Ex C Form D (Rev. 1, 9/22/08) Exhibit C Form D – Subcontract Schedule September 16, 2019
EXHIBIT “C”
FORM D
SUBCONTRACT SCHEDULE
PN: Edit the Clause titles identified below to fit the Subcontract pro forma being used. For example, Services and Architect/Engineer proformas incorporate schedule requirements in the milestone clause.
Bidder to submit a Preliminary Subcontract Schedule addressing the Subcontract Target and Milestone dates listed in the Task Order Schedule and the Target/Milestone dates in the table below.
Bidder is to identify at least three potential problem areas that may affect successful subcontract completion and Bidder’s proposed resolution of each problem should it occur.
Based on the successful Bidder’s Preliminary Subcontract Schedule and CONTRACTOR requirements, an agreed schedule shall be developed after award, in accordance with RFP-0000476.
| Issue RFP |
| September 9,2019 |
| Pre-bid meeting & Site Visit |
| NA |
| Questions Due |
| September 13, 2019 |
| Response to Questions Complete |
| September 17,2019 |
| Bid Due Date |
| September 30, 2019 |
| Notice of Award (NOA) |
| October 14, 2019 |
| Pre-Job Submittals Complete |
| October 28, 2019 |
| Readiness Review Complete |
| November 11, 2019 |
| Notice to Proceed (NTP) |
| November 15, 2019 |
| Begin Mobilization |
| November 22,2019 |
| Fall 2019 round of sampling MDA-C |
| November 25, 2019 |
| Fall 2019 round of sampling MDA-L |
| November 25, 2019 |
| Field Summary Report for Fall round of sampling at MDA-C |
| 30 days after completion of sampling |
| Field Summary Report for Fall round of sampling at MDA-L |
| 30 days after completion of sampling |
| Spring 2020 round of sampling MDA-C |
| March-April 2020 |
| Spring 2020 round of sampling MDA-L |
| March-April 2020 |
| Field Summary Report for Spring 2020 round of sampling at MDA-C |
| 30 days after completion of sampling |
| Field Summary Report for Spring 2020 round of sampling at MDA-L |
| 30 days after completion of sampling |
| Draft annual Periodic Monitoring Report for Spring 2020 MDA-C sampling |
| 45 days after completion of spring sampling |
| Draft annual Periodic Monitoring Report for Spring 2020 MDA-L sampling |
| 45 day after completion of spring sampling |
| Fall 2020 round of sampling MDA-C |
| September-October 2020 |
| Fall 2020 round of sampling MDA-L |
| September-October 2020 |
| Field Summary Report for Fall 2020 sampling at MDA-C |
| 30 days after completion of sampling |
| Field Summary Report for Fall 2020 sampling at MDA-L |
| 30 days after completion of sampling |
| Spring 2021 round of sampling at MDA-C |
| March -April 2021 |
| Spring 2021 round of sampling at MDA-L |
| March -April 2021 |
| Field Summary Report for Spring 2021 sampling at MDA-C |
| 30 days after completion of sampling |
| Field Summary Report for Spring 2021 sampling at MDA-L |
| 30 days after completion of sampling |
| Draft annual Periodic Monitoring report MDA-C |
| 45 days after completion of spring sampling |
| Draft annual Periodic Monitoring report MDA-L |
| 45 days after completion of spring sampling |
PR# RFP-0000476