This document is an attachment to a Request for Proposal (RFP) for a C-130 Maintenance & Repair Services contract opportunity, providing details on the airfield requirements for KC-130J aircraft.

The attachment outlines the external and internal dimensions, weights, and performance characteristics of the KC-130J aircraft, referencing the NAS 3306 airfield category 4 requirements. It specifies that the runway must have a Load Classification Number (LCN) of 37 for asphalt and 42 for concrete. The document also addresses requirements for the compass rose and Aircraft Rescue and Firefighting (ARFF) capabilities. Contractors unable to meet the specified facility requirements may seek relief through the appropriate waiver authority.

View the file

Other files

File Type Posted
Attachment 40 Request for Data.docx DOCX document
N6264924R0029 PreSol Questions and Responses.pdf PDF
RFP KC-130J_IDIQ_Attachment_01_PWS_(2024-07-26).docx DOCX document
Draft RFP KC130J N6264924R0029.pdf PDF
RFP KC-130J_IDIQ_Attachment_02_Contract_Admin_Plan_(2023-06-23).docx DOCX document
RFP KC-130J_IDIQ_Attachment_06_Drafting and Processing TEI (2023-06-23).docx DOCX document
RFP CDRL_C002_PRESENTATION_DOCUMENTATION_C-130 DistroE.pdf PDF
RFP CDRL_A013_NON-DESTRUCTIVE_INSPECTION_(NDI)_REPORT_C-130.pdf PDF
RFP CDRL_D001_PHASE-IN_TRANSITION_PLAN_C-130 DistroE.pdf PDF
RFP KC-130J_IDIQ_Attachment_03_QASP_(2023-06-23).docx DOCX document
RFP CDRL_D004_TRAINING_PLAN_C-130 DistroE.pdf PDF
RFP KC-130J_IDIQ_Attachment_04_OSHE_Provisions_(2023-06-23).docx DOCX document
RFP CDRL_G001_MATERIAL_EXPENSE_REPORT_C-130 DistroE.pdf PDF
RFP CDRL_A009_AIRCRAFT_CONDITION_EVALUATION_REPORT_C-130.pdf PDF
RFP KC-130J_IDIQ_Attachment_09_Facility_Requirements_(2023-06-23).docx DOCX document
RFP KC-130J_IDIQ_Attachment_12_GFP_(2023-06-23).xlsx XLSX spreadsheet
RFP CDRL_A003_TDC_KIT_RECEIPT_AND_REPORT_OF_KIT_DISCREPANCY_C-130.pdf PDF
RFP CDRL_A008_SITUATION_SUMMARY_REPORT_C-130.pdf PDF
RFP CDRL_A001_TECHNICAL_DIRECTIVES_REQUIREMENTS_10_DAY_REPORT_C-130.pdf PDF
RFP CDRL_A012_Maintenance_History_Summary_(MHS)_Report_C-130.pdf PDF
RFP CDRL_A014_CORROSION_INSPECTION_(CI)_REPORT_C-130 (2023-07) P000XX.pdf PDF
RFP CDRL_A006_NOTIFICATION_OF_AIRCRAFT_DELAY.pdf PDF
RFP CDRL_B001_AVDLR_TRACKER_C-130.pdf PDF
RFP CDRL_D002_TRANSITION_STATUS_REPORT_C-130 DistroE.pdf PDF
RFP CDRL_A005_PRODUCTION_PLAN_C-130.pdf PDF
Draft N6264924R0029 KC130J.pdf PDF
RFP KC-130J_IDIQ_Attachment_05_Drafting and Processing LMR (2023-06-23).docx DOCX document
RFP KC-130J_IDIQ_Attachment_10_Repairable_Items_(2023-06-23).docx DOCX document
RFP KC-130J_IDIQ_Attachment_07_PEMA_Specifications_(2023-06-23).docx DOCX document
RFP CDRL_F001_INTEGRATED_MASTER_SCHEDULE_C-130 DistroE.pdf PDF
RFP KC-130J_IDIQ_Attachment_01_PWS_(2023-06-23).docx DOCX document
RFP CDRL_A011_WEIGHT_AND_BALANCE_REPORTS_C-130 (2023-07) P000XX.pdf PDF
RFP CDRL_B003_FINAL_MATERIAL_CONSUMPTION_REPORT_C-130.pdf PDF
RFP CDRL_B002_AIRCRAFT_AWAITING_PARTS_REPORT_(AWP)_C-130 DistroE.pdf PDF
RFP CDRL_B004_MATERIAL_RECEIPT_TRACKER_REPORT_C-130.pdf PDF
RFP CDRL_A007_SCHEDULED_REMOVAL_CARDS_C-130.pdf PDF
RFP CDRL_A010_NOTED_BUT_NOT_CORRECTED_(NBNC)_REPORT_C-130.pdf PDF
RFP CDRL_A002_TECHNICAL_DIRECTIVES_REPORT_C-130.pdf PDF
RFP CDRL_L001_TECHNICAL_DATA_INVENTORY_LIST_C-130.pdf PDF
RFP KC-130J_IDIQ_Attachment_11_Support_Equipment_(2023-06-23).docx DOCX document
RFP CDRL_D003_TRANSITION_INVENTORY_PLAN_(SHUT-DOWN)_C-130 DistroE.pdf PDF
RFP CDRL_A004_DISCREPANT_PART_ON_INDUCTION_REPORT_C-130.pdf PDF
RFP CDRL_C001_MEETING_MINUTES_C-130 DistroE.pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N62649XXXXXXX

Attachment (8) 23 June 2023

Attachment (8): Airfield Requirement For

KC-130J

Integrated Maintenance Plan (IMP) Planned Maintenance Interval (PMI)

C-130 Reference for Airfield requirements.

NAS 3306 - Airfield Category 4: Wingspans of 118ft (36m) up to but not including 171 ft (52m) and 1.3 VS of less than 141 knots.

External Dimensions

Wing Span132.6 ft/ 40.41 m
Wing Aspect Ratio10.1
Length (Overall)97.75 ft/ 29.79 m
Height (Overall)38.8 ft/ 11.84 m
Tailplane Span52.7 ft/ 16.05 m
Wheel Track14.25 ft / 4.34 m
Propeller Diameter13.5ft/4.11 m
Wing Area (gross)1,745 sq. ft/ 162.12 sq. m

Internal Dimensions

Cabin Length (excluding ramp)40 ft I 12.19 m
Cabin Length (including ramp)50.7ft/15.44m
Max. Width10.25 ft/ 3.12 m
Max. Height9 ft/2.74 m
Total useable volume4,551 cubic ft/ 128.9 cubic m

Weights

Operating Empty Weight75,562 lbs/ 34,274 kg
Takeoff Run to 15 m4,700 ft/ 1,433 m
Takeoff Run using max. effort procedures1,800ft/549m
Landing from 15 mat 58,967 kg AI.JW2,550 ft / 777 m
Landing Run at 58,967 kg AI.JW1 ,400 ft / 427 m
Runway LCN: asphalt37
Runway LCN: concrete42

Range with 18,144 kg payload and MIL-STD-3013 reserves 2,835 nm / 5,250 km

In tandem with C-130 characteristics above; must comply with DCMA 8210.1C Change 1 (or latest revision). When unable to meet the specific facility requirements of NAS 3306, contractors may seek relief through the appropriate Waiver Authority for this Instruction per DCMA 8210.1C Change 1 (or latest revision) per paragraphs 6.15.1, 6.16.1, and 6.18.2.

Compass Rose Must be compliant to USN/USMC requirements.

ARFF

Must comply with DCMA 8210.1C Change 1 and National Aerospace Standard (NAS) 3306. (latest revisions shall be used). When unable to meet the specific facility requirements of NAS 3306, contractors may seek relief through the appropriate Waiver Authority for this Instruction per DCMA 8210.1C Change 1 (or latest revision) per paragraphs 6.15.1, 6.16.1, and 6.18.2.