCLIN | Airport | Description | Contract Type | Charge Type | Price | PWS Sections | Quantity for Evaluation | Extended Price |
| 01A1.AUS.01 | AUS | Non-recurring price to establish Service Operations and Management year 1 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 1 | $ - 0 |
| 01A2.AUS.01 | AUS | Monthly recurring price for Service Operations and Management year 1 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 6 | $ - 0 |
| 01A1.BNA.01 | BNA | Non-recurring price to establish Service Operations and Management year 1 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 1 | $ - 0 |
| 01A2.BNA.01 | BNA | Monthly recurring price for Service Operations and Management year 1 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 6 | $ - 0 |
| 01A1.DAL.01 | DAL | Non-recurring price to establish Service Operations and Management year 1 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 1 | $ - 0 |
| 01A2.DAL.01 | DAL | Monthly recurring price for Service Operations and Management year 1 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 6 | $ - 0 |
| 01A1.IND.01 | IND | Non-recurring price to establish Service Operations and Management year 1 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 1 | $ - 0 |
| 01A2.IND.01 | IND | Monthly recurring price for Service Operations and Management year 1 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 6 | $ - 0 |
| 01A1.TPA.01 | TPA | Non-recurring price to establish Service Operations and Management year 1 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 1 | $ - 0 |
| 01A2.TPA.01 | TPA | Monthly recurring price for Service Operations and Management year 1 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 6 | $ - 0 |
| 01A1.AUS.02 | AUS | Non-recurring price to establish Service Operations and Management year 2 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.AUS.02 | AUS | Monthly recurring price for Service Operations and Management year 2 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.BNA.02 | BNA | Non-recurring price to establish Service Operations and Management year 2 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.BNA.02 | BNA | Monthly recurring price for Service Operations and Management year 2 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.DAL.02 | DAL | Non-recurring price to establish Service Operations and Management year 2 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.DAL.02 | DAL | Monthly recurring price for Service Operations and Management year 2 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.IND.02 | IND | Non-recurring price to establish Service Operations and Management year 2 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.IND.02 | IND | Monthly recurring price for Service Operations and Management year 2 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.TPA.02 | TPA | Non-recurring price to establish Service Operations and Management year 2 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.TPA.02 | TPA | Monthly recurring price for Service Operations and Management year 2 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.AUS.03 | AUS | Non-recurring price to establish Service Operations and Management year 3 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.AUS.03 | AUS | Monthly recurring price for Service Operations and Management year 3 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.BNA.03 | BNA | Non-recurring price to establish Service Operations and Management year 3 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.BNA.03 | BNA | Monthly recurring price for Service Operations and Management year 3 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.DAL.03 | DAL | Non-recurring price to establish Service Operations and Management year 3 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.DAL.03 | DAL | Monthly recurring price for Service Operations and Management year 3 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.IND.03 | IND | Non-recurring price to establish Service Operations and Management year 3 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.IND.03 | IND | Monthly recurring price for Service Operations and Management year 3 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.TPA.03 | TPA | Non-recurring price to establish Service Operations and Management year 3 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.TPA.03 | TPA | Monthly recurring price for Service Operations and Management year 3 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.AUS.04 | AUS | Non-recurring price to establish Service Operations and Management year 4 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.AUS.04 | AUS | Monthly recurring price for Service Operations and Management year 4 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.BNA.04 | BNA | Non-recurring price to establish Service Operations and Management year 4 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.BNA.04 | BNA | Monthly recurring price for Service Operations and Management year 4 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.DAL.04 | DAL | Non-recurring price to establish Service Operations and Management year 4 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.DAL.04 | DAL | Monthly recurring price for Service Operations and Management year 4 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.IND.04 | IND | Non-recurring price to establish Service Operations and Management year 4 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.IND.04 | IND | Monthly recurring price for Service Operations and Management year 4 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.TPA.04 | TPA | Non-recurring price to establish Service Operations and Management year 4 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.TPA.04 | TPA | Monthly recurring price for Service Operations and Management year 4 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.AUS.05 | AUS | Non-recurring price to establish Service Operations and Management year 5 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.AUS.05 | AUS | Monthly recurring price for Service Operations and Management year 5 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.BNA.05 | BNA | Non-recurring price to establish Service Operations and Management year 5 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.BNA.05 | BNA | Monthly recurring price for Service Operations and Management year 5 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.DAL.05 | DAL | Non-recurring price to establish Service Operations and Management year 5 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.DAL.05 | DAL | Monthly recurring price for Service Operations and Management year 5 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.IND.05 | IND | Non-recurring price to establish Service Operations and Management year 5 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.IND.05 | IND | Monthly recurring price for Service Operations and Management year 5 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| 01A1.TPA.05 | TPA | Non-recurring price to establish Service Operations and Management year 5 | FFP | Only once per airport | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 0 | $ - 0 |
| 01A2.TPA.05 | TPA | Monthly recurring price for Service Operations and Management year 5 | FFP | Per month per order | $ - 0 | 4.2.1 – 4.2.8, and 4.3.1 | 12 | $ - 0 |
| AUS | Subtotal | $ - 0 | ||||||
| BNA | Subtotal | $ - 0 | ||||||
| DAL | Subtotal | $ - 0 | ||||||
| IND | Subtotal | $ - 0 | ||||||
| TPA | Subtotal | $ - 0 |
SubCLIN1B
| SubCLIN | Airport | Description | Contract Type | Charge Type | Price | PWS Sections | Quantity for Evaluation | Extended Price |
| 01B1.AUS.01 | AUS | Base station and connectivity nonrecurring price year 1 for a base station at AUS | FFP | Only once per Base Station at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.AUS.01 | AUS | Monthly recurring base station and connectivity price year 1 for a base station at AUS | FFP | Per Base Station at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.BNA.01 | BNA | Base station and connectivity nonrecurring price year 1 for a base station at BNA | FFP | Only once per Base Station at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.BNA.01 | BNA | Monthly recurring base station and connectivity price year 1 for a base station at BNA | FFP | Per Base Station at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.DAL.01 | DAL | Base station and connectivity nonrecurring price year 1 for a base station at DAL | FFP | Only once per Base Station at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.DAL.01 | DAL | Monthly recurring base station and connectivity price year 1 for a base station at DAL | FFP | Per Base Station at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.IND.01 | IND | Base station and connectivity nonrecurring price year 1 for a base station at IND | FFP | Only once per Base Station at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.IND.01 | IND | Monthly recurring base station and connectivity price year 1 for a base station at IND | FFP | Per Base Station at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.TPA.01 | TPA | Base station and connectivity nonrecurring price year 1 for a base station at TPA | FFP | Only once per Base Station at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.TPA.01 | TPA | Monthly recurring base station and connectivity price year 1 for a base station at TPA | FFP | Per Base Station at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.AUS.02 | AUS | Base station and connectivity nonrecurring price year 2 for a base station at AUS | FFP | Only once per Base Station at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.AUS.02 | AUS | Monthly recurring base station and connectivity price year 2 for a base station at AUS | FFP | Per Base Station at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.BNA.02 | BNA | Base station and connectivity nonrecurring price year 2 for a base station at BNA | FFP | Only once per Base Station at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.BNA.02 | BNA | Monthly recurring base station and connectivity price year 2 for a base station at BNA | FFP | Per Base Station at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.DAL.02 | DAL | Base station and connectivity nonrecurring price year 2 for a base station at DAL | FFP | Only once per Base Station at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.DAL.02 | DAL | Monthly recurring base station and connectivity price year 2 for a base station at DAL | FFP | Per Base Station at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.IND.02 | IND | Base station and connectivity nonrecurring price year 2 for a base station at IND | FFP | Only once per Base Station at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.IND.02 | IND | Monthly recurring base station and connectivity price year 2 for a base station at IND | FFP | Per Base Station at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.TPA.02 | TPA | Base station and connectivity nonrecurring price year 2 for a base station at TPA | FFP | Only once per Base Station at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.TPA.02 | TPA | Monthly recurring base station and connectivity price year 2 for a base station at TPA | FFP | Per Base Station at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.AUS.03 | AUS | Base station and connectivity nonrecurring price year 3 for a base station at AUS | FFP | Only once per Base Station at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.AUS.03 | AUS | Monthly recurring base station and connectivity price year 3 for a base station at AUS | FFP | Per Base Station at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.BNA.03 | BNA | Base station and connectivity nonrecurring price year 3 for a base station at BNA | FFP | Only once per Base Station at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.BNA.03 | BNA | Monthly recurring base station and connectivity price year 3 for a base station at BNA | FFP | Per Base Station at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.DAL.03 | DAL | Base station and connectivity nonrecurring price year 3 for a base station at DAL | FFP | Only once per Base Station at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.DAL.03 | DAL | Monthly recurring base station and connectivity price year 3 for a base station at DAL | FFP | Per Base Station at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.IND.03 | IND | Base station and connectivity nonrecurring price year 3 for a base station at IND | FFP | Only once per Base Station at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.IND.03 | IND | Monthly recurring base station and connectivity price year 3 for a base station at IND | FFP | Per Base Station at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.TPA.03 | TPA | Base station and connectivity nonrecurring price year 3 for a base station at TPA | FFP | Only once per Base Station at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.TPA.03 | TPA | Monthly recurring base station and connectivity price year 3 for a base station at TPA | FFP | Per Base Station at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.AUS.04 | AUS | Base station and connectivity nonrecurring price year 4 for a base station at AUS | FFP | Only once per Base Station at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.AUS.04 | AUS | Monthly recurring base station and connectivity price year 4 for a base station at AUS | FFP | Per Base Station at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.BNA.04 | BNA | Base station and connectivity nonrecurring price year 4 for a base station at BNA | FFP | Only once per Base Station at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.BNA.04 | BNA | Monthly recurring base station and connectivity price year 4 for a base station at BNA | FFP | Per Base Station at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.DAL.04 | DAL | Base station and connectivity nonrecurring price year 4 for a base station at DAL | FFP | Only once per Base Station at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.DAL.04 | DAL | Monthly recurring base station and connectivity price year 4 for a base station at DAL | FFP | Per Base Station at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.IND.04 | IND | Base station and connectivity nonrecurring price year 4 for a base station at IND | FFP | Only once per Base Station at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.IND.04 | IND | Monthly recurring base station and connectivity price year 4 for a base station at IND | FFP | Per Base Station at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.TPA.04 | TPA | Base station and connectivity nonrecurring price year 4 for a base station at TPA | FFP | Only once per Base Station at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.TPA.04 | TPA | Monthly recurring base station and connectivity price year 4 for a base station at TPA | FFP | Per Base Station at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.AUS.05 | AUS | Base station and connectivity nonrecurring price year 5 for a base station at AUS | FFP | Only once per Base Station at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.AUS.05 | AUS | Monthly recurring base station and connectivity price year 5 for a base station at AUS | FFP | Per Base Station at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.BNA.05 | BNA | Base station and connectivity nonrecurring price year 5 for a base station at BNA | FFP | Only once per Base Station at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.BNA.05 | BNA | Monthly recurring base station and connectivity price year 5 for a base station at BNA | FFP | Per Base Station at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.DAL.05 | DAL | Base station and connectivity nonrecurring price year 5 for a base station at DAL | FFP | Only once per Base Station at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.DAL.05 | DAL | Monthly recurring base station and connectivity price year 5 for a base station at DAL | FFP | Per Base Station at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.IND.05 | IND | Base station and connectivity nonrecurring price year 5 for a base station at IND | FFP | Only once per Base Station at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.IND.05 | IND | Monthly recurring base station and connectivity price year 5 for a base station at IND | FFP | Per Base Station at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| 01B1.TPA.05 | TPA | Base station and connectivity nonrecurring price year 5 for a base station at TPA | FFP | Only once per Base Station at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01B2.TPA.05 | TPA | Monthly recurring base station and connectivity price year 5 for a base station at TPA | FFP | Per Base Station at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 0 | $ - 0 |
| AUS | Subtotal | $ - 0 | ||||||
| BNA | Subtotal | $ - 0 | ||||||
| DAL | Subtotal | $ - 0 | ||||||
| IND | Subtotal | $ - 0 | ||||||
| TPA | Subtotal | $ - 0 |
SubCLIN1C
| SubCLIN | Airport | Description | Contract Type | Charge Type | Price | PWS Sections | Quantity for Evaluation | Extended Price |
| 01C1.AUS.01 | AUS | Airport Tower equipment and connectivity nonrecurring price year 1 for a base at AUS | FFP | Only once per Airport Tower at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 1 | $ - 0 |
| 01C2.AUS.01 | AUS | Monthly Airport Tower equipment and connectivity recurring price year 1 for a base at AUS | FFP | Per Airport Tower at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 6 | $ - 0 |
| 01C1.BNA.01 | BNA | Airport Tower equipment and connectivity nonrecurring price year 1 for a base at BNA | FFP | Only once per Airport Tower at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 1 | $ - 0 |
| 01C2.BNA.01 | BNA | Monthly Airport Tower equipment and connectivity recurring price year 1 for a base at BNA | FFP | Per Airport Tower at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 6 | $ - 0 |
| 01C1.DAL.01 | DAL | Airport Tower equipment and connectivity nonrecurring price year 1 for a base at DAL | FFP | Only once per Airport Tower at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 1 | $ - 0 |
| 01C2.DAL.01 | DAL | Monthly Airport Tower equipment and connectivity recurring price year 1 for a base at DAL | FFP | Per Airport Tower at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 6 | $ - 0 |
| 01C1.IND.01 | IND | Airport Tower equipment and connectivity nonrecurring price year 1 for a base at IND | FFP | Only once per Airport Tower at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 1 | $ - 0 |
| 01C2.IND.01 | IND | Monthly Airport Tower equipment and connectivity recurring price year 1 for a base at IND | FFP | Per Airport Tower at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 6 | $ - 0 |
| 01C1.TPA.01 | TPA | Airport Tower equipment and connectivity nonrecurring price year 1 for a base at TPA | FFP | Only once per Airport Tower at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 1 | $ - 0 |
| 01C2.TPA.01 | TPA | Monthly Airport Tower equipment and connectivity recurring price year 1 for a base at TPA | FFP | Per Airport Tower at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 6 | $ - 0 |
| 01C1.AUS.02 | AUS | Airport Tower equipment and connectivity nonrecurring price year 2 for a base at AUS | FFP | Only once per Airport Tower at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.AUS.02 | AUS | Monthly Airport Tower equipment and connectivity recurring price year 2 for a base at AUS | FFP | Per Airport Tower at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.BNA.02 | BNA | Airport Tower equipment and connectivity nonrecurring price year 2 for a base at BNA | FFP | Only once per Airport Tower at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.BNA.02 | BNA | Monthly Airport Tower equipment and connectivity recurring price year 2 for a base at BNA | FFP | Per Airport Tower at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.DAL.02 | DAL | Airport Tower equipment and connectivity nonrecurring price year 2 for a base at DAL | FFP | Only once per Airport Tower at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.DAL.02 | DAL | Monthly Airport Tower equipment and connectivity recurring price year 2 for a base at DAL | FFP | Per Airport Tower at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.IND.02 | IND | Airport Tower equipment and connectivity nonrecurring price year 2 for a base at IND | FFP | Only once per Airport Tower at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.IND.02 | IND | Monthly Airport Tower equipment and connectivity recurring price year 2 for a base at IND | FFP | Per Airport Tower at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.TPA.02 | TPA | Airport Tower equipment and connectivity nonrecurring price year 2 for a base at TPA | FFP | Only once per Airport Tower at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.TPA.02 | TPA | Monthly Airport Tower equipment and connectivity recurring price year 2 for a base at TPA | FFP | Per Airport Tower at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.AUS.03 | AUS | Airport Tower equipment and connectivity nonrecurring price year 3 for a base at AUS | FFP | Only once per Airport Tower at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.AUS.03 | AUS | Monthly Airport Tower equipment and connectivity recurring price year 3 for a base at AUS | FFP | Per Airport Tower at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.BNA.03 | BNA | Airport Tower equipment and connectivity nonrecurring price year 3 for a base at BNA | FFP | Only once per Airport Tower at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.BNA.03 | BNA | Monthly Airport Tower equipment and connectivity recurring price year 3 for a base at BNA | FFP | Per Airport Tower at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.DAL.03 | DAL | Airport Tower equipment and connectivity nonrecurring price year 3 for a base at DAL | FFP | Only once per Airport Tower at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.DAL.03 | DAL | Monthly Airport Tower equipment and connectivity recurring price year 3 for a base at DAL | FFP | Per Airport Tower at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.IND.03 | IND | Airport Tower equipment and connectivity nonrecurring price year 3 for a base at IND | FFP | Only once per Airport Tower at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.IND.03 | IND | Monthly Airport Tower equipment and connectivity recurring price year 3 for a base at IND | FFP | Per Airport Tower at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.TPA.03 | TPA | Airport Tower equipment and connectivity nonrecurring price year 3 for a base at TPA | FFP | Only once per Airport Tower at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.TPA.03 | TPA | Monthly Airport Tower equipment and connectivity recurring price year 3 for a base at TPA | FFP | Per Airport Tower at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.AUS.04 | AUS | Airport Tower equipment and connectivity nonrecurring price year 4 for a base at AUS | FFP | Only once per Airport Tower at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.AUS.04 | AUS | Monthly Airport Tower equipment and connectivity recurring price year 4 for a base at AUS | FFP | Per Airport Tower at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.BNA.04 | BNA | Airport Tower equipment and connectivity nonrecurring price year 4 for a base at BNA | FFP | Only once per Airport Tower at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.BNA.04 | BNA | Monthly Airport Tower equipment and connectivity recurring price year 4 for a base at BNA | FFP | Per Airport Tower at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.DAL.04 | DAL | Airport Tower equipment and connectivity nonrecurring price year 4 for a base at DAL | FFP | Only once per Airport Tower at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.DAL.04 | DAL | Monthly Airport Tower equipment and connectivity recurring price year 4 for a base at DAL | FFP | Per Airport Tower at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.IND.04 | IND | Airport Tower equipment and connectivity nonrecurring price year 4 for a base at IND | FFP | Only once per Airport Tower at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.IND.04 | IND | Monthly Airport Tower equipment and connectivity recurring price year 4 for a base at IND | FFP | Per Airport Tower at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.TPA.04 | TPA | Airport Tower equipment and connectivity nonrecurring price year 4 for a base at TPA | FFP | Only once per Airport Tower at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.TPA.04 | TPA | Monthly Airport Tower equipment and connectivity recurring price year 4 for a base at TPA | FFP | Per Airport Tower at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.AUS.05 | AUS | Airport Tower equipment and connectivity nonrecurring price year 5 for a base at AUS | FFP | Only once per Airport Tower at AUS | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.AUS.05 | AUS | Monthly Airport Tower equipment and connectivity recurring price year 5 for a base at AUS | FFP | Per Airport Tower at AUS per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.BNA.05 | BNA | Airport Tower equipment and connectivity nonrecurring price year 5 for a base at BNA | FFP | Only once per Airport Tower at BNA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.BNA.05 | BNA | Monthly Airport Tower equipment and connectivity recurring price year 5 for a base at BNA | FFP | Per Airport Tower at BNA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.DAL.05 | DAL | Airport Tower equipment and connectivity nonrecurring price year 5 for a base at DAL | FFP | Only once per Airport Tower at DAL | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.DAL.05 | DAL | Monthly Airport Tower equipment and connectivity recurring price year 5 for a base at DAL | FFP | Per Airport Tower at DAL per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.IND.05 | IND | Airport Tower equipment and connectivity nonrecurring price year 5 for a base at IND | FFP | Only once per Airport Tower at IND | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.IND.05 | IND | Monthly Airport Tower equipment and connectivity recurring price year 5 for a base at IND | FFP | Per Airport Tower at IND per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| 01C1.TPA.05 | TPA | Airport Tower equipment and connectivity nonrecurring price year 5 for a base at TPA | FFP | Only once per Airport Tower at TPA | $ - 0 | 4.2.9, 4.2.9.1, 4.2.9.4-4.2.9.6 | 0 | $ - 0 |
| 01C2.TPA.05 | TPA | Monthly Airport Tower equipment and connectivity recurring price year 5 for a base at TPA | FFP | Per Airport Tower at TPA per month | $ - 0 | 4.2.9.7-4.2.9.8, 4.2.10 | 12 | $ - 0 |
| AUS | Subtotal | $ - 0 | ||||||
| BNA | Subtotal | $ - 0 | ||||||
| DAL | Subtotal | $ - 0 | ||||||
| IND | Subtotal | $ - 0 | ||||||
| TPA | Subtotal | $ - 0 |
SubCLIN1D
| SubCLIN | Description | Contract Type | Charge Type | Price | PWS Sections | Quantity for Evaluation |
| 01D.01 | Site Survey and Site Design price for year 1 | FFP | Non-recurring per Airport | $ - 0 | 4.2.9.1 – 4.2.9.3 | 5 |
| 01D.02 | Site Survey and Site Design price for year 2 | FFP | Non-recurring per Airport | $ - 0 | 4.2.9.1 – 4.2.9.3 | - 0 |
| 01D.03 | Site Survey and Site Design price for year 3 | FFP | Non-recurring per Airport | $ - 0 | 4.2.9.1 – 4.2.9.3 | - 0 |
| 01D.04 | Site Survey and Site Design price for year 4 | FFP | Non-recurring per Airport | $ - 0 | 4.2.9.1 – 4.2.9.3 | - 0 |
| 01D.05 | Site Survey and Site Design price for year 5 | FFP | Non-recurring per Airport | $ - 0 | 4.2.9.1 – 4.2.9.3 | - 0 |
| AUS | Subtotal | $ - 0 | ||||
| BNA | Subtotal | $ - 0 | ||||
| DAL | Subtotal | $ - 0 | ||||
| IND | Subtotal | $ - 0 | ||||
| TPA | Subtotal | $ - 0 |
CLIN2
| SubCLIN | Description | Contract Type | Charge Type | Price | Requirements Met | Quantity for Evaluation |
| 0002A.01 | Non-recurring price to establish incremental enhanced capability as identified by Offeror provided requirements | FFP | Non-recurring per Airport | $ - 0 | C.4.3.1 | 1 |
| 0002B.01 | Monthly recurring price to provide incremental enhanced capability as identified by Offeror provided requirements | FFP | Recurring per Airport | $ - 0 | C.4.3.1 | 6 |
| 0002A.02 | Non-recurring price to establish incremental enhanced capability as identified by Offeror provided requirements | FFP | Non-recurring per Airport | $ - 0 | C.4.3.1 | - 0 |
| 0002B.02 | Monthly recurring price to provide incremental enhanced capability as identified by Offeror provided requirements | FFP | Recurring per Airport | $ - 0 | C.4.3.1 | 12 |
| 0002A.03 | Non-recurring price to establish incremental enhanced capability as identified by Offeror provided requirements | FFP | Non-recurring per Airport | $ - 0 | C.4.3.1 | - 0 |
| 0002B.03 | Monthly recurring price to provide incremental enhanced capability as identified by Offeror provided requirements | FFP | Recurring per Airport | $ - 0 | C.4.3.1 | 12 |
| 0002A.04 | Non-recurring price to establish incremental enhanced capability as identified by Offeror provided requirements | FFP | Non-recurring per Airport | $ - 0 | C.4.3.1 | - 0 |
| 0002B.04 | Monthly recurring price to provide incremental enhanced capability as identified by Offeror provided requirements | FFP | Recurring per Airport | $ - 0 | C.4.3.1 | 12 |
| 0002A.05 | Non-recurring price to establish incremental enhanced capability as identified by Offeror provided requirements | FFP | Non-recurring per Airport | $ - 0 | C.4.3.1 | - 0 |
| 0002B.05 | Monthly recurring price to provide incremental enhanced capability as identified by Offeror provided requirements | FFP | Recurring per Airport | $ - 0 | C.4.3.1 | 12 |
| AUS | Subtotal | $ - 0 | ||||
| BNA | Subtotal | $ - 0 | ||||
| DAL | Subtotal | $ - 0 | ||||
| IND | Subtotal | $ - 0 | ||||
| TPA | Subtotal | $ - 0 |
EvaluatedPricePerAirport
| Airport | Price | Value |
| AUS | Evaluated Price Base Services | $ - 0 |
| BNA | Evaluated Price Base Services | $ - 0 |
| DAL | Evaluated Price Base Services | $ - 0 |
| IND | Evaluated Price Base Services | $ - 0 |
| TPA | Evaluated Price Base Services | $ - 0 |
| AUS | Evaluated Price Enhanced Capabilities | $ - 0 |
| BNA | Evaluated Price Enhanced Capabilities | $ - 0 |
| DAL | Evaluated Price Enhanced Capabilities | $ - 0 |
| IND | Evaluated Price Enhanced Capabilities | $ - 0 |
| TPA | Evaluated Price Enhanced Capabilities | $ - 0 |
LaborRates
| Labor Category | Labor Category Level | Experience & Education | Year | T&M Hourly Rate |
| Program Management | Level 5 | Work Experience and Education Requirements | 1 | $ - 0 |
| Program Management | Level 4 | Work Experience and Education Requirements | 1 | $ - 0 |
| Program Management | Level 3 | Work Experience and Education Requirements | 1 | $ - 0 |
| Program Management | Level 2 | Work Experience and Education Requirements | 1 | $ - 0 |
| Program Management | Level 1 | Work Experience and Education Requirements | 1 | $ - 0 |
| Program Management | Level 5 | Work Experience and Education Requirements | 2 | $ - 0 |
| Program Management | Level 4 | Work Experience and Education Requirements | 2 | $ - 0 |
| Program Management | Level 3 | Work Experience and Education Requirements | 2 | $ - 0 |
| Program Management | Level 2 | Work Experience and Education Requirements | 2 | $ - 0 |
| Program Management | Level 1 | Work Experience and Education Requirements | 2 | $ - 0 |
| Program Management | Level 5 | Work Experience and Education Requirements | 3 | $ - 0 |
| Program Management | Level 4 | Work Experience and Education Requirements | 3 | $ - 0 |
| Program Management | Level 3 | Work Experience and Education Requirements | 3 | $ - 0 |
| Program Management | Level 2 | Work Experience and Education Requirements | 3 | $ - 0 |
| Program Management | Level 1 | Work Experience and Education Requirements | 3 | $ - 0 |
| Program Management | Level 5 | Work Experience and Education Requirements | 4 | $ - 0 |
| Program Management | Level 4 | Work Experience and Education Requirements | 4 | $ - 0 |
| Program Management | Level 3 | Work Experience and Education Requirements | 4 | $ - 0 |
| Program Management | Level 2 | Work Experience and Education Requirements | 4 | $ - 0 |
| Program Management | Level 1 | Work Experience and Education Requirements | 4 | $ - 0 |
| Program Management | Level 5 | Work Experience and Education Requirements | 5 | $ - 0 |
| Program Management | Level 4 | Work Experience and Education Requirements | 5 | $ - 0 |
| Program Management | Level 3 | Work Experience and Education Requirements | 5 | $ - 0 |
| Program Management | Level 2 | Work Experience and Education Requirements | 5 | $ - 0 |
| Program Management | Level 1 | Work Experience and Education Requirements | 5 | $ - 0 |
| Engineering | Level 5 | Work Experience and Education Requirements | 1 | $ - 0 |
| Engineering | Level 4 | Work Experience and Education Requirements | 1 | $ - 0 |
| Engineering | Level 3 | Work Experience and Education Requirements | 1 | $ - 0 |
| Engineering | Level 2 | Work Experience and Education Requirements | 1 | $ - 0 |
| Engineering | Level 1 | Work Experience and Education Requirements | 1 | $ - 0 |
| Engineering | Level 5 | Work Experience and Education Requirements | 2 | $ - 0 |
| Engineering | Level 4 | Work Experience and Education Requirements | 2 | $ - 0 |
| Engineering | Level 3 | Work Experience and Education Requirements | 2 | $ - 0 |
| Engineering | Level 2 | Work Experience and Education Requirements | 2 | $ - 0 |
| Engineering | Level 1 | Work Experience and Education Requirements | 2 | $ - 0 |
| Engineering | Level 5 | Work Experience and Education Requirements | 3 | $ - 0 |
| Engineering | Level 4 | Work Experience and Education Requirements | 3 | $ - 0 |
| Engineering | Level 3 | Work Experience and Education Requirements | 3 | $ - 0 |
| Engineering | Level 2 | Work Experience and Education Requirements | 3 | $ - 0 |
| Engineering | Level 1 | Work Experience and Education Requirements | 3 | $ - 0 |
| Engineering | Level 5 | Work Experience and Education Requirements | 4 | $ - 0 |
| Engineering | Level 4 | Work Experience and Education Requirements | 4 | $ - 0 |
| Engineering | Level 3 | Work Experience and Education Requirements | 4 | $ - 0 |
| Engineering | Level 2 | Work Experience and Education Requirements | 4 | $ - 0 |
| Engineering | Level 1 | Work Experience and Education Requirements | 4 | $ - 0 |
| Engineering | Level 5 | Work Experience and Education Requirements | 5 | $ - 0 |
| Engineering | Level 4 | Work Experience and Education Requirements | 5 | $ - 0 |
| Engineering | Level 3 | Work Experience and Education Requirements | 5 | $ - 0 |
| Engineering | Level 2 | Work Experience and Education Requirements | 5 | $ - 0 |
| Engineering | Level 1 | Work Experience and Education Requirements | 5 | $ - 0 |
| Implementation | Level 5 | Work Experience and Education Requirements | 1 | $ - 0 |
| Implementation | Level 4 | Work Experience and Education Requirements | 1 | $ - 0 |
| Implementation | Level 3 | Work Experience and Education Requirements | 1 | $ - 0 |
| Implementation | Level 2 | Work Experience and Education Requirements | 1 | $ - 0 |
| Implementation | Level 1 | Work Experience and Education Requirements | 1 | $ - 0 |
| Implementation | Level 5 | Work Experience and Education Requirements | 2 | $ - 0 |
| Implementation | Level 4 | Work Experience and Education Requirements | 2 | $ - 0 |
| Implementation | Level 3 | Work Experience and Education Requirements | 2 | $ - 0 |
| Implementation | Level 2 | Work Experience and Education Requirements | 2 | $ - 0 |
| Implementation | Level 1 | Work Experience and Education Requirements | 2 | $ - 0 |
| Implementation | Level 5 | Work Experience and Education Requirements | 3 | $ - 0 |
| Implementation | Level 4 | Work Experience and Education Requirements | 3 | $ - 0 |
| Implementation | Level 3 | Work Experience and Education Requirements | 3 | $ - 0 |
| Implementation | Level 2 | Work Experience and Education Requirements | 3 | $ - 0 |
| Implementation | Level 1 | Work Experience and Education Requirements | 3 | $ - 0 |
| Implementation | Level 5 | Work Experience and Education Requirements | 4 | $ - 0 |
| Implementation | Level 4 | Work Experience and Education Requirements | 4 | $ - 0 |
| Implementation | Level 3 | Work Experience and Education Requirements | 4 | $ - 0 |
| Implementation | Level 2 | Work Experience and Education Requirements | 4 | $ - 0 |
| Implementation | Level 1 | Work Experience and Education Requirements | 4 | $ - 0 |
| Implementation | Level 5 | Work Experience and Education Requirements | 5 | $ - 0 |
| Implementation | Level 4 | Work Experience and Education Requirements | 5 | $ - 0 |
| Implementation | Level 3 | Work Experience and Education Requirements | 5 | $ - 0 |
| Implementation | Level 2 | Work Experience and Education Requirements | 5 | $ - 0 |
| Implementation | Level 1 | Work Experience and Education Requirements | 5 | $ - 0 |
MaximumEscalation
| Description | Value |
| Maximum Annual Escalation factor. | 0% |
File details come from the government source that posted it. Updated .