EX-I_Attachement_B_-_Subcontractor_Submittals__MDA_SVM.doc

DOC document 191 KB Posted

Attached to
MDA Soil Vapor Monitoring
Solicitation number
RFP-0000476
Issued by

About this file

Exhibit I Attachment B Subcontractor Submittals_MDA SVM

View the file

Other files

File Type Posted
Exhibit_D_MDA_Vapor_Monitoring_FINAL_Rev1.doc DOC document
RFP-0000476_MDA_Final_Rev._1.pdf PDF
Exhibit_C_Form_D_Subcontract_Schedule_-_FINAL.doc DOC document
RFP-0000476_Amendment_1_Rev_0_071619.docx DOCX document
map_19-0011-07_MDA_H_wells.pdf PDF
IMG_0173.jpg JPG image
IMG_0157.jpg JPG image
Appendix_D_2_N3B_RFI.docx DOCX document
IMG_0177.jpg JPG image
Appendix_D_5.docx DOCX document
IMG_0146.jpg JPG image
N3B-SOP-ER-2008.pdf PDF
WCSF_Vapor_Sampling_DRAFT.pdf PDF
RFP-0000476_MDA_Final.pdf PDF
IMG_0158.jpg JPG image
MDA_SVM_Training_Matrix_Rev0.docx DOCX document
IMG_0154.jpg JPG image
N3B-ER-SOP-20235.pdf PDF
IMG_0271.JPG JPG image
Certificate_of_Current_Cost_or_Pricing_Data.pdf PDF
Exhibit_C_FORM_F_Project_Organization_and_Workplan.doc DOC document
IMG_0141.jpg JPG image
IMG_0183.jpg JPG image
IMG_0266.JPG JPG image
MDA_L_-_Periodic_Monitoring_Report_for_Vapor_Sampling_-_Second_Quarter_FY11_LA-UR-11-4246.pdf PDF
N3B-AP-ER-1001.pdf PDF
IMG_0268.JPG JPG image
IMG_0253.JPG JPG image
Insurance_Requirements_RFP-0000476.pdf PDF
IMG_0167.jpg JPG image
EX-H_Final.pdf PDF
IMG_0138.jpg JPG image
manifold.jpg JPG image
Exhibit_C_FORM_C_Subcontractor_and_Vendor_List.doc DOC document
Exhibit_G_FINAL.pdf PDF
Exhibit_D_Appendix_D-8_SDDR_Form_2178.pdf PDF
map_19-0011-05_TA21_wells.pdf PDF
IMG_0181.jpg JPG image
Exhibit_C_Form_H_Resume_of_Key_Personnel_-_FINAL.doc DOC document
Exhibit_C_FORM_B_Construction_Plant_Equipment_List.doc DOC document
IMG_0269.JPG JPG image
switches.jpg JPG image
IMG_0151.jpg JPG image
IMG_0172.jpg JPG image
IMG_0252.JPG JPG image
Exhibit_C_FORM_C-1_Lower_Tier_Experience_Statement.doc DOC document
N3B-ER-SOP-10094.pdf PDF
Exhibit_C_Form_A_-_MDA_Vapor_Monitoring_FINAL.docx DOCX document
collecting_tritium_samples.jpg JPG image
N3B-ER-SOP-20145.pdf PDF
Show 40 more

Latest 50 of 86 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exhibit I Attachment B (Rev. 0, 2-23-09) Subcontractor Submittal Requirements Summary

Exhibit I Attachment B for EP (Rev. 0.1, 2-17-15) Subcontractor Submittal Requirements Summary

Dated 9/5/2019

Subcontractor Submittal Requirements Summary

NOTICE

Failure to submit required submittals as delineated on this form may result in withholding of payment in accordance with subcontract terms and conditions.

Submit To:
Overnight Delivery Address:
Regular Mailing Address:

SUBMITTAL SCHEDULE

A
Per Subcontract Schedule
S
Prior to Shipment
Z
When Required
SANN
Semi Annual
B
Prior to Balance of Payment
U
Prior to Use
ANN
Annually
WKLY
Weekly
F
Prior to Fabrication
W
Prior to Commencing Work
DAY
Daily
WRR
Implemented at work release level on Blanket Agreements
M
Prior to Mobilization
X
Prior to Purchase
MON
Monthly
BI-WKLY
Every 2 weeks
N
Prior to Notice to Proceed
Y
Prior to Progress Payment for Each Specific Task
QRTLY
Quarterly

SUBMITTAL TYPE REQUIRED

D
Drawings
ED
Electrical Diagrams
P
Prints /photocopies
SD
Shop Drawings
EM
Electronic media
II
Installation Instructions
PD
Performance Data - Curves
SP
Spare Parts and Maintenance Materials
CA
Calculations
ML
Materials/Parts List/Design Mixes
PH
Photographs
TR
Test Reports
CD
Catalog Data
OM
Operations & Maintenance Data
RD
Project Record Documents
WA
Warranties
CT
Certifications
OT
Other
S
Sample
(2)
(*) indicates quantity
R
Report
O
Original
SC
Samples/Colors

REVIEWER DESIGNATION (For N3B Use Only)

CA
Contract Administrator
IH
Industrial Hygiene
RAD
RADCON
CFO
Chief Financial Office
IT
Information Technology
RM/L
Risk Manager/Legal
CON
Construction
LR
Labor Relations
RM
Regulatory Manager
DC
Derivative Classifier
LTS
Long Term Stewardship
SA
Safety
EC
Environmental Compliance
NFS
Nuclear/Facility Safety
SBM
Small Business Office Manager
ES&H
Environmental Safety & Health
NMC
Nuclear Materials & Accountability
SEC
Security
ERM
Emergency Management
OCI
Office of Counterintelligence
SST
Secondary SCC
FETL
Field Execution Technical Lead
OIG
Office of Inspector General
TA
Transportation
FM
Facility Manager
PCE
Project Controls
TL
Technical Lead
FP
Fire Protection
PHS
Physical Security
TRN
Training
HR
Human Resources
PM
Project Manager
VC
Visitor Control
HRE
HR Employee Concern
PS
Personnel Security
WGS
Waste Generator Services
HRS
HR Secondary
QA
Quality Assurance
(*)
Denotes Lead Reviewer

Submittal No./ Submittal Description

Reference

Submittal Schedule
Submittal Type
N3B Response Needed?
N3B Reviewer

(For N3B Use Only)

Commercial Document Requirements (CDR)

3.0 Exhibit D Scope of Work and Technical Requirements

3.8 Field Data

3.8.1
Field Screening of VOC’s, percent O2, percent CO
Exhibit D: 3.3.1
Z
RD
Y
FETL/TL(*)/PM
3.8.2
Sample Collection Logs
Exhibit D: 3.3.4
Within 24 hours of sample collection
RD
Y
FETL/TL(*)/PM
3.8.3
Field Chain of Custody records
Exhibit D: 3.3.4
Within 24 hours of final chain of custody signature
P,RD
Y
FETL/TL(*)/PM
3.8.4
Field log and note books (PIC logbooks, Health & Safety logbooks, field photographic logbooks, Field Data logs, Field Waste Technician logbook)
Exhibit D: 3.5.8
15 days after each sampling campaign
RD
Y
FETL/TL(*)/PM
3.8.5
Digital photography and associated electronic files
Z
R,EM
Y
FETL/TL(*)/PM
3.8.6
Field Data tables/Samples Taken Tables
15 days after each sampling campaign
RD
Y
FETL/TL(*)/PM
3.8.7
Field Container Summary and Transmittal Forms
Within 5 days of obtaining final signature from SMO.
RD
Y
FETL/TL(*)/PM

3.9 Mapping

3.14 Readiness

3.14.1
Schedules
Exhibit D: 3.5.2
MON,Z, N
OT
Y
FETL/PM(*)
3.14.2
Readiness Assessments, including training audit verification sheets
Exhibit D: 3.5.2
N
EM
Y
FETL/PM(*)
3.14.3
Site Specific Sampling and Analysis Plan (SAP)
Exhibit D: 3.5.2
N
EM
Y
FETL/PM(*)
3.14.4
Project Execution Plan (PEP)
Exhibit D: 3.5.2
N, 15 working days after notice of award
R
Y
FETL/PM(*)

3.15 Reports

3.15.1
Base Scope: MDA-C Field Summary Report (FSR)
2.1.4
Within 30 days after sampling completion
RD
Y
FETL/PM(*)
3.15.2
Base Scope: MDA-L Field Summary Report (FSR)
2.1.5
Within 30 days after sampling completion
RD
Y
FETL/PM(*)
3.15.3
Base Scope: MDA-C Periodic Monitoring Report (PMR)
2.1.6
Within 45 days of completion of the spring round of sampling
RD
Y
FETL/PM(*)
3.15.4
Base Scope: MDA-L Periodic Monitoring Report (PMR)
2.1.7
Within 45 days of completion of spring round of sampling
RD
Y
FETL/PM(*)
3.15.5
Optional Scope: Field Summary Report
2.2.6
Within 30 days of sampling completion at the specific MDA
RD
Y
FETL/PM(*)
3.15.6
Optional Scope: Periodic Monitoring Report (PMR)
2.1.6\2.1.7
To being included with Base scope PMR’s, 45 days fo completion of the spring round of sampling
RD
Y
FETL/PM(*)
3.15.7
Daily Progress report
Exhibit D: 3.5.4
DAY
RD
N
FETL
3.15.8
Weekly Progress report
Exhibit D: 3.5.4
WKLY
RD
N
FETL
3.15.9
Monthly Progress Report
Exhibit D: 3.5.4
MON
RD
N
FETL
3.15.10
Monthly Accrual
Exhibit D: 3.5.7
MON
RD
Y
FETL/CA(*)
3.15.11
Schedules
Exhibit D: 3.5.2
WKLY, MON,Z
OT
Y
FETL/PM(*)

4.0 Exhibit F Environmental Safety & Health

4.1
ES&H Plan (Corporate)
F2, 3.5.2
M
RD
Y
FETL/ES&H(*)
4.2
SSESHP
F2, 3.5.2
M
RD
Y
FETL/ES&H(*)
4.3
Subcontractor & Lower-Tier Subs Minimum Performance Eligibility Factors
F3.1 and F3.2 Attachment F3-2
M, 15 days prior to new lower- tier start
RD
Y
FETL/ES&H(*)
4.4
Qualifications ES&H Specialists
F4.0 Option C
M
RD
Y
FETL/ES&H(*)
4.5
Incident Reporting Written
F5.2
Within 24 hours of the incident
RD
Y
FETL/ES&H(*)
4.6
Complete Accident/Incident
F5.4
Within 2 working days of the incident
RD
Y
FETL/ES&H(*)
4.7
Weekly Productive Man-hour report
F6.4 Attachment F6-1
WKLY- Mondays
RD
N
FETL/ES&H(*)
4.8
Emergency procedures
F11.3
M ES&H plan
RD
Y
FETL/ES&H(*)
4.09
Motor Vehicle Safety Program
F16.1
M ES&H plan
RD
Y
FETL/ES&H(*)
4.10
Major Equipment Declaration and documentation of removal of uncontaminated equipment
F16.10 Attachment F16-1
Prior to placing in service
RD
Y
FETL/ES&H(*)
4.11
Hazard Communication Plan
F19.1
M ES&H plan
RD
Y
FETL/ES&H(*)
4.12
Material Safety Data Sheets (SDS)
F19.2
M, Z
RD
Y
FETL/ES&H(*)
4.13
Data for EPA Annual Toxic Release Inventory Report/CAA section 112
F19.4 Attachment 19-1
Z
RD
Y
FETL/ES&H(*)
4.14
Integrated Work Documents (IWDs)
F20.3, D2.4.4
M
RD
Y
FETL/ES&H(*)
4.15
Fire Protection and Prevention Plan
F21.3
M ES&H plan
RD
Y
FETL/ES&H(*)
4.16
Gas Cylinder Use and Storage Procedure
F35.1
M ES&H plan
RD
Y
FETL/ES&H(*)
4.17
Radiological Requirements
F49.0
M ES&H plan
RD
Y
FETL/PM(*)
4.18
Industrial Hygiene Program
F52.1
M ES&H Plan
RD
Y
FETL/ES&H(*)

5.0 Exhibit G Security

5.1
Vehicle Information
G4.4
M, Z
RD
N
FETL/SEC(*)
5.2
Badging
G6.2
M, Z
RD
N
FETL/SEC(*)
5.3
PED’s/Computing Devices in Limited Area
G8.2
Z
RD
Y
FETL/SEC(*)

6.0 Exhibit H Quality Assurance Requirements

6.1
Qualification and Certification of Personnel and Staff
QC-03
M
RD
Y
FETL/QA(*)
6.2
Corporate Quality Assurance Program

M

6.3
Traceability - Item
QC-04
Z
RD
Y
FETL/QA(*)
6.4
Certificate of Conformance
QC-06
Z
RD
Y
FETL/QA(*)
6.5
Post –Use Certification of Calibration for Subcontractor M&TE
QC-12B
Z
RD
Y
FETL/QA(*)
6.6
Shelf Life Certifications/Storage Requirements
QC-16
Z
RD
N
FETL/QA(*)
6.7
Contractor’s Right of Access to Subcontractor’s Facility
QC-22
Z
RD
N
FETL/QA(*)
6.8
Nonconformance Reporting
QC-25
Z, Within 3 days of occurrence
RD
Y
FETL/QA(*) / TL/PM
6.9
Corrective Action Reports
QC-26
Z, Acknowledge within 5 days of request, response within 30 days of request
RD
Y
FETL/QA(*)/ TL
6.10
Suspect/Counterfeit Items
QC-27
Z
RD
Y
FETL/QA / TL(*)/PM
6.11
Handling, Receiving, Storage, Shipping, and Packaging
QC-29
Z
RD
N
FETL/QA(*) / TL/PM
6.12
Documents and Records
QC-34
Z
RD
Y
FETL/QA(*) / TL
6.13
Documents and Records: Environmental Work
QC-34A
Z
RD
Y
FETL/QA(*)
6.14
Certificates of Analysis
QC-35A
Z
RD
Y
FETL/QA(*)
6.15
Other
QC-37
Z
RD
Y
FETL/QA(*)