View the file

Other files

File Type Posted
Amendment 0007 Attachment 1 RFI Question Answer MATOC Solicitation.pdf PDF
Amendment 0007 Solicitation 36C26222R0044.pdf PDF
Amendment 0006 Solicitation 36C26222R0044.pdf PDF
Amendment 0005 Attachment 7 RFI Questions 28-51-119 B162 Geotechnical Evaluation Report.pdf PDF
Amendment 0005 Attachment 8 RFI Questions 28-51-119 Lab Pharmacy Soils Report.pdf PDF
Amendment 0005 Attachment 12 RFI 125 SF 24.pdf PDF
Amendment 0005 Attachment 5 RFI 24 Specification 32 12 16 Asphalt Paving.pdf PDF
Amendment 0005 Solicitation 36C26222R0044.pdf PDF
Amendment 0005 Attachment 15 Earthwork Fill Material Lab Rpt.pdf PDF
Amendment 0005 Attachment 10 RFI Questions 104-107 B162 Elevator Airflow.pdf PDF
Amendment 0005 Attachment 19 Testing_and_Inspection_Plans_Elevator_Pit_Footing_17.09.21_(28)_Day_Bre_14167911.pdf PDF
Amendment 0005 Attachment 2 RFI 11 Seed Project.pdf PDF
Amendment 0005 Attachment 17 GTI New Lab Pharmacy As Builts.pdf PDF
Amendment 0005 Attachment 1 RFI 2 Seed Project Physical_Access_Control__Data.pdf PDF
Amendment 0005 Attachment 9 RFI 34 EPDM Submittal.pdf PDF
Amendment 0005 Attachment 3 RFI Questions 20-104-107 B162 Elevator Drawings.pdf PDF
Amendment 0005 Attachment 6 RFI Questions 28-30-51-81-82 119 ED Soils Report.pdf PDF
Amendment 0005 Attachment 20 Testing_and_Inspection_Plans_Elevator_Pit_Walls_17.09.28_(7)_Day_Break_14167948.pdf PDF
Amendment 0005 Attachment 4 RFI Questions 20-104-107 B164 Elevator Drawings.pdf PDF
Amendment 0005 Attachment 13 RFI Questions 23-25-54-84 Additional Civil Specs.pdf PDF
Amendment 0005 FAR 52.216-22.pdf PDF
Amendment 0005 Seed Project RFI Questions and Answers.pdf PDF
Amendment 0005 Attachment 14 Earthwork Base Course Lab Rpt.pdf PDF
Amendment 0005 Attachment 11 RFI Questions 104 and 107 B162 Elevator Pit.pdf PDF
Amendment 0005 Attachment 16 ED Drainage Details.pdf PDF
Amendment 0005 Attachment 18 Proposed Lab_Pharmacy Bldg Plans_Hole locations.pdf PDF
Amendment 0004 Solicitation 36C26222R0044.pdf PDF
Amendment 0003 Solicitation 36C26222R0044.pdf PDF
Amendment 0002 Attachment 1 Site Visit Sign-In Sheet.pdf PDF
Amendment 0002 Solicitation 36C26222R0044.pdf PDF
Amendment 0001 Attachment 1 Site Visit Map - Bldg. 19.pdf PDF
Amendment 0001 Solicitation 36C26222R0044.pdf PDF
S02 Solicitation Attachment 2 Technical Proposal Data.docx DOCX document
Amendment 0001 Attachment 2 Seed Project Site Visit Information.pdf PDF
S02 Solicitation Attachment 3 Evaluation Ratings and Definitions.pdf PDF
S02 Solicitation Attachment 6 Contractor Surety Limitations.docx DOCX document
S02 Solicitation Attachment 4 Subcontractor Information And Consent.docx DOCX document
S02 Solicitation Attachment 1 Past Performance Questionnaire.docx DOCX document
S02 Solicitation Attachment 13 Seed Project Specifications.pdf PDF
S02 Solicitation Attachment 5 Bid Schedule - MATOC SEED Project.docx DOCX document
S02 Solicitation Attachment 12 Seed Project Drawings.pdf PDF
S02 Solicitation Attachment 9 Contractor Safety and EMR Info.docx DOCX document
S02 Solicitation Attachment 14 Seed Project Structural Calculations.pdf PDF
S02 Solicitation Attachment 7 Financial Disclosure Questionnaire.docx DOCX document
S02 Solicitation Attachment 2 Technical Proposal Data.docx DOCX document
S02 Solicitation Attachment 10 Seed Project Wage Determination.pdf PDF
S02 Solicitation Attachment 8 Location Capabilities Questionnaire.docx DOCX document
S02 Solicitation Attachment 11 Prescott Facility Map.pdf PDF
S02 Solicitation 36C26222R0044.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Prescott Install Elevators and Space Build Out in Buildings 162 and 164 Project 649-22-136

This project is to install the elevators that were descoped from the construction of Buildings 162 and 164, and address the operational issues that have become apparent after the building have been in operation for several years, including delivery area shortcomings, patient counseling facilities, Pharmacy Cache location problems, breakroom renovation, and additional offices in Building 164, and patient flow issues in Building 162.

Security

The C&A requirements do not apply, and a Security Accreditation Package is not required.

NAVAHCS Historic District Requirements

Building 162 and 164 are not listed on the Register of Historic Places, however they are both on the Fort Whipple Historic District. Although no changes inside the buildings need to be approved through the Arizona SHPO, all excavation work needs to be approved. All excavation work requires archeological monitoring, regardless of the depth, unless the area has been previously disturbed, which should apply to all excavation work in this project.

However, this must be reviewed by SHPO prior to the start of the excavation. If monitoring is required the certification requirements for the monitor can be found at The Secretary of the Interior Professional Qualifications Standards | U.S. Department of the Interior (doi.gov)

Smoking

Smoking is prohibited on site for contract employees.

Parking

Parking is available for contractor in Lot “S”, which is North of the construction area.

TB

TB testing will be required for contractors working on the site.

Badging

All contract employees will be required to have a security badge issued by the NAVAHCS VAPD prior to start of any work. To be issued a badge the contractor must contact the COR at least 72 hours prior to the employee arriving on site so the COR can officially request that a badge be issued to the employee. Once this has been done the contract employee must go to be Building 28 and show the VAPD an official form of ID (typically a driver’s license) and they will be issued a badge. The contractor must provide the full legal name of the employee, along with how many weeks or months that are expected to be on site and (if they are a subcontractor) what company they work for. If the employee fails to provide some official form of identification they will not be give a badge and will be sent off the site.

Construction Site Security

A 7’ (or higher) construction fence is required to be around any construction site that can be accessed by non-contractor personnel. The specific requirements for the fence can be found in Section 1.6.I of specification section 01 00 00. All interior work requires that the work areas be either inside a negative pressure enclosure or clearly marked as off limits to non-construction personnel.

Photographs

Photographs of the construction site are acceptable provided that no patients are included in the photograph. A professional photographer is not required for the project, just clear photographs with attached information describing the location of the photograph, and if necessary, the reason for the photograph.

Laydown area

The laydown area will be on the west side of Building 107, near the entrance to the “B” courtyard.

Road closures

A road closure leading to the ED is expected as part of the project. Prior to closing the road, the process of getting an ambulance to the ED ambulance entrance will need to be worked out with the COR. Because of the significance of closing an ambulance access way, a 2 week notice for the closure will be needed, and a process for allowing ambulances through after hours will need to be developed and approved. A plan for the closure, including the plan for signage and flaggers will be required.

Utility shutdowns

Utility shutdowns that will affect other buildings will need to be planned with the COR and have at least 7 days of notification prior to the shutdown.

Phasing

The Pharmacy Cache will need to be completed prior to any other work being done. This is necessary for a different project that will displace the existing Pharmacy Cache, so the pharmacy cache is the highest priority for completion. There are no additional phasing requirements.

ILSM

If the man door on the lower lever of B164 is blocked for reason for more than 4 hours at a time, an ILSM plan will be needed. Since there is some re-sloping work at the exterior apron adjacent to Room 15, the construction fence at the area should be placed as to not block the exterior door on the ground floor to eliminate the need for an ILSM for the project.

ICRA

The work in both B162 and B164 will require all IC measures listed in Class III precautions.

File details come from the government source that posted it. Updated .