S02-RFP Attachment 17-Drawings-Dublin_Part8.pdf
PDF 2 MB Posted
- Solicitation number
- 36C77626R0031_1
About this file
These are construction design documents for the renovation of Building 9A at Carl Vinson VA Medical Center in Dublin, Georgia, prepared by SPEES Design Build as the Architect/Engineer of Record. The project (557-21-703) involves converting Building 9A into EHRM (Employee Health Records Management) Administrative Space across two phases, with the documents dated June 14, 2024.
The electrical construction documents include lighting plans (EL101-EL102) for Level 01 showing fixture locations, control systems, and emergency lighting provisions; power plans (EP100-EP101) detailing panelboard locations, branch circuits, equipment connections, and feeder routing across multiple buildings (03, 09A, and 11); and general electrical notes addressing coordination requirements, existing equipment modifications, conduit routing, circuit directory updates, and fire rating compliance. Key specifications require low-voltage dimmable lighting controls with occupancy sensors, emergency transfer switches for designated fixtures, coordination of all electrical work with construction phasing and other trades, protection of existing systems from damage, maintenance of power to essential equipment during construction with backup power provisions, sealing of wall and ceiling penetrations to match fire ratings, and updated circuit panel directories for affected panels. The drawings reference panelboards 9LNA1-9LNA6, 9LCA1-9LCA2, and emergency panel 11LCC1, with conduit routing directed overhead to accessible ceilings where available and core-drilled floor penetrations requiring X-ray scanning to avoid structural members.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
aMo
M o
M oM o M o
Mo tt b f Mo c e b a hi ihgfg
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
MoOS
OS OS
OS
OS OS OS
OS
aMo
M o
M oM o M o
Mo tt b f Mo c e b a hi ihgfg
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
MoOS
OS OS
OS
OS OS OS
OS
AREA OF WORK
BLDG 09A
BLDG 03BLDG 11
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 60 61 62 63 64
17 18 19 20 21 25 26 27 28 29 30 31 32
E-502
HAC
TR
CORRIDOR
CR11-9
IV TESTING
IV SUPPORT
WAITING
ALCOVE
IV TESTING
CORRIDOR
CR11-9
STAFF BREAK
MECHANICAL
RESTROOM
RESTROOM
RESTROOM
RESTROOM
STORAGE
CORRIDOR
CR11-9
L1 c
L1 c
L1
L1
L1 c
L2 c
L1 c
L1 c
L1 c
L1
L1 g
L1 g
L1 g
L1 g
L1 g
L1 f
L1 f
L1 f
L1 f
L1 f
L1
L1
L1
L1
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1
L3
MECHANICAL
ELECTRICAL ROOM
E-401
L4
L4
L4
L1
L1
L1 L1
X
X
X
X
X a L1 a L1 a L1 a L1 a L1 a L1 a L1 a L1 a L1 b L1 b L1 b L1 b L1 b L1 b L1 b L1 b L1 b L1 h L1 h L1 h L1 h L1 h L1 h L1 h L1 h L1 h L1 i L1 i L1 i L1 i L1 i L1 i L1 i L1 i L1 i L1
L3 tt
L3 tt
L3 tt
L3 tt g
L4 L4
L4
L4 L4 L4
L2
L2
L1
L1
L1
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c L1 f
L1 f
L1 f
L1 L1 g
L1L1
ELECTRICAL
CLOSET
STG
103A e e a a b b f f g g h h i i
E-502TYP.
TYP.
PNL '9LNA6'
PNL '9LNA4'
PNL '9LNA3'
PNL '9LCA2'
9LNA6-4
9LNA6-6
9LNA6-8
9LNA6-10
9LNA6-20
9LNA6-20
9LNA6-20
9LNA6-229LNA6-24
c
9LNA6-24
CHANGE
MGMT USER
9LNA6-24
9LNA5-40
(TYPICAL FOR ALL
LIGHTING IN CORRIDOR
"CR11-9")
9LNA5-42
9LNA5-449LNA6-45 9LNA6-47 9LNA6-49 9LNA6-51
3 TYP.
L1 c
X e e e e e e e e c c c c c
PNL '9LNA5'
c c
L1 f g g c c
X
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
(206) 590-2118
RAY SPEES
/1
/2
:2
:4
P
M
A u to d e s k D o c s /5
-2
-7
V A
G A
D u b lin
E H
R M
T A
S S
/V A
D U
C
E N
T R
A L
E
L
S D
B .r v t
EL101
BLDG 09A - LEVEL 01 - LIGHTING
PLAN - PHASE 1 09A
JPB/WNM BCL
CONSTRUCTION
DOCUMENTS
06/14/2024
557-21-703RENOVATE BUILDING 9A FOR
EHRM ADMINISTRATIVE SPACE
CARL VINSON VA MEDICAL CENTER _ DUBLIN, GA
KEY PLAN
GENERAL NOTES
TRUE
NORTH
KEY NOTES
- 1" = 10'-0"
1 BLDG 09A - LEVEL 01 - LIGHTING PLAN - PHASE 1
Revisions: Date:
0 10' 20'
PROJECT
NORTH
TRUE NORTH
(DASHED)
EXISTING LUMINAIRES SHALL BE SWITCHED BY ROOM WALL OCCUPANCY SWITCH;
UTILIZE EXISING RACEWAYS AND CONDUCTORS AS REQUIRED.
EXISTING LUMINAIRES SHALL MAINTAIN EXISTING OPERABILITY. IF NECESSARY,
EXTEND EXISTING CONDUIT AND WIRE AS REQUIRED.
ALL LUMINAIRES WITH SHADED SYMBOLS SHALL BE PROVIDED WITH NORMAL AND
EMERGENCY POWER VIA EMERGENCY LIGHTING UL-1008 TRANSFER SWITCH.
PROVIDE RACEWAYS AND WIRING TO INTERFACE WITH FIRE ALARM SYSTEM AS
REQUIRED. LOCATE TRANSFER SWITCH(ES) WITHIN ELECTRICAL CLOSET 115.
REFERENCE PANELBOARD SCHEDULE "9LCA2" FOR ADDITIONAL EMERGENCY
CIRCUITING INFORMATION.
1. COORDINATE LIGHTING INSTALLATIONS WITH ALL OBSTRUCTIONS AND EQUIPMENT.
2. ALL ELECTRICAL WORK SHALL BE CLOSELY COORDINATED WITH THE CONTRACTORS
PHASING OF THE PROJECT. COORDINATE ALL ELECTRICAL WORK WITH ALL OTHER
TRADES.
3. MAKE ALL CONNECTIONS TO EQUIPMENT PER MANUFACTURER'S REQUIREMENTS.
4. ROUTE ALL CONDUIT HOME RUNS TO PANELS OVERHEAD AND ABOVE ACCESSIBLE
CEILINGS WHERE AVAILABLE.
5. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
6. ALL FINAL LOCATIONS AND ARRANGEMENTS OF CEILING LIGHTING FIXTURES SHALL
BE COORDINATED WITH ALL OTHER TRADES.
7. ALL LIGHTING CONTROLS SHALL BE LOW-VOLTAGE AND PROVIDE DIMMABLE
CONTROL UNLESS OTHERWISE NOTED. LINE VOLTAGE WALL MOUNTED OCCUPANCY
SWITCHES SHALL BE NON-DIMMABLE.
8. LOCATION AND QUANTITIES OF OCCUPANCY SENSORS ARE SHOWN FOR
FUNCTIONAL PURPOSES ONLY. POWER PACKS ARE NOT SHOWN FOR CLARITY
REASONS; PROVIDE POWER PACKS AS REQUIRED. CONTRACTOR SHALL PROVIDE
ALL REQUIRED LIGHTING CONTROL DEVICES (QUANTITIES AND TYPES) AS REQUIRED
FOR A COMPLETE AND FULLY FUNCTIONAL SYSTEM.
aMo
M o
M oM o M o
Mo tt b f Mo c e b a hi ihgf
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
OS
MoOS
OS OS
OS
OS OS OS
OS
aMo
M o
M oM o M o
Mo tt b f Mo c e b a hi ihgfg
Mo
AREA OF WORK
BLDG 09A
BLDG 03BLDG 11
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 60 61 62 63 64
17 18 19 20 21 25 26 27 28 29 30 31 32
L1 c
L1 c
L1
L1
L1 c
L4
L1 c
L2 c
L1 c
L1 c
L1 c
L1 c
L1 c
L4
L1 c
HAC
TR ROOM
CORRIDOR
CR11-9
CLASSROOM
103A
CLASSROOM
103B
CLASSROOM
104A
CLASSROOM
106A
CLASSROOM
106B
CORRIDOR
CR11-9
STAFF BREAK
MECH
RESTROOM
RESTROOM
RESTROOM
RESTROOM
STORAGE
CORRIDOR
CR11-9
L1 g
L1 g
L1 g
L1 g
L1 g
L1 g
L1 g
L1 g
L1 g
L1 f
L1 f
L1 f
L1 f
L1 f
L1 f
L1 f
L1 f
L1 f
L1
L1
L1
L1
L1 c
L1 c
L1 c
L1 c
L1 c
L1 cL1
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1 c
L1
L3
L1
ELECTRICAL
L4 a L1 a L1 a L1 a L1 a L1 a L1 a L1 a L1 a L1 b L1 b L1 b L1 b L1 b L1 b L1 b L1 b L1 b L1 h L1 h L1 h L1 h L1 h L1 h L1 h
L1 h L1 h L1 i L1 i L1 i L1 i L1 i L1 i L1 i L1 i L1 i L1
L1
L1L1
L1 L1
L1L1
L4
L4
L4 L4
CLASSROOM
104B
MECHANICAL
102A e e a a b b f f g g h h i i c ccc c c
L3 tt
L3 tt
L3 tt
L3 tt e e e e e e e e c c
L4
L4
X
X c
X
L2
L2 X
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
(206) 590-2118
RAY SPEES
/1
/2
:5
:1
P
M
A u to d e s k D o c s /5
-2
-7
V A
G A
D u b lin
E H
R M
T A
S S
/V A
D U
C
E N
T R
A L
E
L
S D
B .r v t
EL102
BLDG 09A - LEVEL 01 - LIGHTING
PLAN - PHASE 2 09A
JPB/WNM BCL
CONSTRUCTION
DOCUMENTS
06/14/2024
557-21-703RENOVATE BUILDING 9A FOR
EHRM ADMINISTRATIVE SPACE
CARL VINSON VA MEDICAL CENTER _ DUBLIN, GA
KEY PLAN
GENERAL NOTES
TRUE
NORTH
KEY NOTES
0 10' 20'
PROJECT
NORTH
TRUE NORTH
(DASHED)
- 1" = 10'-0"
1 BLDG 09A - LEVEL 01 - LIGHTING PLAN - PHASE 2
Revisions: Date:
1. SHEET INCLUDED TO DEPICT FINAL LIGHTING LAYOUT WITH ARCHITECTURAL
EXTENDABLE WALLS.
ARCHITECTURAL EXTENDABLE WALL.1
CONSTRUCTION
DOCUMENTS
X c t
AREA OF WORK
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 60 61 62 63 64
17 18 19 20 21 25 26 27 28 29 30 31 32
3LNC1
MS-3LNC1
CONTINUES TO PANEL '9LNA5'.
REFERENCE SHEET EP101 FOR
CONTINUATION.
APPROX. LOCATION
PANEL '11LCC1'
APPROXIMATE FOOTPRINT OF
TR 100 ON LEVEL 01 ABOVE
CONTINUES TO PANEL '9LCA3'.
REFERENCE SHEET E-401 FOR
CONTINUATION.
1 CONTINUED FROM PANEL '9LNA5'.
REFERENCE SHEET EP101 FOR
CONTINUATION.
CONTINUES TO PANEL '9LNA7'.
REFERENCE SHEET E-401 FOR
CONTINUATION.
09-P-10
09-P-03
09-P-01
09-P-04
CONTINUES TO SOUTH
SIDE OF BUILDING 11
CORRIDOR
BUILDING 03
BUILDING 11
CORRIDOR
BUILDING 9A CORRIDOR
5 4
BM116-3
CORRIDOR BUILDING 11BUILDING 9A
PRIMARY BONDING
BUSBAR (PBB)
E-503
APPROXIMATE FOOTPRINT OF
ELECTRICAL ROOM 116 ON
LEVEL 01 ABOVE
CONTINUE TO PANEL '9LNA1'.
REFERENCE SHEET EP101 FOR
CONTINUATION.
A SIDE POWER
B SIDE POWER
SHEET SHALL PRINTED
IN COLOR TO PROVIDE
ALL INFORMATION.
LEGEND:
BLDG 09A
BLDG 03BLDG 11
CORRIDOR
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
(206) 590-2118
RAY SPEES
/1
/2
:5
:2
P
M
A u to d e s k D o c s /5
-2
-7
V A
G A
D u b lin
E H
R M
T A
S S
/V A
D U
C
E N
T R
A L
E
L
S D
B .r v t
EP100
BLDG 03, 09A, AND 11 - LEVEL 00 -
POWER PLAN - PHASE 1 03, 09A, 11
JPB/WNM BCL
CONSTRUCTION
DOCUMENTS
06/14/2024
557-21-703RENOVATE BUILDING 9A FOR
EHRM ADMINISTRATIVE SPACE
CARL VINSON VA MEDICAL CENTER _ DUBLIN, GA
KEY PLAN
GENERAL NOTES
TRUE
NORTH
KEY NOTES
1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.
2. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
3. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN
ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH
VA STANDARDS.
4. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
5. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
6. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
7. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
8. ALL ELECTRICAL WORK SHALL BE CLOSELY COORDINATED WITH THE CONTRACTORS
PHASING OF THE PROJECT. COORDINATE ALL ELECTRICAL WORK WITH ALL OTHER
TRADES.
9. MAKE ALL CONNECTIONS TO EQUIPMENT PER MANUFACTURER'S REQUIREMENTS.
10. ROUTE ALL CONDUIT HOME RUNS TO PANELS OVERHEAD AND ABOVE ACCESSIBLE
CEILINGS WHERE AVAILABLE.
CORE-DRILLED CONDUIT FLOOR PENETRATION. PROVIDE XRAY SCAN OF AREA
PRIOR TO DRILLING TO AVOID STRUCTURAL MEMBERS; COORDINATE WITH
STRUCTURAL AS REQUIRED.
EXISTING SWITCHBOARD 'MS-3LNC1' TO BE MODIFIED. REFER TO ONE-LINE DIAGRAM
ON SHEET EP602 FOR MORE INFORMATION.
EXISTING EMERGENCY PANEL '11LCC1' TO BE MODIFIED. REFER TO ONE-LINE
DIAGRAM ON SHEET EP601 FOR MORE INFORMATION.
PROVIDE TBC AS SHOWN. REFERENCE TELECOMMUNICATIONS BONDING RISER
DIAGRAM ON SHEET ET601 FOR ADDITIONAL INFORMATION.
CONTINUE TBB TO TR SBBs. REFERENCE TELECOMMUNICATIONS BONDING RISER
DIAGRAM ON SHEET ET601 FOR ADDITIONAL INFORMATION.
- 1/16" = 1'-0"
1 BLDG 03, 09A, AND 11 - LEVEL 00 - POWER PLAN - PHASE 1 8'0 16' 32'
PROJECT
NORTH
TRUE NORTH
(DASHED)
Revisions: Date:
CONSTRUCTION
DOCUMENTS
OS
OS
AREA OF WORK
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 60 61 62 63 64
17 18 19 20 21 25 26 27 28 29 30 31 32
FA EQUIPMENT
FACP (ABOVE)
FACP BATTERY BOX (BELOW)
PNL '9LCA1'
PNL '9LNA1'
PNL '9LNA2'
PULL BOX
PULL BOX
POWER SUPPLY EXPANDER
TYP.
CHANGE MGMT USER
IV SUPPORT
MECHANICAL
HAC
STORAGE
IV TESTING
IV TESTING
TR
STAFF BREAK
WAITING ALCOVE
RESTROOM
CORRIDOR
CR11-9
ELECTRICAL ROOM
RESTROOM
RESTROOM
RESTROOM
009A-EF-03
9LNA6-23
009A-EF-04
9LNA6-25
009A-EF-02
9LNA6-15
009A-EF-01
9LNA6-4
E-401
FRIDGE
9LNA6-29
AC
MICROWAVE
9LNA6-25
P-103B
9LNA6-12
P-418B
9LNA6-14
P-418D
9LNA6-14
P-103D
9LNA6-12
P-103A
9LNA6-12
P-418A
9LNA6-14
PNL '9LNA5'
9LNA6-7
9LNA6-39
9LNA6-41
9LNA6-2
9LNA6-41
9LNA6-41
9LNA6-41
9LNA6-35
9LNA5-31 9LNA5-31 9LNA5-10 9LNA5-10 9LNA5-39
09A-EF-05
9LNA5-41
ELECTRICAL
CLOSET
009A-VAV-11
9LNA5-41
009A-VAV-10
9LNA5-41
009A-VAV-06
9LNA6-30
009A-VAV-05
9LNA6-30
009A-VAV-01
9LNA6-30
009A-VAV-03
9LNA6-30
009A-VAV-04
9LNA6-30
009A-VAV-09
9LNA5-41
009A-VAV-08
9LNA5-41
AC
AC
P-103C
9LNA6-12
P-418C
9LNA6-14
09-P-02
09-P-07 09-P-06
TV TV TV TV TVTV TV
TV
TV
TYP.
TV
TV
TV
009A-VAV-02
9LNA6-30
009A-VAV-07
9LNA5-41
9LNA6-1
9LNA6-3
9LNA6-5
9LNA6-9
9LNA6-11
9LNA6-13
9LNA6-17
9LNA6-15
9LNA6-19
9LNA6-21
9LNA6-23
PNL '9LCA2'
PNL '9LNA6'
PNL '9LNA4'
PNL '9LNA3'
COFFEE MAKER
9LNA6-27
9LNA6-31
9LNA6-33
9LNA6-33
9LNA6-37
9LNA6-35
TYP.
8 9LNA6-39
9LNA5-15
9LNA5-13
9LNA5-17
9LNA5-19
9LNA5-25
9LNA5-23
9LNA5-21
9LNA5-29
9LNA5-27
009A-AHU-1
9LNA5-12
9LNA5-10
9LNA5-8
9LNA5-16
9LNA5-14
9LNA5-18
9LNA5-20
9LNA5-22
9LNA5-24
9LNA5-28
9LNA5-26 9LNA5-32
9LNA5-30
9LNA5-33
9LNA5-37
9LNA5-35 9LNA5-34 9LNA5-36
9LNA5-37
STG
103A 9LNA5-39
MECHANICAL
9LNA5-39
9LNA5-37
9LNA6-18
9LNA6-16
9LNA6-16
9LNA6-16
9LNA6-18
9LNA5-43
09-P-01 7
09-P-08
09-P-09APROXIMATE
FOOTPRINT
OF RM 220
ABOVE
BLDG 09A
BLDG 03BLDG 11
A SIDE POWER
B SIDE POWER
SHEET SHALL PRINTED
IN COLOR TO PROVIDE
ALL INFORMATION.
LEGEND:
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ENGINEERING DISCIPLINE:
SPEES DESIGN BUILD
23830 PACIFIC HIGHWAY S. SUITE 203
KENT, WA 98032
(206) 590-2118
RAY SPEES
/1
/2
:5
:1
P
M
A u to d e s k D o c s /5
-2
-7
V A
G A
D u b lin
E H
R M
T A
S S
/V A
D U
C
E N
T R
A L
E
L
S D
B .r v t
EP101
BLDG 09A - LEVEL 01 - POWER
PLAN - PHASE 1 09A
JPB/WNM BCL
CONSTRUCTION
DOCUMENTS
06/14/2024
557-21-703RENOVATE BUILDING 9A FOR
EHRM ADMINISTRATIVE SPACE
CARL VINSON VA MEDICAL CENTER _ DUBLIN, GA
KEY PLAN
GENERAL NOTES
TRUE
NORTH
KEY NOTES
1. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES AND THE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
2. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN
ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH
VA STANDARDS.
3. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
4. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
5. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
6. ALL ELECTRICAL WORK SHALL BE CLOSELY COORDINATED WITH THE CONTRACTORS
PHASING OF THE PROJECT. COORDINATE ALL ELECTRICAL WORK WITH ALL OTHER
TRADES.
7. MAKE ALL CONNECTIONS TO EQUIPMENT PER MANUFACTURER'S REQUIREMENTS.
8. ROUTE ALL CONDUIT HOME RUNS TO PANELS OVERHEAD AND ABOVE ACCESSIBLE
CEILINGS WHERE AVAILABLE.
9. COORDINATE WITH OWNERS AGENT FOR FINAL LOCATIONS OF ALL RECEPTACLES
AND SPECIAL CONNECTIONS FOR EQUIPMENT PRIOR TO ROUGH-IN. COORDINATE
RECEPTACLE INSTALLATION WITH MILLWORK AND BACKSPLASH INSTALLERS TO
AVOID INTERFERENCES.
10. PROVIDE LOCAL DISCONNECTS RATED FOR EQUIPMENT LOAD FOR ALL MECHANICAL
EQUIPMENT. REFERENCE "EQUIPMENT SCHEDULE" LOCATED ON SHEET E-701 FOR
ADDITIONAL EQUIPMENT INFORMATION INCLUDING CONDUIT AND WIRE
REQUIREMENTS.
11. ALL EXTERIOR MOUNTED STARTERS OR DISCONNECTS SHALL BE NEMA 3R OR
GREATER.
12. NOT ALL CONDUIT TAGS MAY BE SHOWN. REFERENCE CONDUIT AND WIRE SCHEDULE
AND ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
- 1" = 10'-0"
1 BLDG 09A - LEVEL 01 - POWER PLAN - PHASE 1
EACH SET OF (2) WORKSTATIONS SHALL BE PROVIDED WITH (1) QUAD
RECEPTACLE. EXACT LOCATION OF RECEPTACLE SHALL BE COORDINATED WITH
VA PRIOR TO INSTALLATION TO CONFORM WITH VA WORKSTATION / FURNITURE
LAYOUT.
REPLACEMENT PANELBOARD. ALL EXISTING BRANCH CIRCUITS AND
PANELBOARD FEEDER SHALL BE EXTENDED TO REVISED LOCATION AS
REQUIRED.
RELOCATED EQUIPMENT. ALL EXISTING RACEWAYS AND CABLING SHALL
EXTEND TO REVISED LOCATION AS REQUIRED.
PROVIDE 120V CIRCUIT AS INDICATED TO CONNECT TO DIVISION 23 FURNISHED
120-24VAC TRANSFORMER. REFERENCE ASSOCIATED PANEL SCHEDULE AND
EQUIPMENT SCHEDULE FOR ADDITIONAL INFORMATION.
EXHAUST FAN CIRCUITED TO ROOM LIGHTING CIRCUIT.
CONTINUED FROM PANEL '9HLS1' ON FLOOR ABOVE. REFER TO ONE-LINE
DIAGRAM ON SHEET EP601 FOR MORE INFORMATION.
CONTINUED FROM SWITCHBOARD 'MS-3LNC1' ON SHEET EP100. REFER TO ONE-
LINE DIAGRAM ON SHEET EP602 FOR MORE INFORMATION.
COORDINATE TV RECEPTACLE MOUNTING HEIGHT WITH ARCHITECTURAL.
Revisions: Date:
0 10' 20'
PROJECT
NORTH
TRUE NORTH
(DASHED)
CONSTRUCTION
DOCUMENTS
File details come from the government source that posted it. Updated .